Mohan Kumar Senapati vs. The Executive Engineer,Rural Works Division

WP(C)/19438/2019HC OrissaGSTCNR ODHC01056984201929 October 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issue of differential tax amounts for works contracts executed under the new GST regime. These guidelines provide a clear procedure for calculating the GST-inclusive work value for balance work executed after June 30, 2017, where tenders were invited before July 1, 2017. Specifically, the guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for that balance work, the works contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by December 30, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are at liberty to challenge it. No coercive action is to be taken against the petitioner until December 30, 2019.

Facts

The petitioner filed a writ petition challenging the action of the opposite parties in not reimbursing the differential tax amount arising from the change in tax regime from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that the introduction of GST required them to pay taxes not envisaged when the agreement was entered into. The State Government had issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address difficulties faced by contractors regarding works contracts under GST. These revised guidelines provided a procedure for determining the amount payable to works contractors for balance work executed after GST implementation, including provisions for reimbursement or recovery of excess payments.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, when tenders were invited prior to that date? The petitioner argued that they are required to pay GST on works contracts entered into before the GST regime, which was not contemplated at the time of agreement, leading to an increased financial burden. They sought reimbursement of this differential tax amount. The revenue or State, through the Additional Government Advocate, submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines provided a mechanism for calculating the GST-inclusive work value for balance work executed after July 1, 2017, and stipulated that contractors would be reimbursed if the revised GST-inclusive work value exceeded the original agreement value for the balance work. The State relied on these revised guidelines to address the petitioner's grievance.

AI-generated summary — verify with the full judgment below

W.P.(C) No.19438 of 2019

2.

29.10.2019

None appears for the petitioner at the time of call.

2.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Departmen

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.