Cause title — parties, addresses and appearances
OMP (COMM.) 380/2025
Page 1 of 22
$~17
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 28.04.2026
+
O.M.P. (COMM) 380/2025 & I.A. 23412/2025
AGRICULTURE INSURANCE COMPANY OF INDIA
LIMITED
.....Petitioner
Through:
Mr. Rana Mukherjee, Sr.Adv.
with Ms. Surabhi Guleria, Adv.
versus
SEMANTIC TECHNOLOGIES AND AGRITECH SERVICES
PVT. LTD.
.....Respondent
Through:
Ms. Fereshte D. Sethna, Mr.
Prakalathan Bathey & Mr.
Abhishek Chauhan, Advs.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
%
JUDGEMENT (ORAL)
1.
The present Petition has been filed under Section 34 of the
Arbitration and Conciliation Act, 19961, seeking partial setting
aside of the Arbitral award dated 30.04.20252 passed by the learned
Sole Arbitrator3 in the arbitration proceedings titled as "Semantic
Technologies and Agritech Services Pvt. Ltd vs. Agriculture Insurance
Company of India Ltd.".
2.
Mr. Rana Mukherjee, learned Senior Counsel, appearing on
behalf of the Petitioner, submits that the challenge to the Impugned
award is confined to Claim No. 10, pertaining to the Kharif Season
1 A&C Act
2 Impugned Award
3 Arbitrator
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 2 of 22
2022 in the State of Maharashtra.
3.
It is contended by the learned Senior Counsel that the finding
returned by the learned Arbitrator suffers from perversity, since
certain material aspects, including the communication dated
07.08.2023 inter se the parties and the conduct of the Respondent in
accepting payments, have not been duly considered whilst
adjudicating upon the Claim No. 10 in the Impugned award.
4.
It is submitted that the Communication dated 07.08.2023, read
in conjunction with the conduct of the Respondent, precludes the
Respondent from raising any further claim for payment against the
Petitioner. In support of this contention, learned counsel draws the
attention of this Court to the aforementioned communication dated
07.08.2023, addressed by the Respondent to the Petitioner, which
reads as follows:
“Dear Sir,
We thank you for the payment against our invoices dated
18.07.2023 for Osmanabad, Nandurbar, Sangli, Gadchiroli,
Washim and Amravati Districts.
It is apparent from the payment made by AIC till date that a large
number of surveys have been rejected. Kindly inform us the details
of the ILA surveys rejected from each of the above districts. This
information is required to enable us to make balance payments due
to the field surveyors along with informing them the details of the
surveys rejected against their account.
We request you to kindly return the rejected ILA Forms to our
office at Pune, along with a declaration from AIC RO Mumbai
stating that the data in the rejected ILA survey forms have not been
used by AIC for Claim Settlement.”
5.
Learned Senior Counsel, therefore, submits that a perusal of the
aforesaid communication would indicate that the said e-mail
constitutes an acknowledgement on the part of the Respondent that the
payments made against the invoices dated 18.07.2023 were in full and
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 3 of 22
final discharge of all dues in respect of the Kharif Season 2022 in the
State of Maharashtra.
6.
He further submits that the payments, in fact, continued to be
made till as late as August 2023, and at no point in time did the
Respondent raise any protest or reservation while accepting the same.
7.
