Amulya Kumar Dash vs. State Of Odisha
Held
The Court noted that the Government of Odisha, Finance Department, had issued revised guidelines on December 10, 2018, superseding the earlier guidelines of December 7, 2017. These revised guidelines provide a detailed procedure for determining the GST-inclusive work value for the balance work executed after July 1, 2017, for contracts tendered before that date based on the pre-revised Schedule of Rates (SoR-2014). The procedure involves ascertaining the balance work quantity and value, determining the revised estimated work value as per the Revised SoR-2014, applying tender premium/discount, and finally adding the applicable GST rate. If the revised GST-inclusive work value exceeds the original agreement work value for the balance work, the contractor is to be reimbursed for the excess amount. The Court directed the Petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by June 5, 2021. No coercive action is to be taken against the Petitioner until June 5, 2021. The writ petition was disposed of in these terms.
Facts
The Petitioner challenged the Opposite Parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The Petitioner, a contractor, argued that the GST regime imposed taxes not anticipated when agreements were entered into. The Government of Odisha, Finance Department, had previously issued guidelines on December 7, 2017, regarding works contracts under GST. However, the learned Additional Government Advocate brought to the Court's attention revised guidelines issued on December 10, 2018, which superseded the earlier ones.
Key Issues
1. Whether the Petitioner is entitled to reimbursement of the differential tax amount due to the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? The Petitioner contended that the introduction of GST resulted in an additional tax burden that was not factored into the original agreements, leading to financial hardship. They sought reimbursement of this differential tax amount. The Revenue, through the learned Additional Government Advocate, submitted that revised guidelines were issued by the Government of Odisha, Finance Department, on December 10, 2018, which addressed the issue of works contracts under GST and provided a procedure for determining payable amounts to contractors in such scenarios. These revised guidelines superseded earlier ones.
Sections Cited
Not specified
AI-generated summary — verify with the full judgment below
1
24.02.2021
Heard Mr. G. M. Rath, learned counsel for the Petitioner and Mrs. S. Pattanayak, learned Additional Government Advocate.
This petition challenges the action of the Opposite Parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 1st July, 2017. 3. A batch of writ petitions have been filed on this very issue. The main issue involved in such matters concerns the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the Petitioner is that in view of the introduction of the GST, the Petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Additional Government Advocate submits that the Government has now come out with a revised set of guidelines in supersession of the guidelines issued vide Finance Department letter dated 7th December, 2017. He has brought to the notice of the Court, the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.