M/S. M.S.Infraenginners PVT.LTD. vs. State Of Odisha

WP(C)/15220/2019HC OrissaGSTCNR ODHC01046199201925 September 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the grievances of contractors regarding works contracts under GST. These guidelines provided a detailed procedure for determining the GST-inclusive work value for balance work executed after June 30, 2017, when tenders were invited before July 1, 2017. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per revised Schedule of Rates (SoR-2014), applying tender premium/discount, and then adding the applicable GST rate. If the revised GST-inclusive work value for the balance work is more than the original agreement value, the contractor is to be reimbursed. Conversely, if it's less, the payment is reduced, and excess payments are recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, which the authority must consider and dispose of in light of the revised guidelines dated December 10, 2018, preferably by November 30, 2019. No coercive action was to be taken against the petitioner until November 30, 2019. The issue of reimbursement was thus to be decided by the authority based on the new guidelines.

Facts

The petitioner, a contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that GST was applicable to works contracts entered into before the GST regime, which was not originally envisaged. The State government, through the Finance Department, issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address issues faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after GST implementation.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? The petitioner argued that the introduction of GST required them to pay taxes that were not contemplated when the agreements were made, leading to a financial burden. They sought reimbursement of this differential tax amount. The revenue, represented by the State government, submitted revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provided a framework for calculating the GST-inclusive work value for balance work executed after July 1, 2017, and stipulated procedures for reimbursement or recovery of amounts based on this calculation. The court considered these revised guidelines in its decision.

Sections Cited

None explicitly mentioned as being discussed or interpreted, but the context relates to the transition to GST and its impact on works contracts.

AI-generated summary — verify with the full judgment below

03.

25.09.2019

None appears for the parties.

2.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX-

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.