It is contended by the learned Senior Counsel that the payments
which were made by the Petitioner were accepted unconditionally and
without demur. Reliance is placed upon the ruling of the Hon‟ble
Supreme Court in Nathani Steels Ltd. v. Associated Constructions4,
particularly paragraph no. 3 thereof, to contend that once a settlement
is arrived at, no arbitrable dispute survives. Paragraph no. 3 of the said
judgment is extracted herein below for ready reference:
“3. The appellant has invited our attention to two decisions of this
Court. The first dated 1-10-1993 in P.K. Ramaiah and
Co. v. Chairman & Managing Director, National Thermal Power
Corpn. [1994 Supp (3) SCC 126] and second, dated 4-2-1994
in State of Maharashtra v. Nav Bharat Builders [1994 Supp (3)
SCC 83]. In the first mentioned case the parties had resolved their
disputes and differences by a settlement pursuant whereto the
payment was agreed and accepted in full and final settlement of the
contract. Thereafter, brushing aside that settlement the Arbitration
clause was sought to be invoked and this Court held that under the
said clause certain matters mentioned therein could be settled
through Arbitration but once those were settled amicably by and
between the parties and there was full and final payment as per the
settlement, there existed no arbitrable dispute whatsoever and,
therefore, it was not open to invoke the Arbitration clause. In the
second mentioned case the respondent-Contractor acknowledged
the receipt of the amount paid to him and stated that there was
unconditional withdrawal of his claim in the suit in respect of the
labour escalation. There was, thus, full and final settlement of the
claim and it was contended that no arbitrable dispute survived in
relation thereto. Other claims, if any, and which were not settled by
and between the parties could be raised and it would be open to
consider whether the arbitrable dispute arose under the contract
necessitating reference to arbitration. Dealing with this question
also this Court after referring to the decision in P.K. Ramaiah
4 1995 Supp (3) SCC 324
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 4 of 22
case [1994 Supp (3) SCC 126] concluded that in relation to the
claim under the head „labour escalation‟ there did not remain any
arbitrable dispute which could be referred to arbitration. It would
thus be seen that once there is a full and final settlement in respect
of any particular dispute or difference in relation to a matter
covered under the Arbitration clause in the contract and that dispute
or difference is finally settled by and between the parties, such a
dispute or difference does not remain to be an arbitrable dispute
and the Arbitration clause cannot be invoked even though for
certain other matters, the contract may be in subsistence. Learned
counsel for the respondent, however, placed great emphasis on an
earlier decision of this Court in Damodar Valley Corpn. v. K.K.
Kar [(1974) 1 SCC 141] and in particular to the observations made
in paras 11 to 13 of the judgment. It may, at the outset, be pointed
out that a similar argument was advanced based on the observations
made in this decision, in Ramaiah case [1994 Supp (3) SCC 126]
also (vide para 7) but the same was rejected holding that on the
facts since the respondent did not give any receipt accepting the
settlement of the claim, the payment made by the other side was
only unilateral and hence the dispute subsisted and the Arbitration
clause in the contract could be invoked. Therefore, that decision
can be distinguished on facts. Even otherwise we feel that once the
parties have arrived at a settlement in respect of any dispute or
difference arising under a contract and that dispute or the difference
is amicably settled by way of a final settlement by and between the
parties, unless that settlement is set aside in proper proceedings, it
cannot lie in the mouth of one of the parties to the settlement to
spurn it on the ground that it was a mistake and proceed to invoke
the Arbitration clause. If this is permitted the sanctity of contract,
the settlement also being a contract, would be wholly lost and it
would be open to one party to take the benefit under the settlement
and then to question the same on the ground of mistake without
having the settlement set aside. In the circumstances, we think that
in the instant case since the dispute or difference was finally settled
and payments were made as per the settlement, it was not open to
the respondent unilaterally to treat the settlement as non est and
proceed to invoke the Arbitration clause. We are, therefore, of the
opinion that the High Court was wrong in the view that it took.”
8.
In view thereof, he submits that the conduct of the Respondent
when seen in totality, clearly evidences a concluded settlement
between the parties, thereby estopping the Respondent from raising
any further claims over and above what had already been
acknowledged as the final payment in respect of the Kharif Season
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 5 of 22
2022 in the State of Maharashtra.
9.
He further submits that as per the arrangement between the
parties and as communicated by the Petitioner, the Respondent was to
ensure that all the ILA survey forms were to be submitted by
30.04.2023 and there was no obligation on the part of the Petitioner to
entertain any forms post this date. The rejection en masse of forms
submitted after this date does not suffer from any infirmity.
10.
It is thus contended by the learned Senior Counsel that the
learned Arbitrator, having failed to consider the aforesaid aspects, has
rendered an award which is vitiated and liable to be set aside.
11.
Per contra, learned counsel appearing on behalf of the
Respondent, submits that the Impugned award is well reasoned and
does not suffer from any infirmity warranting interference under
Section 34 of the A&C Act.
12.
She submits that the learned Arbitrator has duly considered all
relevant aspects of the matter, including the express terms of the
contract, and has correctly observed that no such deadline, as is now
sought to be asserted by the Petitioner, was ever stipulated therein.
