Sibu Kanungo vs. State Of Odisha

WP(C)/1754/2023HC OrissaGSTCNR ODHC01004564202328 July 2023Bench: DR. JUSTICE B.R.SARANGI,MR. JUSTICE MURAHARI SRI RAMAN27 pages
AI SummaryAllowed

Held

The Court held that the impugned order dated 12.01.2023, rescinding the contract, was passed in gross violation of the principles of natural justice. This violation was explicitly admitted in the pleadings made in the counter affidavit filed by the opposite parties. The Court relied on various Supreme Court judgments, including Maneka Gandhi v. Union of India, Swadeshi Cotton Mills v. Union of India, Basudeo Tiwary v. Sido Kanhu University, Nagarjuna Construction Company Limited v. Government of Andhra Pradesh, Uma Nath Panday v. State of U.P., Mohinder Singh Gill v. The Chief Election Commissioner, Bhagwan v. Ramchand, and Sukdev Singh v. Bhagatram, to emphasize that the principles of natural justice are fundamental and must be followed when a person's rights are affected by administrative or statutory decisions. The Court found no hesitation in holding that the rescission order could not be sustained in the eye of law and was liable to be quashed. The Court quashed the impugned order. The Court did not expressly leave any issue undecided.

Facts

The petitioner, Sibu Kanungo, a contractor, filed a writ petition challenging an order dated 12.01.2023 issued by the Executive Engineer, Nayagrah (R&B) Division. This order rescinded the contract agreement no. 223P1/2018-19 for road improvement work and imposed a 20% penalty on the value of the leftover work. The petitioner contended that the work could not commence due to encroachments on the land, despite his requests to the authorities. The authorities later decided to double the width of the road, leading to a revised estimate finalized on 24.11.2021 and approved on 04.03.2022. The petitioner resumed work after approval but was verbally stopped by the Assistant Engineer. He received the rescission order while his grievance was pending.

Key Issues

1. Whether the impugned order dated 12.01.2023, rescinding the contract, is arbitrary, unreasonable, and contrary to law, violating principles of natural justice, specifically the right to show cause and be heard (Article 14 of the Constitution of India)? Petitioner's arguments: The petitioner argued that the rescission order was passed without issuing a show-cause notice or providing an opportunity for a hearing, thus violating principles of natural justice. He contended that the delay in work was attributable to the authorities' failure to provide encroachment-free land and their prolonged delay in finalizing and approving the revised work estimate, which significantly changed the scope of work. The petitioner asserted that the authorities' actions were unfair, illegal, arbitrary, and infringed upon his legitimate expectation and fundamental rights under Articles 14, 19, and 21. Revenue's arguments: The State-opposite parties admitted the factual matrix but contended that the petitioner failed to complete the work as per his commitment. They stated that contract rescission was initiated as per Clause-2(i) of the agreement and approved by the competent authority. They also highlighted that the petitioner had failed to start work despite a Contract Management Meeting on 07.12.2018, a commitment to start by 13.12.2018, and several show-cause notices issued between 18.12.2019 and 07.07.2021.

Sections Cited

Clause-2(i)

AI-generated summary — verify with the full judgment below

ORISSA HIGH COURT: CUTTACK

W.P(C) NO. 1754 OF 2023 In the matter of an application under Articles 226 and 227 of the Constitution of India. ---------------

Sibu Kanungo

..… Petitioner -versus- State of Odisha and others

….. Opp. Parties

For petitioner : Mr. Milan Kanungo,

Sr. Advocate along with M/s. S.R. Mohanty and D. Acharya, Advocates.

For opp. parties : Mr. P.P. Mohanty, Addl. Government Advocate

P R E S E N T:

THE HONOURABLE DR. JUSTICE B.R.SARANGI AND THE HONOURABLE MR JUSTICE MURAHARI SRI RAMAN

Date of Hearing: 25.07.2023:: Date of Judgment: 28.07.2023

DR. B.R. SARANGI, J. The petitioner, who is a contractor, has filed this writ petition challenging the order dated 12.01.2023 under Annexure-7, by which the Executive Engineer, Nayagrah (R&B) Division, Nayagarh, in pursuance of the approval of rescission of contract vide letter no.2198 dated AFR

15.11.

2022 of the Chief Construction Engineer, Khurdha (P&B) Circle, Kh

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.