Nirmal Chandra Rout vs. State Of Odisha
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the difficulties faced by works contractors due to the transition to GST. These guidelines outlined a specific procedure for determining the GST-inclusive work value for the balance portion of works contracts where tenders were invited before July 1, 2017, but execution continued after that date. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the revised Schedule of Rates (SoR-2014), applying any tender premium/discount, and then adding the applicable GST rate. Crucially, the guidelines state that if the revised GST-inclusive work value for the balance work is more than the original agreement work value for that balance work, the contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation to the appropriate authority, which would then consider and dispose of the representation in light of these revised guidelines by December 31, 2019. No coercive action was to be taken against the petitioner until that date.
Facts
The petitioner, a works contractor, filed a writ petition challenging the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner's grievance was that the introduction of GST meant they had to pay taxes not originally envisaged when entering into agreements for works contracts. The State Government, in response to representations from contractors facing similar difficulties, issued revised guidelines on December 10, 2018, superseding earlier guidelines. These revised guidelines provided a procedure for determining the GST-inclusive work value for balance work executed after GST implementation, where tenders were invited before July 1, 2017.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed partly or wholly after that date? The petitioner argued that the introduction of GST was not contemplated at the time of entering into agreements, leading to an increased tax burden that was not factored into the original contract prices. They sought reimbursement for this differential tax amount. The revenue or State contended that the issue was addressed by the revised guidelines issued by the Finance Department on December 10, 2018. These guidelines provided a mechanism for calculating the GST-inclusive work value for the balance work and stipulated that contractors would be reimbursed if the revised value exceeded the original agreement value for the balance work.
Sections Cited
Section 73, Section 129, Rule 86A
AI-generated summary — verify with the full judgment below
30.10.2019
By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 2. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX- 0045-2017/38535/F Dated 10.12.2018, which
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.