13.
She further submits that the learned Arbitrator has also taken
into account the contemporaneous correspondence exchanged between
the parties, including the email dated 27.04.2023, read in conjunction
with the minutes of meetings held on various dates, which, according
to her, clearly indicate that the alleged deadline of 30.04.2023 was
introduced for the first time only by way of the said email.
14.
It is further submitted that the jurisdiction of this Court under
Section 34 of the A&C Act is extremely circumscribed, and given the
narrow scope of interference permissible thereunder, this Court ought
not to interfere with the findings returned by the learned Arbitrator.
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 6 of 22
15.
She, therefore, submits that no ground is made out for the
exercise of jurisdiction by this Court under Section 34 of the A&C
Act, and the present Petition is liable to be dismissed.
ANALYSIS:
16.
This Court has carefully considered the submissions advanced
on behalf of both sides and, with their able assistance, has perused the
Impugned Award and the material placed before this Court.
17.
At the outset, it is apposite to note that this Court remains
conscious of the limited scope of its jurisdiction while examining an
objection petition under Section 34 of the A&C Act. There is a
consistent and evolving line of precedents whereby the Hon‟ble
Supreme Court has authoritatively delineated and settled the contours
of judicial intervention in such proceedings.
18.
In this regard, a 3-Judge Bench of the Hon‟ble Supreme Court,
after an exhaustive consideration of a catena of earlier judgments, in
OPG Power Generation Pvt. Ltd. v. Enexio Power Cooling Solutions
(India) Pvt. Ltd5 (supra), while dealing with the grounds of conflict
with the public policy of India, perversity and patent illegality,
grounds which have also been urged in the present case, made certain
pertinent observations, which are reproduced hereunder:
“Relevant legal principles governing a challenge to an arbitral
award
30. Before we delve into the issue/sub-issues culled out above, it
would be useful to have a look at the relevant legal principles
governing a challenge to an arbitral award. Recourse to a court
against an arbitral award may be made through an application for
setting aside such award in accordance with sub-sections (2), (2-A)
and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section 34
has two clauses, (a) and (b). Clause (a) has five sub-clauses which
are not relevant to the issues raised before us. Insofar as clause (b)
5 (2025) 2 SCC 417
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 7 of 22
is concerned, it has two sub-clauses, namely, (i) and (ii). Sub-
clause (i) of clause (b) is not relevant to the controversy in hand.
Sub-clause (ii) of clause (b) provides that if the Court finds that the
arbitral award is in conflict with the public policy of India, it may
set aside the award.
Public policy
31. “Public policy” is a concept not statutorily defined, though it
has been used in statutes, rules, notification, etc. since long, and is
also a part of common law. Section 23 of the Contract Act, 1872
uses the expression by stating that the consideration or object of an
agreement is lawful, unless, inter alia, opposed to public policy.
That is, a contract which is opposed to public policy is void.
*****
37. What is clear from above is that for an award to be against
public policy of India a mere infraction of the municipal laws of
India is not enough. There must be, inter alia, infraction of
fundamental policy of Indian law including a law meant to serve
public interest or public good.
*****
The 2015 Amendment in Sections 34 and 48
42. The aforementioned judicial pronouncements were all prior to
the 2015 Amendment. Notably, prior to the 2015 Amendment the
expression “in contravention with the fundamental policy of Indian
law” was not used by the legislature in either Section 34(2)(b)(ii) or
Section 48(2)(b). The pre-amended Section 34(2)(b)(ii) and its
Explanation read:
*****
44. By the 2015 Amendment, in place of the old Explanation to
Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove
any doubt as to when an arbitral award is in conflict with the public
policy of India.
45. At this stage, it would be pertinent to note that we are dealing
with a case where the application under Section 34 of the 1996 Act
was filed after the 2015 Amendment, therefore the newly
substituted/added Explanations would apply [Ssangyong Engg. &
Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131].
46. The 2015 Amendment adds two Explanations to each of the
two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b), in
place of the earlier Explanation. The significance of the newly
inserted Explanation 1 in both the sections is two-fold. First, it does
away with the use of words : (a) “without prejudice to the
generality of sub-clause (ii)” in the opening part of the pre-
amended Explanation to Section 34(2)(b)(ii); and (b) “without
prejudice to the generality of clause (b) of this section” in the
opening part of the pre-amended Explanation to Section 48(2)(b);
secondly, it limits the expanse of public policy of India to the three
specified
categories
by
using
the
words
“only
if”.
