Ashok Kumar Dhal vs. The Principal Secretary, Finance Dept
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issues faced by works contractors due to the GST implementation. These guidelines provided a detailed procedure for calculating the GST-inclusive work value for the balance work executed after June 30, 2017, for contracts tendered before July 1, 2017. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by December 31, 2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until December 31, 2019.
Facts
The petitioner, a works contractor, challenged the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also challenged Clause-6 of a Finance Department Memorandum dated July 22, 2017. The grievance stemmed from being required to pay GST on contracts entered into before the GST regime, where such tax was not initially envisaged. The State Government subsequently issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? 2. Whether Clause-6 of the Finance Department Memorandum dated July 22, 2017, is valid in its application to the petitioner's claim? Petitioner's arguments: The petitioner contended that they are required to pay GST on contracts where the agreement was made before the GST regime, leading to an unforeseen tax liability. They sought reimbursement for this differential tax amount. Revenue/State's arguments: The State, through the Additional Government Advocate, placed on record revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provided a procedure for determining the amount payable to works contractors for balance work executed after the GST implementation, including provisions for reimbursement or recovery based on revised calculations.
AI-generated summary — verify with the full judgment below
14.10.2019
By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also challenged Clause-6 of the Finance Department Memorandum dated 22.07.2017 at Annexure-2. 2. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of O
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.