M/S Thakur Buildtech PVT,LTD vs. State Of Odisha

WP(C)/1540/2021HC OrissaGSTCNR ODHC01002972202105 February 2021Bench: DR. JUSTICE S. MURALIDHAR (CJ),MR. JUSTICE S.K.SAHOO6 pages
AI SummaryRemanded

Held

The Court noted the State's submission regarding the revised guidelines issued on December 10, 2018, which superseded earlier guidelines. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance portion of works contracts executed after July 1, 2017, where tenders were invited before that date. The guidelines stipulated that if the revised GST-inclusive work value for the balance work was more than the original agreement work value for that balance work, the works contractor was to be reimbursed for the excess amount. The Court directed the Petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by June 5, 2021. The Petitioner was informed that they could challenge the authority's decision if aggrieved. No coercive action was to be taken against the Petitioner until June 5, 2021. The Writ Petition was disposed of accordingly.

Facts

The Petitioner, a works contractor, filed a Writ Petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The Petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not originally envisaged in the agreements. The State submitted that revised guidelines were issued by the Finance Department on December 10, 2018, superseding earlier guidelines from December 7, 2017, to address such issues concerning works contracts under GST.

Key Issues

1. Whether the Petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after July 1, 2017, where tenders were invited prior to that date. Petitioner's Contention: The Petitioner argued that the introduction of GST resulted in an additional tax burden that was not contemplated when the agreements were finalized, leading to a claim for reimbursement of this differential tax amount. Revenue's Contention: The State submitted that revised guidelines were issued on December 10, 2018, by the Finance Department, Government of Odisha, to address the concerns of contractors regarding works contracts under GST. These guidelines provided a procedure for determining the GST-inclusive work value for the balance work executed after July 1, 2017, and stipulated reimbursement if the revised value exceeded the original agreement value.

Sections Cited

Not Specified

AI-generated summary — verify with the full judgment below

02.

05.02.2021

1.

This matter is taken up by video conferencing mode.

2.

Heard Mr. Bikram Kishore Nayak, learned counsel for the Petitioner as well as learned Additional Government Advocate for the State-Opposite Parties and perused the record.

3.

By way of this Writ Petition, in substance, Petitioner has challenged the action of the Opposite Parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 1st July, 2017. 4. Batch of Writ Petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the Petitioner is that in view of the introduction of the GST, Petitioner is required to pay tax which was not envisaged while entering into the agreement.

5.

Learned Additional Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 7th December, 2017. He ha

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.