Whereas, Explanation 2 lays down the standard for adjudging
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 8 of 22
whether there is a contravention with the fundamental policy of
Indian law by providing that a review on merits of the dispute shall
not be done. This limits the scope of the enquiry on an application
under either Section 34(2)(b)(ii) or Section 48(2)(b) of the 1996
Act.
47. The 2015 Amendment by inserting sub-section (2-A) in Section
34, carves out an additional ground for annulment of an arbitral
award arising out of arbitrations other than international
commercial arbitrations. Sub-section (2-A) provides that the Court
may also set aside an award if that is vitiated by patent illegality
appearing on the face of the award. This power of the Court is,
however, circumscribed by the proviso, which states that an award
shall not be set aside merely on the ground of an erroneous
application of the law or by reappreciation of evidence.
48. Explanation 1 to Section 34(2)(b)(ii), specifies that an arbitral
award is in conflict with the public policy of India, only if:
(i) the making of the award was induced or affected by fraud or
corruption or was in violation of Section 75 or Section 81; or
(ii) it is in contravention with the fundamental policy of Indian law;
or
(iii) it is in conflict with the most basic notions of morality or
justice.
49. In the instant case, there is no allegation that the making of the
award was induced or affected by fraud or corruption, or was in
violation of Section 75 or Section 81. Therefore, we shall confine
our exercise in assessing as to whether the arbitral award is in
contravention with the fundamental policy of Indian law, and/or
whether it conflicts with the most basic notions of morality or
justice. Additionally, in the light of the provisions of sub-section
(2-A) of Section 34, we shall examine whether there is any patent
illegality on the face of the award.
50. Before undertaking the aforesaid exercise, it would be apposite
to consider as to how the expressions:
(a) “in contravention with the fundamental policy of Indian law”;
(b) “in conflict with the most basic notions of morality or justice”;
and
(c) “patent illegality” have been construed.
In contravention with the fundamental policy of Indian law
51. As discussed above, till the 2015 Amendment the expression
“in contravention with the fundamental policy of Indian law” was
not found in the 1996 Act. Yet, in Renusagar Power Co.
Ltd. v. General Electric Co., 1994 Supp (1) SCC 644, in the
context of enforcement of a foreign award, while construing the
phrase “contrary to the public policy”, this Court held that for a
foreign award to be contrary to public policy mere contravention of
law would not be enough rather it should be contrary to:
(a) the fundamental policy of Indian law; and/or
(b) the interest of India; and/or
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 9 of 22
(c) justice or morality.
*****
55. The legal position which emerges from the aforesaid discussion
is that after “the 2015 Amendments” in Section 34(2)(b)(ii) and
Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
public policy of India” must be accorded a restricted meaning in
terms of Explanation 1. The expression “in contravention with the
fundamental policy of Indian law” by use of the word
“fundamental” before the phrase “policy of Indian law” makes the
expression narrower in its application than the phrase “in
contravention with the policy of Indian law”, which means mere
contravention of law is not enough to make an award vulnerable.
To bring the contravention within the fold of fundamental policy of
Indian law, the award must contravene all or any of such
fundamental principles that provide a basis for administration of
justice and enforcement of law in this country.
56. Without intending to exhaustively enumerate instances of such
contravention, by way of illustration, it could be said that:
(a) violation of the principles of natural justice;
(b) disregarding orders of superior courts in India or the binding
effect of the judgment of a superior court; and
(c) violating law of India linked to public good or public interest,
are considered contravention of the fundamental policy of Indian
law.
However, while assessing whether there has been a contravention
of the fundamental policy of Indian law, the extent of judicial
scrutiny must not exceed the limit as set out in Explanation 2 to
Section 34(2)(b)(ii).
*****
Patent illegality
65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
inserted by the 2015 Amendment, provides that an arbitral award
not arising out of international commercial arbitrations, may also
be set aside by the Court, if the Court finds that the award is visited
by patent illegality appearing on the face of the award. The proviso
to sub-section (2-A) states that an award shall not be set aside
merely on the ground of an erroneous application of the law or by
reappreciation of evidence.
