Cause title — parties, addresses and appearances
Page 1 of 45
ORISSA HIGH COURT: CUTTACK
AFR
W.P.(C) NO. 37472 OF 2023
In the matter of an application under Article 226 of the
Constitution of India.
---------------
M/s. Neelachal Ispat Nigam Ltd.
..… Petitioner
-Versus-
Union of India and others
….. Opp. Parties
For petitioner : Mr. T. Gulati, Sr. Advocate
along
with
M/s.
Jnanesh
Mohanty, S. Gumansingh and
S. Mohanty, Advocates
For opp. parties : Mr. T.K. Satapathy, Sr. Standing
Cousnel along with Mr. Avinash
Kedia, Jr. Standing Counsel for
GST & Central Excise
P R E S E N T:
THE HONOURABLE DR. JUSTICE B.R.SARANGI
AND
THE HONOURABLE MR JUSTICE G. SATAPATHY
Date of Hearing: 09.05.2024:: Date of Judgment : 14.05.2024
DR. B.R. SARANGI, J. M/s. Neelachal Ispat Nigam Limited, a
Joint Venture Company registered under the provisions
of Companies Act, 1956 and promoted by M/s MMTC
Page 2 of 45
Limited
and
Industrial
Promotion
&
Investment
Corporation of Orissa Limited (IPICOL), having its factory
premises located at Kalinga Nagar Industrial Complex,
Duburi in the district of Jajpur, Odisha, having Central
Excise Registration Certificate No. AAACN9433BXM001,
engaged in manufacturing of ‘Pig Iron’ and ‘Billet’ falling
under Chapter-72 and ‘Coke & Crude Tar’, falling under
Chapter-27 of the First Schedule to the Central Excise
Tariff Act, 1985, has filed this writ petition seeking to
quash the demand-cum-show cause notice dated
10.09.2008 under Annexure-2 issued by the opposite
party no.2; the consequential notices dated 05.12.2017
and 05.01.2018 issued under Annexure-3 (Colly.); and
also the Order-in-Original dated 04.09.2023 under
Annexure-9, whereby the demand made in the show
cause notice dated 10.09.2008 has been confirmed.
2.
The factual matrix of the case, in a nutshell, is
that the petitioner, being a Public Limited Company, is
primarily engaged in the manufacturing of ‘Pig Iron’ and
‘Billet’ falling under Chapter-72 and ‘Coke & Crude Tar’
Page 3 of 45
falling under Chapter-27 of the First Schedule to the
Central Excise Tariff Act, 1985 in its factory located in
Kalinga Nagar Industrial Complex, Jajpur. Another
company, namely, M/s. Konark Met Coke Limited
(KMCL), also situated in the same complex, has set up a
Metallurgical Coke Plant along with a Captive Power
Plant. The electricity generated was captively used by
M/s. KMCL as well as by the Petitioner. M/s. KMCL is
the manufacturer of Metallurgical Coke, Pearl Coke,
Breeze Coke falling under Chapter-27 and Ammonium
Sulphate falling under Chapter-31 of the First Schedule
to the Central Excise Tariff Act, 1985, having Central
Excise
Registration
Certificate
No.
1/Ch.27&31/KMCL.JPR/99
dated
01.03.1999.
Subsequently,
M/s
KMCL
amalgamated
with
the
petitioner with all its assets and liabilities with effect
from
08.12.2004,
pursuant
to
the
order
dated
05.11.2004 passed by this Court in COPET No. 26 of
2004. Paragraphs-2 and 3 of the said order dated
Page 4 of 45
05.11.2004 passed in COPET No. 26 of 2004 reads as
under:-
“Para-2: That all the property, rights and powers
of the transferor company specified in the scheme
of amalgamation annexed hereto and all the other
property, rights and powers of the transferor
company be transferred without further act or
deed to the transferee company and accordingly
the same shall pursuant to section 394(2) of the
Companies Act, 1956 be transferred to and vest
in the transferee company for all estate and
interest of the transferor company therein but
subject nevertheless to all charges now affecting
the same;
Para-3: That all the liabilities and duties of the
transferor company be transferred without further
act or deed to the transferee company and
accordingly the same shall pursuant to Section
394(2) of the Companies Act, 1956 be transferred
to and become the liabilities and duties of the
transferee company.”
2.1.
M/s KMCL on the date of merger was having
unutilized
Cenvat
Credit
balance
amounting
to
Rs.39,17,30,118/ - (Rs.1,14,41,688/- on inputs and
Rs.38,02,88,430/- on capital goods) in its Cenvat
account. Consequent upon merger of M/s. KMCL with
the petitioner, on the application of the petitioner dated
22.12.2004, the Jurisdictional Asst. Commissioner,
Balasore Division, vide his letter dated 24.12.2004,
Page 5 of 45
allowed the petitioner to take back the unutilised Cenvat
credit of Rs.39,17,30,118/- available with M/s. KMCL.
2.2.
During verification of records by AG (Audit),
the petitioner could not produce any documents
evidencing physical transfer of Inputs/Capital Goods
from M/s. KMCL to the petitioner. The petitioner, in
their statement dated 12.09.2007 recorded before the
Jurisdictional Range Officer, against summons issued
under Section 14 of the Central Excise Act, 1944, stated
that complying with the direction of the this High Court,
M/s. KMCL was merged with the petitioner with effect
from 08.12.2004. All assets and liabilities were taken
over by the amalgamated company as on that date. The
company took possession of the assets and necessary
entries in the asset register/bin card were made. After
hearing both sides, i.e., Creditors and Shareholders, this
Court had given its verdict for merger of both the
companies as mentioned above. Therefore, with the
necessary permission of the Jurisdictional Assistant
Commissioner, Central Excise, Customs & Service Tax,
Page 6 of 45
Balasore Division, Balasore and as per the order of this
Court, the petitioner has taken the Cenvat Credit
lawfully. But, on the alleged contravention of the
provisions of Rule 10 (1) and (3) of the Cenvat Credit
Rules, 2004, as the petitioner had never disclosed this
fact to the Department by any communication and it is
only during verification of relevant documents of the
petitioner by AG, Audit the matter came to the
knowledge of the Department, it was thus presumed that
the petitioner knowingly/ intentionally suppressed all
the information in respect of their wrong availment of
Cenvat Credit from the Department. It was also observed
that the aforesaid credit of Rs.39,17,30,118/- availed by
the petitioner is recoverable from it, along with interest
due thereon, under Rule 14 of the Cenvat Credit Rules,
2004 read with proviso to Section 11A and 11AB of the
Central Excise Act, 1944 (“the Act” in short).
