Ajit Kumar Sahoo vs. The Executive Engineer Rural Works Division.Ii Kendrapara

WP(C)/9403/2020HC OrissaGSTCNR ODHC01020171202020 March 2020Bench: DR. JUSTICE S.K. PANIGRAHI,MR. JUSTICE C.R.DASH6 pages
AI SummaryRemanded

Held

The Court noted that the Revenue had issued revised guidelines on December 10, 2018, to address the difficulties faced by contractors due to the GST implementation. These guidelines provided a detailed procedure for ascertaining the balance work done after June 30, 2017, determining its revised estimated work value as per the Revised SoR-2014, applying tender premium/discount, and then adding the applicable GST rate to arrive at the GST-inclusive work value. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for the balance work, the contractor was to be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by April 30, 2020. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until April 30, 2020. The issue of whether the petitioner was entitled to reimbursement was not directly decided but was to be determined by the authority under the revised guidelines.

Facts

The petitioner, a works contractor, challenged the action of the opposite parties for not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that they were required to pay GST on contracts entered into before the GST regime, which was not originally envisaged. The Revenue submitted revised guidelines issued by the Government of Odisha, Finance Department, vide Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated December 10, 2018, which superseded earlier guidelines dated December 7, 2017. These revised guidelines provided a procedure for determining the amount payable to works contractors for balance work executed after GST implementation.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? (Mixed question of law and fact, concerning the interpretation and application of tax laws and contractual terms). Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated at the time of entering into the agreement, thus entitling them to reimbursement of this differential tax amount. Revenue's contention: The Revenue submitted revised guidelines dated December 10, 2018, which provided a framework for calculating the GST-inclusive work value for balance work and determining reimbursement or recovery based on the comparison with the original agreement value. The Revenue relied on the said revised guidelines.

Sections Cited

Section 129 (This section is not explicitly mentioned in the provided text, but it is a common section related to goods in transit and detention, which might be tangentially related to tax disputes. However, based solely on the provided text, no specific CGST/SGST Act sections or Rules were explicitly discussed or relied upon by the Court for its decision. The decision was based on administrative guidelines.)

AI-generated summary — verify with the full judgment below

2.

20.03.2020

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised gui

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.