66. In ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, while
dealing with the phrase “public policy of India” as used in Section
34, this Court took the view that the concept of public policy
connotes some matter which concerns public good and public
interest. If the award, on the face of it, patently violates statutory
provisions, it cannot be said to be in public interest. Thus, an award
could also be set aside if it is patently illegal. It was, however,
clarified that illegality must go to the root of the matter and if the
illegality is of trivial nature, it cannot be held that award is against
public policy.
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 10 of 22
67. In Associate Builders v. DDA, (2015) 3 SCC 49, this Court
held that an award would be patently illegal, if it is contrary to:
(a) substantive provisions of law of India;
(b) provisions of the 1996 Act; and
(c) terms of the contract [See also three-Judge Bench decision of
this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022)
2 SCC 275].
The Court clarified that if an award is contrary to the substantive
provisions of law of India, in effect, it is in contravention of
Section 28(1)(a) of the 1996 Act. Similarly, violating terms of the
contract, in effect, is in contravention of Section 28(3) of the 1996
Act.
68. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
15 SCC 131 this Court specifically dealt with the 2015
Amendment which inserted sub-section (2-A) in Section 34 of the
1996 Act. It was held that “patent illegality appearing on the face
of the award” refers to such illegality as goes to the root of matter,
but which does not amount to mere erroneous application of law. It
was also clarified that what is not subsumed within “the
fundamental policy of Indian law”, namely, the contravention of a
statute not linked to “public policy” or “public interest”, cannot be
brought in by the backdoor when it comes to setting aside an award
on the ground of patent illegality [See Ssangyong Engg. &
Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131]. Further, it
was observed, reappreciation of evidence is not permissible under
this category of challenge to an arbitral award [See Ssangyong
Engg. & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131].
Perversity as a ground of challenge
69. Perversity as a ground for setting aside an arbitral award was
recognised in ONGC Ltd. v. Western Geco International Ltd.,
(2014) 9 SCC 263. Therein it was observed that an arbitral decision
must not be perverse or so irrational that no reasonable person
would have arrived at the same. It was observed that if an award is
perverse, it would be against the public policy of India.
70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests
were laid down to determine whether a decision of an Arbitral
Tribunal could be considered perverse. In this context, it was
observed that where:
(i) a finding is based on no evidence; or
(ii) an Arbitral Tribunal takes into account something irrelevant to
the decision which it arrives at; or
(iii) ignores vital evidence in arriving at its decision, such decision
would necessarily be perverse.
However, by way of a note of caution, it was observed that when a
court applies these tests it does not act as a court of appeal and,
consequently, errors of fact cannot be corrected. Though, a possible
view by the arbitrator on facts has necessarily to pass muster as the
arbitrator is the ultimate master of the quantity and quality of
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 11 of 22
evidence to be relied upon. It was also observed that an award
based on little evidence or on evidence which does not measure up
in quality to a trained legal mind would not be held to be invalid on
that score.
71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
15 SCC 131, which dealt with the legal position post the 2015
Amendment in Section 34 of the 1996 Act, it was observed that a
decision which is perverse, while no longer being a ground for
challenge under “public policy of India”, would certainly amount to
a patent illegality appearing on the face of the award. It was
pointed out that an award based on no evidence, or which ignores
vital evidence, would be perverse and thus patently illegal. It was
also observed that a finding based on documents taken behind the
back of the parties by the arbitrator would also qualify as a decision
based on no evidence inasmuch as such decision is not based on
evidence led by the parties, and therefore, would also have to be
characterised as perverse [ See Ssangyong Engg. & Construction
Co. Ltd. v. NHAI, (2019) 15 SCC 131].
72. The tests laid down in Associate Builders v. DDA, (2015) 3
SCC 49 to determine perversity were followed in Ssangyong
Engg. & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131 and
later approved by a three-Judge Bench of this Court in Patel Engg.
Ltd. v. North Eastern Electric Power Corpn. Ltd., (2020) 7 SCC
167.
