M/S Arya Construction vs. The Principal Secretary Finance Dept.

WP(C)/21865/2019HC OrissaGSTCNR ODHC01063699201920 November 2019Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted the submission by the learned Additional Government Advocate regarding the revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018. These guidelines provided a framework for addressing the claims of contractors for additional amounts towards GST on works put to tender before July 1, 2017, but executed thereafter. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was instructed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by January 31, 2020. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until January 31, 2020. The writ petition was disposed of with these directions.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State/Revenue) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not envisaged in the original agreements. The State submitted revised guidelines issued by the Finance Department of Odisha on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address such issues concerning works contracts under GST.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? Petitioner's contention: The petitioner argued that the introduction of GST necessitated payment of tax that was not contemplated at the time of entering into the agreements, leading to a financial burden. They sought reimbursement for this differential tax amount. Revenue's contention: The Revenue submitted revised guidelines issued by the Government of Odisha, Finance Department, vide Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated December 10, 2018. These guidelines provided a procedure for determining the amount payable to works contractors in cases where tenders were invited before July 1, 2017, but payments were made for the balance work after the implementation of GST.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

02.

20.11.2019

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P.- authority in similar cases annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memora

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.