M/S Akshaya Kumar Mohanty Construction PVT.LTD. vs. The Executive Engineer, Rural Works Division-Ii

WP(C)/1177/2020HC OrissaGSTCNR ODHC01002565202004 February 2020Bench: MR. JUSTICE BISWAJIT MOHANTY,MR. JUSTICE C.R.DASH5 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, to address the issue of works contracts under GST, particularly for tenders invited before July 1, 2017, but executed thereafter. These guidelines outline a procedure for determining the GST-inclusive work value for the balance work, involving ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the revised Schedule of Rates (SoR-2014), adjusting for tender premium/discount, and finally adding the applicable GST rate. If this revised GST-inclusive work value for the balance work exceeds the original agreement work value for the balance work, the contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority must consider and dispose of in light of the revised guidelines dated December 10, 2018, preferably by March 30, 2020. No coercive action was to be taken against the petitioner until March 30, 2020. The issue of whether the petitioner was *entitled* to reimbursement was not definitively decided but was to be processed under the new guidelines.

Facts

The petitioner, a works contractor, filed a writ petition challenging the opposite parties' (State authorities) inaction in reimbursing the differential tax amount. This arose due to the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The State government had issued revised guidelines on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address such issues concerning works contracts under GST.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed partly or wholly after that date? The petitioner argued that the introduction of GST imposed a tax liability not contemplated at the time of entering into agreements, thus necessitating reimbursement of the differential tax amount. The State, through its learned Additional Government Advocate, presented revised guidelines issued by the Finance Department on December 10, 2018, which provided a procedure for determining and reimbursing GST on the balance work executed after July 1, 2017. The State's contention was that these guidelines offered a mechanism to address the petitioner's grievance.

Sections Cited

Not specified

AI-generated summary — verify with the full judgment below

02.

04.02.2020

Heard Ms. K.B. Roy Choudhury, learned counsel for the petitioner and learned Additional Government Advocate for the State-opposite parties.

2.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. 3. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

4.

The Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. Learned Addl. Government Advocate has filed Additional Counter Affidavit of O.P.-authority in similar cases annexing the revised guidelines relating to works contrac

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.