73. In a recent three-Judge Bench decision of this Court in DMRC
Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357,
the ground of patent illegality/perversity was delineated in the
following terms: (SCC p. 376, para 39)
“39. In essence, the ground of patent illegality is available
for setting aside a domestic award, if the decision of the
arbitrator is found to be perverse, or so irrational that no
reasonable person would have arrived at it; or the
construction of the contract is such that no fair or
reasonable person would take; or, that the view of the
arbitrator is not even a possible view. A finding based on
no evidence at all or an award which ignores vital
evidence in arriving at its decision would be perverse and
liable to be set aside under the head of “patent illegality”.
An award without reasons would suffer from patent
illegality. The arbitrator commits a patent illegality by
deciding a matter not within its jurisdiction or violating a
fundamental principle of natural justice.”
Scope of interference with an arbitral award
74. The aforesaid judicial precedents make it clear that while
exercising power under Section 34 of the 1996 Act the Court does
not sit in appeal over the arbitral award. Interference with an
arbitral award is only on limited grounds as set out in Section 34 of
the 1996 Act. A possible view by the arbitrator on facts is to be
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 12 of 22
respected as the arbitrator is the ultimate master of the quantity and
quality of evidence to be relied upon. It is only when an arbitral
award could be categorised as perverse, that on an error of fact an
arbitral award may be set aside. Further, a mere erroneous
application of the law or wrong appreciation of evidence by itself is
not a ground to set aside an award as is clear from the provisions of
sub-section (2-A) of Section 34 of the 1996 Act.
75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,
(2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court
held that courts need to be cognizant of the fact that arbitral awards
are not to be interfered with in a casual and cavalier manner, unless
the court concludes that the perversity of the award goes to the root
of the matter and there is no possibility of an alternative
interpretation that may sustain the arbitral award. It was observed
that jurisdiction under Section 34 cannot be equated with the
normal appellate jurisdiction. Rather, the approach ought to be to
respect the finality of the arbitral award as well as party's autonomy
to get their dispute adjudicated by an alternative forum as provided
under the law.”
19.
Having perused the limited contours of Section 34 of the A&C
Act, this Court proceeds further to examine the challenge raised by the
Petitioner pertaining to the finding of the learned Arbitrator in regard
to the Claim No. 10. The relevant extract of the Impugned Award
insofar as it pertains to the said claim, is reproduced herein below:
“Analysis and Reasons
53. As noted earlier, the first issue to be determined is whether the
Respondent is in breach of its contractual obligations under the
Tender dated 8th June 2020 together with the Corrigendum, the
Agreement dated 14th August 2020 and the subsequent WOs in
relation to:
(a) Kharif season of 2020-21 of Rajasthan;
(b) Kharif season of 2020-22 of Maharashtra;
(c) Rabi season 2020-21 of Maharashtra.
54. Appendix-l to the written submissions of the Claimant further
gives the breakup of the claims season-wise and state-wise. This
indicates that for Kharif 2022 of the 10,15,766 ILA surveys,
payment was made by the Respondent to the Claimant only in
respect of 2,59,292 ILA surveys. The reasons for non-payment in
respect of the remaining 7,56,474 ILA surveys involving an
amount of Rs. 23,57,81,229/- (including an interest amount of Rs.
4,66,62,729/-) were under two broad heads: (i) 'Submitted After
30.04.2023' and (ii) "Sub-survey issue". As far as ground (i) is
concerned, as many as 4,94,282 ILA surveys involving a sum of
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 13 of 22
Rs. 12,35,70,500/- were rejected only because they were
submitted after 30th April 2023.
Rejection of claims on account of the 30h April 2023 deadline
55. It has been the contention of the Claimant that the rejection of so
many ILA surveys for Kharif 2022, only on the ground that the
forms were submitted after 30th April 2023, was totally arbitrary,
particularly since a mere three-day advance intimation was given
by the Respondent to the Claimant in this regard.
56. The Tribunal has carefully examined the email dated 27th April
2023 sent by the Respondent to the Claimant which is at
Annexure-C-141 to the SoC. The subject matter of this
communication reads „Submission of Original Survey Form of
Kharif 2022 on or before 30th April 2023‟. The purport of this
letter appears to be that the Claimant, had despite of several
reminders by the Respondent submitted only partial survey forms
(approximately 3,38,000) and photographs of the ILA surveys
conducted under the PMFBY Kharif 2022 season. It further states
that the District Authorities were repeatedly asking the
Respondent to submit the survey forms. Thereafter, it states that
the Claimant should submit all the remaining forms along with
photographs on or before 30th April 2023 failing which the
unsubmitted forms/ photographs will not be considered for
payment'.
