Manoj Kumar Maharana vs. The State Of Odisha

WP(C)/18885/2020HC OrissaGSTCNR ODHC01042971202003 November 20205 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on December 10, 2018, in supersession of the earlier memorandum dated December 7, 2017. These revised guidelines provide a procedure for determining the GST-inclusive work value for the balance work executed after June 30, 2017, for contracts where tenders were invited before July 1, 2017. The guidelines stipulate that if the revised GST-inclusive work value for the balance work exceeds the original agreement work value for that balance work, the works contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by the end of December 2020. The Court also stated that if the petitioner is aggrieved by the authority's decision, they are free to challenge it. No coercive action was to be taken against the petitioner until the end of December 2020.

Facts

The petitioner, a contractor, filed a writ petition challenging the action of the opposite parties in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance stemmed from the requirement to pay GST on works contracts, which was not anticipated when agreements were entered into under the previous tax regime. The State's counsel submitted that a similar matter was decided by the Court on December 12, 2018, where revised guidelines for works contracts under GST were presented.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? Petitioner's contention: The petitioner argued that the introduction of GST necessitated paying taxes that were not envisaged at the time of entering into the agreements, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue/State's contention: The State submitted that revised guidelines were issued by the Finance Department on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines address the issue of works contracts under GST, particularly for tenders invited before July 1, 2017, but executed thereafter. The State relied on the revised guidelines and a previous High Court decision in a similar matter (W.P.(C) No.12244 of 2018).

Sections Cited

Section 1(iii) of Finance Department Memorandum dated 07.12.2017, Finance Department Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F Dated 10.12.2018

AI-generated summary — verify with the full judgment below

03.

03.11.2020

This matter is taken up through Video Conferencing because of COVID-19 pandemic.

Heard Mr. B. Panda, learned counsel for the petitioner and Mr. M.S. Sahoo, learned Additional Government Advocate for the State.

By way of this writ petition, the petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that similar matter i.e. W.P.(C) No.12244 of 2018 has been decided by this Court on 12.12.2018

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.