M/S.M.M.Construction vs. Union Of INDIA.

WP(C)/9162/2009HC OrissaGSTCNR ODHC01003955200908 March 2022Bench: DR. JUSTICE S. MURALIDHAR (CJ),MR. JUSTICE R.K.PATTANAIK2 pages
AI SummaryRemanded

Facts

The Petitioner, M/s. M.M. Constructions, entered into an agreement with the Railways on October 18, 2005. The Railways later rescinded this contract by a letter dated March 26, 2009, and floated a fresh tender. The Petitioner filed a writ petition, and on July 22, 2009, the High Court issued an interim order restraining the Railways from proceeding with the fresh tender. The Petitioner alleged that the Railways proceeded with the fresh tender and got the work completed by another contractor despite the interim order. The Railways contended that these steps were taken before the interim order was passed. Subsequently, the Petitioner filed a rejoinder affidavit raising grievances regarding money owed for work done, including the return of a security deposit, and the charging of GST in the final bill, which was introduced in July 2017.

Held

The Court noted that the original cause of action for the petition no longer survived. However, acknowledging the Petitioner's subsequent grievances raised in the rejoinder affidavit concerning money owed for work done, the return of security deposit, and the charging of GST, the Court held that the scope of the present writ petition did not permit adjudication of these new issues. Nevertheless, the Court permitted the Petitioner to make a representation to the Railways by April 25, 2022, detailing all their claims. The Railways were directed to consider this representation, provide a hearing to the Petitioner, and pass a reasoned order by June 27, 2022, communicating it to the Petitioner by July 4, 2022. The Petitioner was granted liberty to seek appropriate remedies if aggrieved by the Railways' decision. The issue of GST charging was not directly decided but was included within the scope of the representation.

Key Issues

1. Whether the Railways proceeded with the fresh tender and got the work completed by another contractor notwithstanding the interim order dated July 22, 2009, passed by this Court? (Mixed question of fact and law) 2. Whether the Petitioner is entitled to claims for work already done, return of security deposit, and the incorrect charging of GST in the final bill? (Question of law) Petitioner's arguments: The Petitioner argued that the Railways proceeded with the fresh tender and completed the work through another contractor despite the Court's interim order. They also raised grievances regarding outstanding payments for work performed and the erroneous imposition of GST on their final bill, which was introduced after the contract period. Revenue/State's arguments: The Railways contended that the actions taken regarding the fresh tender and work completion occurred prior to the issuance of the interim order. No specific arguments were recorded by the Court regarding the Petitioner's subsequent claims for payment and GST.

Sections Cited

None

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
Page 1 of 2 IN THE HIGH COURT OF ORISSA AT CUTTACK W.P. (C) No. 9162 of 2009 M/s. M.M.Constructions …. Petitioner Mr. S. D. Das, Senior Advocate -versus- Union of India and others …. Opp. Parties Mr.A.K.Mishra, Advocate CORAM: THE CHIEF JUSTICE JUSTICE R.K.PATTANAIK Order No.

ORDER 08.3.2022

07.1.

The subject matter of the Petitioner concerns the floating of a tender by the Railways notwithstanding that it had entered into an agreement with the present Petitioner

on 18th October, 2005 for the execution of the contract.

2.

On 22nd July, 2009, this Court had passed an interim

order restraining the Railways from proceeding with the fresh tender pursuant to the letter dated 26th March, 2009

whereby it had rescinded the contract awarded in favour of the Petitioner.

3.

Mr. Saktidhar Das, learned Senior counsel appearing for the Petitioner, submits that notwithstanding the interim order, the Railways proceeded with the fresh tender and got the work completed through another contractor. Mr. Mishra, learned cou

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.