Ajit Kumar Sahoo vs. The Executive Engineer Rural Works Division Kendrapara

WP(C)/9400/2020HC OrissaGSTCNR ODHC01020157202020 March 2020Bench: DR. JUSTICE S.K. PANIGRAHI,MR. JUSTICE C.R.DASH6 pages
AI SummaryRemanded

Held

The Court acknowledged the issue faced by contractors due to the change in tax regime. It noted that the State had issued revised guidelines on December 10, 2018, to address these concerns. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, detailing their grievances. The authority was instructed to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by April 30, 2020. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they would be at liberty to challenge it. No coercive action was to be taken against the petitioner until April 30, 2020. The Court did not decide the ultimate entitlement to reimbursement but provided a procedural path for resolution.

Facts

The petitioner, a works contractor, challenged the action of the opposite parties (State revenue authorities) for not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective from July 1, 2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not originally envisaged. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017. These revised guidelines provided a procedure for determining the payable amount to works contractors for balance work executed after July 1, 2017, on contracts tendered before that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed partly or wholly thereafter? (Mixed question of law and fact, concerning the interpretation and application of tax laws and contractual terms). Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated at the time of entering into the agreements, thus entitling them to reimbursement of this differential tax amount. Revenue's contention: The State submitted revised guidelines issued by the Finance Department on December 10, 2018, which provided a mechanism for calculating the GST-inclusive work value for balance work and stipulated reimbursement if the revised value exceeded the original agreement value, or recovery if it was less. The State relied on these revised guidelines as the basis for resolving such claims.

AI-generated summary — verify with the full judgment below

2.

20.03.2020

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged the action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He has filed an Additional Counter Affidavit of O.P. No.2 in similar cases annexing the revised guid

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.