2.3.
In the light of the above observation and
allegations, a show cause notice dated 10.09.2008
proposing the following was issued:-
Page 7 of 45
“(i)
The
Cenvat
Credit
amounting
to
Rs.39,17,30,118/- (Rs.1,14,41,688/- on inputs
and Rs.38,02,88,430/- on capital goods) wrongly
availed by the Noticee shall not be recovered from
them under the provisions of rule 14 of the CCR
read with Section 11A(1) of the Act;
(ii)
Interest at the appropriate rate till the date
of payment shall not be charged under Section
11AB of the Act; and
(iii) Penalty shall not be imposed on it under Rule
15 of the Cenvat Credit Rules, 2004 read with
Section 11AC of the Act for its said legal
infractions.”
2.4.
The said show cause notice was not received
by the petitioner. However, personal hearing of the case
was fixed to 22.12.2017, i.e., after a lapse of more than 9
years from the date of issue of the impugned notice. As
the impugned show cause notice dated 10.09.2008 was
not received by the petitioner, the Commissioner was
approached by the petitioner to provide a copy of the
same, along with supporting documents, enabling the
petitioner to file its reply. Another date of personal
hearing was fixed to 08.01.2018, vide communication
dated 05.01.2018, which was received by the petitioner
on 10.01.2018. The petitioner was given a copy of the
show cause notice by the office of the Commissioner,
Page 8 of 45
Central Excise, Bhubaneswar-I on 08-01.2018 and was
asked to file the reply by the last week of January, 2018.
2.5.
Needless to mention here, the dispute involved
in the impugned show cause notice relates to the period
2004-05. The related documents, being 14 years old,
were not easily traceable, for which the petitioner was
unable to file its reply by the end of January, 2018. After
thorough search of the records, the petitioner with much
difficulty was able to locate the relevant records and filed
the reply to the notice of show cause dated 10.09.2008,
contending that the notice of show cause has been
issued with reference to the permission accorded by the
Jurisdictional Assistant Commissioner, Central Excise,
Customs & Service Tax, Balasore Division, vide his letter
dated 24.12.2004, under which he allowed the petitioner
to take the Cenvat Credit of Rs.39,17,30,118/- lying un-
utilized in the account of erstwhile M/s KMCL in terms
of Rule 10(1) of the Cenvat Credit Rules, 2004,
consequent upon its amalgamation with the petitioner
Page 9 of 45
and pursuant to order of this Court dated 05.11.2004 in
COPET No.26 of 2004.
2.6.
Therefore, on the basis of a show cause notice
issued on 10.09.2008 and after lapse of about 10 years
from the date of issuance of show cause notice, notice for
personal hearing was issued and the final Order-in-
Original was passed on 04.09.2023, after a period of 15
years and, therefore, the present writ petition.
3.
Mr. Tarun Gulati, learned Senior Advocate
appearing along with Mr. Jnanesh Mohanty and Ms.
Gumansingh,
learned
counsel
for
the
petitioner
contended that even though a show cause notice was
issued on 10.09.2008, the same was not served on the
petitioner and for the first time, on 05.12.2017, the same
was served on the petitioner. In compliance of the show
cause notice, the petitioner gave its reply, but no action
was taken thereon nor the same was decided and, as
such, it was kept pending and after lapse of six years,
the order dated 04.09.2023 was passed, whereas the
matter should have been decided within a reasonable
Page 10 of 45
period. It is contended that initially the show cause
notice was issued on 10.09.2008, which took 9 years to
bring to the notice of the petitioner vide letter dated
05.12.2017. Thereafter, even if reply was filed, the same
was kept pending for six years and ultimately the final
order was passed on 04.09.2023. Thereby, the entire
claim is grossly barred by limitation and belated claim
cannot be considered. It is further contended that the
audit objection was contested and was taken out after
the circular dated 08.04.2016, for which the same is not
the valid explanation for delay. The inordinate delay in
adjudication of a show cause notice is fatal to its validity,
since it causes prejudice. The words “where is it is
possible to do so” cannot be construed to be without any
meaning. Further, it is contended that the department
was bound to inform the petitioner of the case to the call
book and if the department was aggrieved with an order,
it could have challenged the same and there cannot be
two adjudications on the same issue. Moreover, the
extended period of limitation cannot be invoked when
Page 11 of 45
the Department was aware of the facts of the case and
had in fact given approval. To substantiate his
contention, learned Senior Advocate appearing for the
petitioner has relied upon the judgment of this Court in
the case of M/s IDCOL Ferro Chrome & Alloys Ltd.,
Ferro Chrome Project v. Commissioner, Central
Excise, [W.P.(C) No. 11809 of 2017 disposed of on
02.01.2023]; judgment of the Punjab and Haryana High
Court in the case of M/s Shree Baba Exports v.
