Santosh Kumar Khandelwal vs. State Of Odisha
Held
The Court acknowledged the difficulty faced by contractors due to the transition from VAT to GST, particularly for works contracts tendered before July 1, 2017, but executed thereafter. The Court noted the issuance of revised guidelines by the Government of Odisha, Finance Department, on December 10, 2018, which superseded earlier guidelines. These revised guidelines established a procedure for determining the GST-inclusive work value for the balance work by considering the original agreement, the revised Schedule of Rates (SoR-2014), and any tender premium/discount. Crucially, the guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance work, the works contractor would be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, which the authority must consider and dispose of in light of these revised guidelines by December 31, 2019. No coercive action was to be taken against the petitioner until that date. The issue of whether the petitioner was *entitled* to reimbursement was implicitly addressed by directing the authority to consider the claim under the revised guidelines, which allow for reimbursement in certain circumstances.
Facts
The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not initially envisaged. The State government subsequently issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address issues related to works contracts under GST for tenders invited prior to July 1, 2017, but executed partly or wholly thereafter. The revised guidelines provide a procedure for determining the GST-inclusive work value for the balance work and reimbursement of excess amounts.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed thereafter? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an increased tax burden not contemplated at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. Revenue/State's contention: The State presented revised guidelines issued by the Finance Department on December 10, 2018, which provide a mechanism for calculating the GST-inclusive work value for balance work and reimbursing contractors if the revised value exceeds the original agreement value. The State relied on these revised guidelines as the basis for addressing the petitioner's grievance.
Sections Cited
Not specified in the judgment
AI-generated summary — verify with the full judgment below
23.10.2019
By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 2. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX- 0045-2017/38535/F Dated 10.12.2018, which
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.