M/S Limin Enterprises And Anr vs. The State Of Ap And 6 Ors
Held
The Court held that the claim of the petitioners for the execution of works amounting to Rs. 13,10,000/- under the specified work orders is not disputed by the respondent authorities. While the respondents raised doubts regarding the delay in the issuance of the work orders, this did not negate the fact that the works were executed and the amount claimed was not contested. Therefore, the Court deemed it appropriate to dispose of the writ petition with a direction to the respondent authorities. The direction mandates the respondents to conduct an inquiry and verify the petitioners' claim. If the claim is found to be admissible, the petitioners are to be paid the outstanding amount of Rs. 13,10,000/-. The Court specified that this exercise should be completed within a period of three months from the date of the order. No specific GST provisions were discussed in detail, but the work orders themselves mention GST at 18%.
Facts
M/s Limin Enterprises and its proprietor, Beli Gadi (petitioners), filed a writ petition seeking a direction for the release of outstanding payment amounting to Rs. 13,10,000/-. This amount is for works executed pursuant to three work orders issued by the Department of Power, Arunachal Pradesh, in February 2024. The petitioners submitted their bills after completing the work, but the payment had not been released. The respondent authorities, while not disputing the amount claimed for the executed works, raised doubts regarding the issuance of the work orders. They noted that the decision to execute the works was taken in 2022, but the work orders were issued in 2024, significantly after the stipulated implementation period of 45 days. Consequently, the authorities decided to conduct an inquiry into the matter.
Key Issues
1. Whether the respondent authorities should be directed to release the undisputed payment of Rs. 13,10,000/- to the petitioners for works executed under work orders dated 23.02.2024 and 26.02.2024, despite doubts raised by the respondents regarding the delayed issuance of these work orders in contravention of the original decision taken in 2022? Petitioner's Contention: The petitioners argued that they have executed the works as per the issued work orders and submitted their bills. They contended that the amount of Rs. 13,10,000/- is undisputed and therefore, the respondent authorities should be directed to release the payment promptly. Respondent's Contention: The respondent authorities, represented by the learned Standing Counsel, Power Department, fairly submitted that the amount claimed by the petitioners is not disputed. However, they raised concerns about the issuance of the work orders in 2024, two years after the decision to execute the works was taken in 2022, and when the implementation was expected within 45 days. Due to these discrepancies, the respondents decided to conduct an inquiry into the matter.
Sections Cited
None explicitly discussed or applied in the judgment's reasoning, though GST is mentioned in the work orders.
AI-generated summary — verify with the full judgment below
Page No.# 1/8 GAHC040005302025
THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) (ITANAGAR BENCH) Case No. : WP(C)/155/2025 M/s Limin Enterprises and Anr C Sector, Gandhi Market, Itanagar, Papum Pare District, Arunachal Pradesh. 2: Beli Gadi Age: Occupation : Son of Shri Tabe Gadi proprietor of M/s Limin Enterprises permanent resident of Deke Village PO and PS Tirbin Leparada District Arunachal Pradesh VERSUS The State of AP and 6 Ors through the Chief Secretary, Govt of Arunachal Pradesh, Itanagar. 2:The Secretary (Power) Age: 0 Occupation : Govt of Arunachal Pradesh Itanagar. 3:The Secretary Planning and Investment Age: 0 Occupation : Civil Secretariat Govt of Arunachal Pradesh Itanagar. 4:The Chief Engineer (Central Zone) Age: 0
Page No.# 2/8 Occupation : Department of Power Electrical at Vidyut Bhawan 0 Point Tinali Govt of Arunachal Pradesh Itanagar. 5:The Chief Engineer Age: 0 Occupation : Transmission Monitoring and Planning Zone Department of Power (Electrical) at Vidyut Bhawan 0 Point Tinali Govt of Arunachal Pradesh Itanagar. 6:The Superintendent Engi
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Gauhati High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.