Commissioner, GST & Central Excise, CWP No. 11860
of 2021 disposed of on 15.03.2022, which has been
confirmed by the apex Court in S.L.P. (C) No. 12376 of
2022 disposed of on 29.07.2022; judgments of the apex
Court in the cases of Commissioner, CGST and Central
Excise v. Shree Baba Exports, SLP (C) No. 12376 of
2022 disposed of on 29.07.2022; and Kamaladitya
Construction (P) Ltd. v. Principal Commissioner of
CGST and Central Excise, 2023 SCC OnLine Jhar
1537. It is contended that the judgments passed by this
Court in the case of M/s IDCOL Ferro Chrome & Alloys
Page 12 of 45
Ltd. and Ferro Chrome Project (supra) have also taken
note of the judgments of this Court in the cases of
Maxcare Laboratories Ltd. v. Joint Commissioner,
CGST, Central Excise & Custom, 2021 (378) ELT 401
(Ori.) and M/s Orissa Mining Corporation Ltd. v. Sales
Tax Officer, (W.P.(C) No. 13195 of 2010 disposed of on
15.12.2021); and also ATA Freight Line (I) Ltd v. Union
of India & Ors., 2022 SCC OnLine Bom 648 (Bombay
High Court), which has been confirmed by the apex
Court in S.L.P. (C) No. 828 of 2023 disposed of on
10.02.2023; M/s. Siemens Ltd. v. Union of India and
Anr, W.P.(C) No. 6757 of 2022 decided on 03.10.2023
(Bombay High Court); Duncans Agro Industries Ltd v.
CCE, (2006) 7 SCC 642; Anand Nishikawa Co. Ltd v.
Comm. Of Central Excise, (2005) 7 SCC 749; Honda
Siel Power Products v. Union of India and another,
2019 SCC OnLine All 5341; Parle International
Limited v. Union of India and Others, Writ Petition
No. 12904 of 2019 disposed of 26.11.2020 (Bombay High
Court); Eveready Industry India Limited v. Customs,
Page 13 of 45
Excise and Service Tax Appellate Tribunal and
others, 2016 SCC OnLine MAD 6066 (Madras High
Court) ; Tata Steel Limited v Union of India and
others, W.P.(T) No. 826 of 2023 disposed of on
13.06.2023 (Jharkhand High Court); BT (India) Pvt. Ltd
v. Union of India and another, 2023 SCC OnLine DEL
7143 (Delhi High Court).
4.
Mr. T.K. Satapathy, learned Sr. Standing
Counsel appearing along with Mr. A. Kedia, learned Jr.
Standing Counsel for GST & Central Excise, raised
preliminary objection with regard to maintainability of
the writ petition. It is contended that the petitioner has
challenged the reassessment order before this Court
under Article 226 of Constitution of India, which is not
maintainable because the order is appealable under
Section 35-B before the learned Custom and Excise and
Service
Tax
Appellate,
Tribunal.
Petitioner
has
approached this Court without exhausting effective
alternative remedies available to it under law raising all
factual contentions which can be redressed before
Page 14 of 45
statutory authorities under the Act. It is further
contended that the show cause notice dated 10.09.2008
was issued to the petitioner and sent by speed post to
the petitioner’s registered address. During the course of
personal hearing held on 08.01.2018, the petitioner
submitted that their copy of the show cause notice has
got misplaced and hence they are not able to file reply.
As per the request of the petitioner, a photocopy of the
show cause notice was handed over to it under
acknowledgement.
He
further
contended
that the
impugned show cause notice has been issued based on
audit para/objection as per Board’s circular dated
10.03.1983. Since the audit para/objection was not
admitted by the Department as per Board’s circular
dated 14.12.1995 and 30.03.98, the show cause notice
was not adjudicated and transferred to call book. The
audit para was converted to statement of facts vide Para
2 of I.R.No.20/2005-06. Later on, CBEC, vide circular
no. 1023/11/2016-CX dated 08.04.2016, issued detailed
guidelines about “Adjudication of Show Cause Notices,
Page 15 of 45
issued on the basis of CERA/CRA objection”. At Para 6
of the said circular, the Board has clarified that the show
cause notices relating to audit objections figuring in the
list should not be adjudicated and further action should
be taken in consultation with the Commissioner. It was
further contended, as per the General Ledger for the
period from 01.04.2004 to 31.03.2005, in Voucher
No.9877 & 9878 both dated 9.12.2004, the Cenvat credit
of
Rs.35,29,10,811.16/-
and
Rs.3,88,83,006.92/-
respectively have been shown against debit with a note
that “merger of KMCL, Transaction for the period
01.04.2004 to 8.12.2004”. The ER-I return stated to
have
been
filed
with
the
Jurisdictional
Range
Superintendent is not available in the case file.
Therefore, it is contended that the show cause notice and
the resultant Order-in-Original deal with transfer of
Cenvat Credit from M/s KMCL to the petitioner not
related to availment of credit by M/s KMCL. The cause of
action against the Order-in-Original lies with the Central
Excise & Service Tax Appellate Tribunal (CESTAT),
Page 16 of 45
Eastern Zonal Bench, Kolkata under Section 35-B of the
Central Excise Act, 1944, therefore, the writ petition
before this Court is liable to be dismissed. To
substantiate his contention, learned Senior Standing has
placed reliance on Whirlpool v. Registrar of Trade
Marks, (1998) 8 SCC 1; State of Maharashtra and
others v Greatship (India) Limited, MANU/ SC/ 1206
/2022; United Bank of India v. Satyawati Tondon,
MANU/SC/0541/2010 : (2010) 8 SCC 110; and Jindal
Steel & Power Ltd. Vs Union of India (W.P.(C) No. 810
of 2016 decided on 02.05.2016)
5.
This Court heard Mr. Tarun Gulati, learned
Senior Advocate appearing along with Mr. Jnanesh
Mohanty and Ms. Gumansingh, learned counsel for the
petitioner; and Mr. T.K. Satapathy, learned Sr. Standing
Counsel along with Mr. A. Kedia, learned Jr. Standing
Counsel for Revenue in hybrid mode and perused the
records. Pleadings have been exchanged between the
parties and with the consent of learned counsel for the
Page 17 of 45
parties, the writ petition is being disposed of finally at
the stage of admission.
