Ajit Kumar Sahoo vs. The Executi Ve Engineer Aul Embarkment Division Aul

WP(C)/9401/2020HC OrissaGSTCNR ODHC01020163202020 March 2020Bench: DR. JUSTICE S.K. PANIGRAHI,MR. JUSTICE C.R.DASH6 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on 10.12.2018 to address the difficulties faced by works contractors due to the change in tax regime. These guidelines provided a mechanism for calculating the GST-inclusive work value for the balance work executed after 01.07.2017, where tenders were invited prior to that date. The procedure involved ascertaining the work value as per the original agreement, determining the revised estimated work value as per the Revised SoR-2014, adjusting for tender premium/discount, and then adding the applicable GST. Crucially, the guidelines stipulated that if the revised GST-inclusive work value for the balance work was more than the original agreement work value for the balance work, the works contractor was to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority, which would then consider and dispose of the representation in light of these revised guidelines. The Court also granted liberty to the petitioner to challenge the authority's decision if aggrieved and ordered that no coercive action would be taken against the petitioner until 30.04.2020.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from 01.07.2017. The petitioner's grievance was that they were required to pay GST on works contracts, which was not envisaged when agreements were entered into before the GST regime. The State submitted revised guidelines issued by the Finance Department, Government of Odisha, on 10.12.2018, superseding earlier guidelines dated 07.12.2017, to address such issues concerning works contracts executed partly or wholly after 01.07.2017, where tenders were invited prior to that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before 01.07.2017 but executed partly or wholly thereafter? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden that was not anticipated at the time of entering into the agreements, leading to a financial disadvantage. They sought reimbursement of this differential tax amount. Revenue's contention: The State submitted revised guidelines issued by the Finance Department on 10.12.2018, which provided a procedure for determining the GST-inclusive work value for the balance work executed after 01.07.2017, and stipulated reimbursement if the revised value exceeded the original agreement value. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

2.

20.03.2020

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guid

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.