M/S S.S. Total Construction (I) PVT. LTD. vs. Union Of INDIA Through Executive Engineer
Held
The Court held that the Commercial Court's judgment was a result of a total non-application of mind. The challenge under Section 34 of the Arbitration and Conciliation Act, 1996, was limited to two specific claims (GST refund and interest) and the rejection of the counter-claim. However, the Commercial Court, in a misguided manner and apparently without examining the record, dealt with an issue pertaining to compensation for delayed completion of work, which was not part of the Section 34 application at all. The Court found that the judgment appeared to be a copy-paste from another case, vitiating the impugned judgment. Consequently, the appeal was allowed, the Commercial Court's judgment was quashed and set aside, and the matter was remanded back for a fresh hearing and decision based on the submissions and the record.
Facts
The appellant, S.S. Total Construction (I) Pvt. Ltd., was awarded a contract for civil and electrical work. The contract commenced on 04.05.2016 with a completion date of 03.07.2017. Following final bill payment, the appellant claimed withheld payments and other losses due to contract prolongation, treating the payment as 'under protest'. A Dispute Redressal Committee's decision was unsatisfactory, leading to the appointment of a Sole Arbitrator. The appellant filed claims under 13 heads, and the Arbitrator awarded claims under 9 heads while dismissing the counter-claim. The respondent, Union of India, filed an application under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the award primarily concerning GST refund (claim no. 10), interest on awarded claims (claim no. 12), and the rejection of the counter-claim regarding the appellant's GST liability on reimbursement.
Key Issues
1. Whether the Commercial Court erred in setting aside the entire arbitral award when the Section 34 application was limited to specific claims and the rejection of the counter-claim? Petitioner's arguments: The Commercial Court failed to apply its mind to the dispute, acting mechanically and without considering the factual aspects. The Section 34 application was restricted to two awarded claims and the rejected counter-claim. The Commercial Court erroneously addressed an issue not raised in the Section 34 application, specifically compensation for delayed completion of the project, and set aside the entire award, including claims already paid. Respondent's arguments: The Union of India's counsel could not dispute the submissions regarding the limited scope of the challenge under Section 34, the payment of the rest of the award, and the Commercial Court's judgment being rendered dehors the challenge laid.
Sections Cited
Section 34, Section 37
AI-generated summary — verify with the full judgment below
HIGH COURT OF JUDICATURE AT ALLAHABAD APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 No. - 205 of 2025 Chief Justice's Court HON'BLE ARUN BHANSALI, CHIEF JUSTICE HON'BLE KSHITIJ SHAILENDRA, J.
This appeal is directed against judgement dated 13.05.2025 passed by the Commercial Court, Bareilly whereby the application filed by the respondent - Union of India under Section 34 of the Arbitration and Conciliation Act, 1996 ('Act') against award dated 10.12.2022 has been allowed and award impugned has been set aside.
Respondent floated a composite tender (civil and electrical work) for construction of permanent infrastructure at SHQ & Bn. Headquarters, Lakhimpur Kheri under Lucknow frontier; the appellant participated in the biding process and was awarded the contract and agreement was entered into. As per the agreement, date of commencement of the work was 04.05.2016 and the stipulated time for completion was fourteen months i.e. the scheduled date of completion was 03.07.2017. 3. It was claimed by the appellant that upon receiving the payment as per unilateral final bill finalized by the respondent, the appellant required the respondent to release
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Allahabad High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.