6.
As would be evident from the factual matrix,
as delineated above, the notice of show cause was issued
on 10.09.2008, which came to the knowledge of the
petitioner on 05.12.2017, when a personal hearing
notice pursuant to the show cause notice dated
10.09.2008, was issued to the petitioner. The same was
followed by another personal hearing notice dated
05.01.2018. It is only after issuance of these personal
hearing notices, the petitioner became aware of the
proceedings and obtained a copy of the show cause
notice dated 10.09.2008 on 08.01.2018, i.e., after a
lapse of more than 9 (nine) years from the date of show
cause notice. The petitioner filed its reply indicating
therein that the show cause notice was sought to be
adjudicated after a considerable lapse of time, without
any justification and without any communication to the
petitioner during the intervening period and, thereby, the
delay in adjudication of the show cause notice dated
Page 18 of 45
10.09.2008 is fatal to the proceedings and subsequent
issuance of notices for personal hearing after a lapse of
about 10 years from the date of issuance of the show
cause notice is contrary to the mandate of Sub-section
(11) of Section 11A of the Central Excise Act, 1944. For a
just and proper adjudication of the case, Section 11A of
the Central Excise Act, 1944 is quoted hereunder:-
“SECTION 11A OF THE CENTRAL EXCISE ACT,
1944
"SECTION 11A- Recovery of duties not levied or
not
paid
or
short-levied
or
short-paid
or
erroneously refunded. –
(1)
Where any duty of excise has not been
levied or paid or has been short-levied or short-
paid or erroneously refunded, for any reason,
other than the reason of fraud or collusion or any
willful mis-statement or suppression of facts or
contravention of any of the provisions of this Act
or of the rules made thereunder with intent to
evade payment of duty ,-
xxx
xxx
xxx
(4)
Where any duty of excise has not been
levied or paid or has been short-levied or short-
paid or erroneously refunded by reason of
(a)
fraud; or
(b)
collusion; or
(c)
wilfulmis-statement; or
(d)
suppression of facts; or
(e)
contravention of any of the
provisions of this Act or of the rules
made thereunder with intent to
evade payment of duty.
by any person chargeable with the duty, the
Central Excise Officer shall, within five years
from the relevant date, serve notice on such
person requiring him to show cause why he
Page 19 of 45
should not pay the amount specified in the notice
along with interest payable thereon under
section 11AA and a penalty equivalent to the
duty specified in the notice.
(5) Where, during the course of any audit,
investigation or verification, it is found that any
duty [has not been levied or paid or has been]
short - levied or short - paid or erroneously
refunded for the reason mentioned in clause (a)
or clause (b) or clause (c) or clause (d) or clause
(e) of sub-clause (4) but the details relating to the
transactions are available in the specified
records, then in such cases, the Central Excise
Officer shall within a period of five years from
the relevant date, serve a notice on the person
chargeable with the duty requiring him to show
cause why he should not pay the amount
specified in the notice along with interest under
section 11AA and penalty equivalent to fifty per
cent of such duty,
xxx
xxx
xxx
(11) The Central Excise Officer shall
determine the amount of duty of excise
under sub-section (10) –
(a) within six months from the date of
notice where it is possible to do so, in
respect of cases falling under subsection
(1);
(b) within two year [substituted for one
year w.e.f. 14-05-2016] from the date of
notice, where it is possible to do so, in
respect of cases falling under the
proviso to subsection (4) or sub-section
(5).
xxx
xxx
xxx”
7.
On perusal of the aforementioned provisions,
it is made clear Section 11A (11) of the Central Excise
Page 20 of 45
Act, 1944 envisages that the Central Excise Officer shall
determine the amount of duty of excise under Sub-
section (10) within six months from the date of notice
where it is possible to do so, in respect of cases falling
under Sub-section (1), i.e., where no suppression of facts
etc. are alleged) and within one year (substituted by two
years by the Finance Act, 2016 w.e.f. 14.05.2016) from
the date of notice, where it is possible to do so, in respect
of cases falling under the Sub-section (4) (i.e. where
suppression of facts etc. are alleged). Therefore, both the
notices for personal hearing issued to the petitioner on
05.12.2017 and 05.01.2018 under Annexure-3 (Colly.)
are contrary to the mandate of Section 11A of the
Central Excise Act, 1944 and thus, the adjudication of
the show cause notice is barred by limitation. Keeping
the show cause notice pending for a period of more than
9 years is contrary to the mandate of Section 11A(11) of
the
Central
Excise
Act,
1944
and,
thereby,
unreasonable, arbitrary, oppressive and violative of
Article 14 of the Constitution of India.
Page 21 of 45
8.
There is no dispute that M/s. KMCL, on the
date of its merger with the petitioner, had an unutilized
Cenvat Credit balance of Rs. 39,17,30,118/ - and the
petitioner filed an application on 22.12.2004 before the
Jurisdictional Officer for transfer of the said unutilised
Cenvat credit, in terms of Rule-10 of the Cenvat Credit
Rules, 2004. The relevant provision of Rule-10 is quoted
herein below:-
“RULE 10. Transfer of CENVAT credit. -
(1)
If a manufacturer of the final products
shifts his factory to another site or the factory is
transferred on account of change in ownership or
on account of sale, merger, amalgamation, lease
or transfer of the factory to a joint venture with
the specific provision for transfer of liabilities of
such factory, then, the manufacturer shall be
allowed to transfer the CENVAT credit lying
unutilized in his accounts to such transferred,
sold, merged, leased or amalgamated factory.
