M/S Kalimata Vyapaar PVT. LTD. vs. The Union Of INDIA And 3 Ors.

WP(C)/5135/2022HC GauhatiGSTCNR GAHC01014982202229 October 2025Bench: HONOURABLE MR. JUSTICE DEVASHIS BARUAH15 pages
AI SummaryAllowed

Held

The Court held that no concluded contract was formed between the petitioner and the respondent authorities. The Court reasoned that the respondent's letter of acceptance dated April 1, 2022, did not unequivocally accept the petitioner's quoted deviations and, importantly, altered the price variation formula specified in Clause 25.5 of the Special Conditions of Contract (SCC). According to Section 7 of the Indian Contract Act, 1872, an acceptance must be absolute and unqualified to convert a proposal into a promise. The changes made by the respondents in the letter of acceptance constituted a counter-offer. The petitioner's refusal of this counter-offer on April 4, 2022, within a reasonable time, meant that no agreement was reached. Consequently, the purchase order dated April 27, 2022, issued without a concluded contract, could not bind the petitioner. The Court further held that the termination of the contract and the imposition of a penalty via the communication dated July 18, 2022, were therefore impermissible. The Court quashed the impugned communication dated July 18, 2022.

Facts

The petitioner, M/s Kalimata Vyapaar Pvt. Ltd., filed a writ petition challenging a communication dated July 18, 2022, by which the respondent authorities, specifically Deputy Chief Engineer/Track Procurement, Northeast Frontier Railway, terminated a contract and imposed a 10% penalty. The dispute arose from a Notice Inviting Tender (NIT) issued on December 6, 2021, for the manufacture and supply of Elastic Rail Clips (ERC). The petitioner submitted its bid on December 27, 2021, with certain deviations. The respondent authorities issued a letter of acceptance on April 1, 2022, which the petitioner refused on April 4, 2022, citing unaccepted deviations and a changed price variation formula. Subsequently, a purchase order was issued on April 27, 2022, which the petitioner contended was invalid due to the lack of a concluded contract.

Key Issues

1. Whether a concluded contract was formed between the petitioner and the respondent authorities for the supply of Elastic Rail Clips (ERC) based on the Notice Inviting Tender (NIT) dated December 6, 2021, and subsequent communications, particularly concerning the acceptance of deviations and the price variation formula? (Question of mixed law and fact, turning on principles of contract formation under the Indian Contract Act, 1872, and the terms of the NIT). Petitioner's arguments: The petitioner contended that no concluded contract was formed because the respondent's letter of acceptance dated April 1, 2022, did not address the deviations quoted by the petitioner and altered the price variation formula stipulated in Clause 25.5 of the Special Conditions of Contract (SCC). Therefore, the letter of acceptance constituted a counter-offer, which the petitioner rightly refused. Consequently, the subsequent purchase order dated April 27, 2022, was invalid, and the termination and penalty imposed by the communication dated July 18, 2022, were unlawful. Revenue's arguments: The respondent authorities argued that a concluded contract existed, implying that the petitioner was bound by the terms and conditions, including the purchase order and the subsequent termination. (Specific arguments for the revenue were not explicitly detailed in the provided text, but their actions imply a belief in a concluded contract).

Sections Cited

Section 2, Section 7

AI-generated summary — verify with the full judgment below

Page No.# 1/15 GAHC010149822022

2025:GAU-AS:14632

THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Case No. : WP(C)/5135/2022 M/S KALIMATA VYAPAAR PVT. LTD. 14/2, OLD CHINA BAZAR STREET 3RD FLOOR, ROOM NO. 213, KOLKATA- 700001, REP BY ONE OF ITS DIRECTORS AND AUTHORIZED SIGNAORY SRI VIKAS JHAWAR (AGE 40 YEARS) S/O SRI MAHENDRA KUMAR JHAWAR R/O AE-9 SALT LAKE CITY SECTOR-I, P.S. BIDHANNAGAR, P.O. SALT LAKE CITY, DIST. NORTH 24 PARGANAS, KOLKATA-700064 VERSUS THE UNION OF INDIA AND 3 ORS. REP. BY THE SECRETARY TO THE GOVERNMENT OF INDIA, MINISTRY OF RAILWAY, RAIL BHAWAN, NEW DELHI- 110001. 2:PRINCIPAL CHIEF ENGINEER NORTHEAST FRONTIER RAILWAY MALIGAON GUWAHATI-781011 3:DEPUTY CHIEF ENGINEER/TRACK PROCUREMENT NORTHEAST FRONTIER RAILWAY MALIGAON GUWAHATI-781011 4:DEPUTY CHIEF ENGINEER TRACK MACHINE NORTHEAST FRONTIER RAILWAY MALIGAON GUWAHATI-78101

Page No.# 2/15

B E F O R E HON’BLE MR. JUSTICE DEVASHIS BARUAH

Advocates for the petitioner(s) :Mr. M Biswas

Advocates for the respondent(s) : Mr

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Gauhati High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.