Union Of INDIA vs. M/S Anand And Company
Held
The Court partially allowed the petition, setting aside certain parts of the arbitral award while upholding others. Regarding the release of amounts withheld for non-achievement of milestones, the award was upheld, but the award of interest on this withheld amount was set aside. The Court corrected the amount awarded for the final bill to Rs. 54,44,112/-, rectifying a clerical error. The award of a three percent difference between post-GST and pre-GST periods was set aside, finding it to be based on assumed calculations and contrary to the contract. The refund of the penalty for the sample flat delay was upheld. Crucially, the award of damages under Section 73 of the Contract Act for contract prolongation was set aside, as the Court found no proof of actual loss or damage suffered by the respondent, and the arbitrator's quantification was based on assumptions. The interest awarded, except on the withheld amount for milestones, and the costs awarded were upheld. The Court relied on the principle of severability of awards as per Gayatri Balasamy v. ISG Novasoft Technologies Ltd., allowing it to set aside specific parts of the award without nullifying the entire award.
Facts
The petitioner, Union of India, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated February 17, 2023. The dispute arose from an e-tender for construction work awarded to the respondent, M/s Anand and Company. The contract stipulated a completion period of twelve months from July 11, 2017. Disputes emerged during execution, leading to arbitration after the respondent invoked Clause 25 of the General Conditions of Contract. The petitioner contested several aspects of the award, including the release of withheld amounts for non-achievement of milestones, the calculation of final bills, the award related to GST vs. VAT difference, the refund of a penalty for a sample flat delay, damages for contract prolongation, interest, and costs.
Key Issues
1. Whether the arbitrator erred in directing the release of Rs. 35,12,328/- withheld for the respondent's failure to achieve milestones, considering the distinction between extension of time and rescheduling of milestones, and the petitioner's entitlement to withhold ten percent of the tender value under Clause 2 of the contract. 2. Whether the arbitrator made a clerical error in awarding Rs. 71,45,578/- for pending final bills by not deducting amounts already paid. 3. Whether the award of a three percent difference on account of GST versus VAT was based on assumed calculations and contrary to Clause 38 of the contract, which mandates reimbursement of GST paid. 4. Whether the refund of Rs. 3,00,000/- penalty for delay in completing the sample flat was allowed without adequate reasoning and in disregard of contract terms. 5. Whether the grant of loss of on-site and off-site expenses for the prolongation period was contrary to Section 73 of the Indian Contract Act, 1872, and Supreme Court precedents like Kailash Nath Associates v. DDA, given the alleged lack of proof of actual loss. 6. Whether the interest awarded at nine percent and costs of Rs. 8,00,000/- were excessive and contrary to the contract provision for equal sharing of arbitration costs. Petitioner's arguments: The arbitrator erred in releasing withheld amounts, making clerical errors in final bills, awarding GST difference without proof of deposit, refunding penalty without reasons, granting damages for prolongation without proof of actual loss, and awarding excessive interest and costs. Respondent's arguments: Delay was attributable to the petitioner, milestones should have been rescheduled under Clause 5.4, interest on withheld amounts was justified, GST reimbursement was correct under Clauses 37 and 38, sample flat delay was due to petitioner's revisions, damages for prolongation were reasonable based on CA certificate and delay, and interest/costs were within the arbitrator's discretion.
Sections Cited
Section 34, Section 73, Section 31A(3)
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
J U D G M E N T
This petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short „the Act‟) challenging the arbitral award dated 17.02.2023. 2. The facts in brief are that the petitioner invited an e-tender for construction of hundred Family Quarters (Type-II, III & IV) including internal W/S, S/I and electrical works for ITBP 22nd Bn. Campus at Chhawla, New Delhi. The bid of the respondent was accepted and a Letter of Acceptance (for short „LOA‟) dated 20.06.2017 was is
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.