(2)
If a provider of output service shifts or
transfers his business on account of change in
ownership
or on
account
of sale,
merger,
amalgamation, lease or transfer of the business to
a joint venture with the specific provision for
transfer of liabilities of such business, then, the
provider of output service shall be allowed to
transfer the CENVAT credit lying unutilized in his
accounts to such transferred, sold, merged, leased
or amalgamated business.
(3)
The transfer of the CENVAT credit under
sub-rules (1) and (2) shall be allowed only if the
stock of inputs as such or in process, or the
capital goods is also transferred along with the
factory or business premises to the new site or
Page 22 of 45
ownership and the inputs, or capital goods, on
which credit has been availed of are duly
accounted for to the satisfaction of the Deputy
Commissioner of Central Excise or, as the case
may be, the Assistant Commissioner of Central
Excise.”
The application of the petitioner was allowed vide letter
of the authority dated 24.12.2004. Therefore, if the
amount has been transferred with the knowledge of the
competent authority after being satisfied, subsequently it
cannot turn around and take a different plea by issuing
a notice of show cause on 10.09.2008 without serving a
copy on the petitioner. However, owing to personal
hearing notices issued on 05.12.2017 and 05.01.2018, it
has been brought to the knowledge of the petitioner after
long lapse of nine years and on receipt of the same, the
petitioner filed show cause reply, but the same has not
been taken into consideration in its proper perspective.
9.
Mr. T.K. Satapathy, learned Sr. Standing
Counsel for Revenue vehemently urged before this Court
that the petitioner has not raised the question of
limitation in his show cause reply. Therefore, the action
taken by the authority is well justified. But it is brought
Page 23 of 45
to our notice by Mr. Gulati, learned Senior Advocate that
in post hearing written submission in Demand-cum-
Show Cause dated 10.09.2008, which has been placed
on record as Annexure-8 at paragraph-3 it has been
stated as follows:-
“It is submitted that the limitation for serving of
SCN under Section 11A of the CEA 1944, even in
cases where suppression, fraud etc. are alleged,
is 5 Years from the period of dispute, whereas in
the instant case, the impugned SCN was served
on the notice after more than 13 Years; hence the
impugned SCN is hopelessly barred by Limitation,
and liable to be dropped on this ground alone.”
Therefore, there is no iota of doubt that the petitioner
has raised the question of limitation by filing show cause
reply on 16.08.2023, but the Order-in-Original passed
by the authority on 04.09.2023 under Annexure-9 has
not spelt about the question raised with regard to
limitation, though the same has been urged before the
authority concerned.
10.
In Anand Nishikawa (supra), the apex Court
at paragraphs-23, 24, 25, 26, 27, 29 and 30 observed as
follows:-
Page 24 of 45
“23.
In the impugned order, CEGAT on perusal
of the correspondence between the appellant and
the department was unable to find any disclosure
in writing by the appellant with respect to post-
forming processes like notching, drilling etc. From
the materials on record which were produced
before the authorities and also from the orders of
the CEGAT and the Commissioner, it can be seen
that the department had the opportunity to inspect
the products of the appellants and in fact, the
factory of the appellants was inspected by them.
It may be true that the appellants might not have
disclosed the post-forming process in detail but
from the correspondence and other materials on
record, it cannot be conceived that the authorities
were not aware of the facts as, we gather from
the materials on record, admittedly, samples were
collected by the Department and even after the
samples
were
collected
and
inspected,
classification as supplied by the appellant in
respect of the products in question was approved
by them.
24.
Further more, it is also evident from
the record that the flow-chart of manufacturing
process
which
was
submitted
to
the
Superintendent of Central Excise, Rampur on
17.5.1990 clearly mentioned the fact of post
forming process on the rubber [See page 15 of the
Order of CEGAT]. The CEGAT in its order has also
recognized the fact of collection of some relevant
samples by the excise authorities on 25.9.1985
and 22.1.1988. [See paragraphs 7.1 & Page 14 of
the Order of CEGAT].
25.
In this view of the matter, we are unable to
persuade ourselves to agree with the finding of
the CEGAT as admittedly, the products of the
appellant were inspected from time to time and
the department was aware of the manufacturing
process of the products although the appellant
Page 25 of 45
might not have disclosed the post forming process
in detail.
26.
In Tata Iron & Steel Co. Ltd. vs. Union of
India & Ors [1988 (35) ELT 605 (SC)], this Court
held that when the classification list continued to
have been approved regularly by the department,
it could not be said that the manufacturer was
guilty of "suppression of facts". As noted herein
earlier,
we
have
also
concluded
that
the
classification lists supplied by the appellant were
duly approved from time to time regularly by the
excise authorities and only in the year 1995, the
department found that there was "suppression of
facts" in the matter of post forming manufacturing
process of the products in question. Furthermore,
in view of our discussion made herein earlier, that
the department has had the opportunities to
inspect the products of the appellant from time to
time and, in fact, had inspected the products of
the appellant. Classification lists supplied by the
appellant were duly approved and in view of the
admitted fact that the flow-chart of manufacturing
process submitted to the Superintendent of
Central Excise on 17.5.1990 clearly mentioned the
fact of post-forming process on the rubber, the
finding on "suppression of facts" of the CEGAT
cannot be approved by us. This Court in the case
of Pushpam
Pharmaceutical
Company
vs.
Collector of Central Excise, Bombay [1995 Supp
(3) SCC 462], while dealing with the meaning of
the expression "suppression of facts" in proviso
to section 11A of the Act held that the term must
be construed strictly, it does not mean any
omission and the act must be deliberate and
willful to evade payment of duty. The Court,
further, held : -
“In taxation, it ("suppression of facts")
can have only one meaning that the
correct information was not disclosed
Page 26 of 45
deliberately to escape payment of duty.
Where facts are known to both the
parties the omission by one to do what
he might have done and not that he
must have done, does not render it
suppression."
27.
Relying on the aforesaid observations of
this Court in the case of Pushpam Pharmaceutical
Co. Vs. Collector of Central Excise, Bombay [1995
Suppl. (3) SCC 462], we find that "suppression of
facts" can have only one meaning that the correct
information was not disclosed deliberately to
evade payment of duty, when facts were known
to both the parties, the omission by one to do
what he might have done not that he must have
done would not render it suppression. It is settled
law that mere failure to declare does not amount
to willful suppression. There must be some
positive act from the side of the assessee to find
willful suppression. Therefore, in view of our
findings made herein above that there was no
deliberate intention on the part of the appellant
not to disclose the correct information or to evade
payment of duty, it was not open to the Central
Excise Officer to proceed to recover duties in the
manner indicated in proviso to section 11A of the
Act. We are, therefore, of the firm opinion that
where facts were known to both the parties, as in
the instant case, it was not open to the CEGAT to
come to a conclusion that the appellant was guilty
of "suppression of facts". In Densons Pultretaknik
vs. Collector of Central Excise [2003 (11) SCC
390], this Court held that mere classification
under
a
different
sub-heading
by
the
manufacturer cannot be said to be willful
misstatement or "suppression of facts". This view
was also reiterated by this Court in Collector of
Central
Excise,
Baroda,
vs.
LMP
Precision
Engg.Co.Ltd. [2004 (9) SCC 703]
Page 27 of 45
xxx
xxx
xxx
29.
Similarly, in the case of Collector Central
Excise, Jamshedpur Vs. Dabur India Ltd., [2005
(121) ECR 129 (SC)], this Court held that the
extended period of limitation was not available to
the Department as classification lists filed by the
Assessee were duly approved by the authorities
from time to time. In that decision this Court
followed its earlier judgment in O.K. Play (India)
Ltd., vs. Collector of Central Excise, Delhi-III,
(Gurgaon) [2005 (66) RLT 657 (SC)], held that in
cases where classification lists filed by the
Assessee were duly approved, the extended
period of limitation would not be available to the
Department.
30.
For the reasons aforesaid, we are of the
view that the CEGAT was not justified in holding
that the extended period of limitation would be
available to the Department for initiating the
recovery proceedings under section 11A of the Act
on a finding that there was suppression of facts
by the appellant. Accordingly, it was not open to
the excise authorities to invoke proviso to section
11A of the Act and therefore, the demand of the
Revenue must be restricted to six months prior to
the issue of notice dated 19.10.1995 instead of
five years. In view of this conclusion, it is not
necessary for us to consider the question of
applicability of the classification lists namely of
4008.29 and 4016.19 and the question of
MODVAT facilities. Accordingly, in our opinion,
CEGAT came to a wrong conclusion for wrong
reasons and therefore, we allow this appeal and
set aside the judgment and order of the CEGAT
and restore the order of the Commissioner.”
11.
The entire proceeding was initiated on the
basis of AG Audit, though the same was contested and
Page 28 of 45
was taken out after the circular dated 08.04.2015, for
which there cannot be a valid explanation for delay. This
Court in IDCOL Ferro Chrome (supra) at paragraphs-6,
8, 9 and 10 observed as follows:-
6. In reply to the writ petition, there is no valid
explanation offered by the Department as to what
prompted it to shift the case to the Call Book on
28th April, 1999 and then retrieved it from the
said Call Book 16 years later, all of a sudden. The
precise averment in the counter affidavit in this
regard reads as under:
“4. That with regard to the averments
made in paragraph 1 of the Writ
petition, it is humbly submitted that no
time limit has been prescribed for
section 11A(2) of the Central Excise Act,
1944.
The
said
case
has
been
transferred to Call Book on 28.04.1999
and kept in Call Book as the matter
was arose out of objection by the office
of the Accountant General, Odisha
(AG(O))
and
the
central
Excise
Department (Opposite Party) contested
the matter with it. However. since no
decision has been taken by the Office of
the Accountant General, Odisha (AG(O)),
even after several letters from the
Opposite Parties to settle the issue, the
said Show Cause Notice was retrieved
from the Call Book on 15.07.2016
based on the Board’s Circular No.
1023/11/2016-CX dated 08.04.2016
and
initiated
the
process
of
Adjudication. A copy of the Board’s
Circular No. 1023/11/2016-CX dated
08.04.2016 is annexed herewith as
ANNEXURE-A/1.”
xxx
xxx
xxx
Page 29 of 45
8.
In Maxcare Laboratories Ltd. (supra), in
more or less identical circumstances, this Court
quashed the SCN and the further notice fixing the
date of hearing. In the presence case also the
Court is unable to find any valid explanation
offered by the Department in delaying in issuing
the initial SCN under Section 11A of the CE Act, 4
years after the period of demand and then, more
importantly, taking 16 years to retrieve the matter
from the Call Book. As noticed by this Court in
Maxcare Laboratories Ltd. (supra), in similar
circumstances, the Supreme Court of India in
Government
of
India
v.
Citedal
Fine
Pharmaceuticals 1989 (42) ELT 515, in the
context of proceedings for recovery of excise duty
on medicinal toilet preparations observed as
under:
“While it is true that Rule 12 does not
prescribe any period within which
recovery of any duty as contemplated
by the Rule is to be made, but that by
itself
does
not
render
the
Rule
unreasonable or violative of Article 14 of
the Constitution. In the absence of any
period of limitation it is settled that
every authority is to exercise the power
within a reasonable period. What would
be reasonable period, would depend
upon the facts of each case. Whenever a
question regarding the inordinate delay
in issuance of notice of demand is
raised, it would be open to the assessee
to contend that it is bad on the ground
of delay and it will be for the relevant
officer to consider the question whether
in the facts and circumstances of the
case notice or demand for recovery was
made within reasonable period. No hard
and fast rules can be laid down in this
regard as the determination of the
question will depend upon the facts of
each case.”
9. Likewise, in CCE v. Cemphar Drugs and
Liniments 1989 (40) ELT 276 (SC), the Supreme
Court observed as under:
Page 30 of 45
“In order to make the demand for duty
sustainable beyond a period of six
months and up to a period of 5 years in
view of the proviso to subsection 11A of
the Act, it has to be established that the
duty of excise has not been levied or
paid or short-levied or short-paid, or
erroneously refunded by reasons of
either fraud or collusion or wilful
misstatement or suppression of facts or
contravention of any provision of the Act
or Rules made thereunder, with intent
to evade payment of duty. Something
positive other than mere inaction or
failure on the part of the manufacturer
or producer or conscious or deliberate
withholding of information when the
manufacturer
knew
otherwise,
is
required before it is saddled with any
liability, beyond the period of six
months. Whether in a particular set of
facts and circumstances there was any
fraud or collusion or wilful misstatement
or suppression or contravention of any
provision of any Act, is a question of
fact depending upon the facts and
circumstances of a particular case.”
10.
Other High Courts too have invalidated
SCNs
where
attempts
were
made
by
the
Department to revive a matter sent to the Call
Book several years later. These decisions include
Siddhi Vinayak Syntex Pvt. Ltd. v. Union of
India 2017 (352) ELT 455 (Guj.) and Meghamani
Organics Ltd. v. Union of India 2019 (368) ELT
433 (Guj.)”
12.
It is well settled in law that inordinate delay in
adjudication of a show cause notice is fatal to its validity
since it causes prejudice. In Kamaladitya Construction
(supra), the Jharkhand High Court at paragraphs-21,
22, 25, 30, 31, 32 and 44 held as follows:-
Page 31 of 45
“21. At this stage it is pertinent to note that the
words "where it is possible to do so" is elastic only
when there are reasonable grounds beyond the
control of the adjudicating authority to conclude
adjudication within the time frame given under
Section 73(4B) and not otherwise.
22.
If there is no reasonable explanation, the
elasticity would not be available. It is fairly well
settled that legislature never wastes words or
says anything in vain. The insertion of sub-section
(4B) by Finance (No. 2) Act, 2014 is not without
any purpose or it is not a dead letter.
xxx
xxx
xxx
25.
Similar provisions exist under Section 11A
(11) of the Central Excise Act, 1944 and Section
28(9) the Customs Act, 1962. The period of
limitation of 6 months or 1 year under Section
73(4B) of the Chapter V of the Finance Act, 1994
be extended to more than seven years as is done
in the instant case.
xxx
xxx
xxx
30.
In the case of Shree Baba Exports Vs.
Commissioner of GST & Central Excise reported in
(2022) 72 PHT 35 (P&H) [Para 13] it is held by the
Punjab & Haryana High Court that the expression
"where it is possible to do so" does not mean that
the time prescribed can be extended perpetually
and the time limit cannot be taken to be directory
except in a case where the authority has a reason
to offer as an explanation for extending the said
time limit.
31.
In the case of Meghmani Organics Ltd. Vs.
UOI reported in 2019 (368) E.L.T. 433 (Guj.) [Para
24] it is held by the Gujarat High Court that when
the legislature has used the expression "where it
is possible to do so" it means that if in the
ordinary course it is possible to determine the
amount of duty with the specified time frame, it
should be so done. Similar views have been held
in the case of Siddhi Vinayak Put. Ltd Vs.
UOI reported in 2017 (352) E.L.T. 455 (Guj.)
Page 32 of 45
"19. Reliance
was
placed
upon
the
decision of the Supreme Court in the case
of Abdul Rehman Antulay v. R.S. Nayak,
(1992) 1 SCC 225, and more particularly
to the contents of paragraph 86 thereof,
wherein the Supreme Court has laid
down certain propositions which are
meant to serve as guidelines. Reference
was
made
to
clause
(3)(c)
thereof,
wherein the Court has observed that the
concerns underlying the right to speedy
trial from the point of view of the accused
are (c) undue delay may well result in
impairment of the ability of the accused
to defend himself, whether on account of
death, disappearance or non-availability
of
witnesses
or
otherwise.
It
was
submitted that the said decision though
rendered in the context of the provisions
of the Code of Criminal Procedure would
also be applicable to the facts of the
present case, inasmuch as, the petitioner
also is entitled to the right of speedy
adjudication of the show cause notice
issued against it and that the delay
would result in disappearance or non-
availability
of
witnesses
and
other
documentary evidence on which the
petitioner may place reliance. It was
submitted
that
in
case
of
indirect
taxation, the sooner the decision is taken,
the assessee can recover its dues from
the Revenue or the Revenue from the as-
sessee, as the case may be. It was
submitted that if transferring of a matter
to the call book to await adjudication by
the higher authority is taken to its logical
end, in a given case, if the Appellate
Tribunal comes to a particular view and
the aggrieved party approaches the High
Court and thereafter the Supreme Court,
the matters would remain in the call book
for years together. It was submitted that
the statute does not contemplate such a
course of action."
Page 33 of 45
32.
In
the case of GPI
Textiles Ltd.
Vs.
UOI reported in 2018 (362) E.L.T. 388 (P&H) [Para
17] the Hon'ble Punjab & Haryana High Court has
held that although the words 'where it is possible
to do' has been used, that will not stretch the
period to decades.”
In the aforesaid judgment, the Jharkhand High Court
also referred to the decision of Punjab and Haryana High
Court in case of M/s. Shree Baba Exports (supra),
which has been confirmed by the apex Court in S.L.P.(C)
No. 12376 of 2022 disposed of on 29.07.2022.
13.
Much argument was advanced with regard to
transfer of the case to the call book. But fact remains, it
has not been brought to the notice of the petitioner at
any point of time, though the obligation casts on the
department to inform the petitioner of transfer of the
case to the call book. In ATA Freights Line (supra), the
High Court of Bombay, at paragraphs- 23, 24, 27 and 29
held as follows:-
“23. Neither
the
affidavit-in-reply
nor
the
arguments advanced by the learned counsel for
the respondents indicated that the petitioner was
at any point of time informed about the transfer of
file relating to the show cause notices in question
to call book prior to the date of the petitioner's
letter asking for closure report.
Page 34 of 45
24. This Court in case of Parle International
Ltd. (supra) after considering the identical facts
and after adverting to the judgment in cases of
Bhagwandas
S.
Tolani
(supra), Sanghvi
Reconditioners
Pvt.
Ltd. (supra)
and Reliance
Industries Ltd. (supra) held that that a show-
cause notice issued a decade back should not be
allowed to be adjudicated upon by the revenue
merely because there is no period of limitation
prescribed in the statute to complete such
proceedings. Larger public interest requires that
revenue should adjudicate the show-cause ppn
12 wp-3671.21_j_.doc notice expeditiously and
within a reasonable period. It is held that keeping
the show-cause notice in the dormant list or the
call book, such a plea cannot be allowed or
condoned by the writ court to justify inordinate
delay at the hands of the revenue. This Court was
accordingly pleased to quash and set aside the
show cause notices which were pending quite
some time.
xxx
xxx
xxx
27. It is held that the respondent having issued
the Show-Cause notice, it is their duty to take the
said Show-Cause notice to its logical conclusion
by adjudicating upon the said Show-Cause Notice
within a reasonable period of time. In view of
gross delay on the part of the respondent, the
petitioner cannot be made to suffer. This Court
accordingly was pleased to quash and set aside
dated 16th September 2005 in that matter. The
principles of law laid down by this Court in the
above referred judgment would apply to the facts
of this case. We are respectfully bound by the
principles of law laid down by this Court in the
said judgment. We do not propose to take a
different view in the matter.
xxx
xxx
xxx
29. In our view, since the respondents were
totally responsible for gross delay in adjudicating
the show cause notices issued by the respondents
causing prejudice and hardship to the petitioner
and have transferred the show cause notices to
Page 35 of 45
call
book
and
kept
in
abeyance
without
communication to the petitioner for more than 7 to
11 years, the respondents cannot be allowed to
raise alternate remedy at this stage. Be that as it
may,
no
order has been passed by the respondents on the said show cause notices. The question of filing any appeal by the petitioner
therefore did not arise.” The said judgment of the Bombay High Court has been confirmed by the apex Court in S.L.P (C) No. 828 of 2023 disposed of on 10.02.2023. 14. A serious contention was raised by learned Senior Standing Counsel for Revenue that due to availability of alternative remedy, i.e., filing of appeal under Section 35-B of the Act, the present proceeding is not maintainable.
“49. The views expressed in Titaghur Paper Mills SCC 260 in the following words: (SCC p. 264, para 3) “3. … Article 226 is not meant to short- circuit or circumvent statutory procedures. It is only where statutory remedies are entirely ill-suited to meet the demands of extraordinary situations, as for instance where the very vires of the statute is in question or where private or public wrongs are so inextricably mixed up and the prevention of public injury and the vindication of public justice require it that recourse may be had to Article 226 of the Constitution. But then the Court must have good and sufficient reason to bypass the alternative remedy provided by statute. Surely matters involving the revenue where statutory remedies are available are not such matters. We can also take judicial notice of the fact that the vast majority of the petitions under Article 226 of the Constitution are filed solely for the purpose of obtaining interim orders and thereafter prolong the proceedings by one device or the other. The practice certainly needs to be strongly discouraged.”
We do not propose to go into the correctness of the decision of the High Court and whether the order passed by the Tribunal was correct or not has to be decided before an appropriate forum.
exercising juri iction under Article 226 of the Constitution. Paras 29 and 30 of that judgment which contain the views of this Court read as under: (SCC pp. 175-76) “29. In our opinion, the High Court while exercising its extraordinary juri iction under Article 226 of the Constitution is duty-bound to take all the relevant facts and circumstances into consideration and decide for itself even in the absence of proper affidavits from the State and its instrumentalities as to whether any case at all is made out requiring its interference on the basis of the material made available on record. There is nothing like issuing an ex parte writ of mandamus, order or direction in a public law remedy. Further, while considering the validity of impugned action or inaction the Court will not consider itself restricted to the pleadings of the State but would be free to satisfy itself whether any case as such is made out by a person invoking its extraordinary juri iction under Article 226 of the Constitution.
(f) grant of relief is against public policy or barred by any valid law; and host of other factors. The Court in appropriate cases in its discretion may direct the State or its instrumentalities as the case may be to file proper affidavits placing all the relevant facts truly and accurately for the consideration of the Court and particularly in cases where public revenue and public interest are involved. Such directions are always required to be complied with by the State. No relief could be granted in a public law remedy as a matter of course only on the ground that the State did not file its counter-affidavit opposing the writ petition. Further, empty and self-defeating affidavits or statements of Government spokesmen by themselves do not form basis to grant any relief to a person in a public law remedy to which he is not otherwise entitled to in law.”
in Sub-Section (1) of Section 11A cannot be applied. If an order of refund is passed after adjudication, the amount refunded will not fall under the category of erroneous refund so as to enable the order of refund to be revoked under Section 11A(1). One Authority cannot be allowed to say in a collateral proceeding that what was done by another Authority was an erroneous thing. Therefore, the question of law has to be answered in favour of the appellant/assessee and the appeal deserves to be allowed.
restraint, which is exercised when called upon to invoke constitutional powers conferred by Article 226 of the Constitution. As such, the Delhi High Court found that the second respondent while considering the claim for refund has clearly acted in excess of the juri iction which could have been exercised and accordingly rejected the objection of the authority.
(DR. B.R. SARANGI)
G. SATAPATHY, J. I agree.
(G. SATAPATHY)