57. In response to the above mail, the Claimant replied on 27th April
2023, pointing out that of the 10,15,766 ILAs conducted by the
Claimant in nine districts of Maharashtra during Kharif 2022,
hard copies of 3,37,495 ILA surveys had in fact been submitted to
the Respondent. The Claimant stated that it was not possible for it
to submit the balance of more than 6lakh ILA survey forms, in
hard copies, by 30th April 2023. It referred to an earlier email of
31st January 2023, setting out the reasons why it will take another
three to four months to submit all the forms.
58. A perusal of the emails of 31st January 2023, sent by the Claimant
to the Respondent refers to the demand sent by the Mumbai RO
of the Respondent that all the loss assessment forms of a Tehsil
should be submitted in a "single lot' only. It was explained by the
Claimant that sorting out of ILA forms „100% Tehsil-wise' before
their despatch would not be possible' as this will further severely
delay the whole process as explained above'. In a separate email
of the same date, the Claimant informed the Respondent that it
would take around three to four months for completion of the
collection, sorting, labeling and dispatch of the entire lot of over
ten lakh survey forms as proposed by you'. It is further pointed
out that the Respondent had not made any payment to the
Claimant for the completed WOs since September, 2022. The
Claimant accordingly informed the Respondent, in the said email
dated 31st January 2023 that it is not possible 'to collect all the
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 14 of 22
forms pertaining to even one WO'. It was stated further that as
and when the Respondent released payments, the Claimant will
'pay the field staff and collect the balance ILA forms'.
59. In the email of 27th April 2023, the Claimant pointed out that at the
meeting held on 19th January 2023, it had been agreed that the
Respondent would release payments immediately on submission
of hard copies of ILA survey forms. The Claimant further pointed
out that they had been submitting ILA survey consignments since
6th March 2023, but had received the Respondent's first net
interim remittance of Rs. 1,09,60,135/- (including GST) only on
21st April 2023. It was the delay in making the payments that had
in turn delayed the collection of the forms from the field
surveyors. The other reason was the insistence by the RO of the
Respondent in Mumbai that the surveys had to be sorted village-
wise. Accordingly, the Claimant pleaded to the Respondent that
while it was making every effort to submit the balance forms, as
early as possible, in view of the circumstances explained it is
difficult to submit the remaining more than six lakh forms before
10th June 2023'.
60. However, from the email dated 27th April 2023 of the Respondent
to the Claimant, it appears that the Respondent was insisting on
the 30th April 2023 deadline and took the stand that "no further
extension of time for submission will be allowed.' The Claimant's
email of 29th April 2023 to the Respondent reveals the insistence
by the Respondent that the Claimant should sort over ten lakh
ILA forms, village-wise, was indeed a deviation from the standard
procedure which was to deliver the ILA forms to the Respondent
"WO wise'. By an email dated 31st January 2023, the Claimant
pointed this out to the Respondent and reminded that this task
would take around three to four months and that it had resulted in
the Claimant having to create additional infrastructure/
manpower, whereby, the Claimant had to incur substantial losses.
The 2nd May 2023 response of the Regional Manager of the
Respondent at Mumbai to the Claimant was extremely curt and
cryptic stating that "forms submitted before 30th April 2023 will
only be considered for payment. Clearly, therefore, there was a
kind of an impasse created.
61. On the above aspect, a pointed question was put by counsel for the
Claimant to the witness for the Respondent (RW-1) during cross-
examination as under:
"Q19 Would you agree that it is only by your email dated
27.04.2023, referred to in para 54 of your affidavit, that you
informed the Respondent for the first time that the deadline
for submission of hard copies of the ILA Forms
Ans. Yes. Volunteered: In an earlier email dated
31.01.2023 of the Claimant, it was stated that it would take
them three to four months to complete the task"
62. In other words, there is a clear admission that prior to the email
Digitally Signed
By:NEERU
Signing Date:05.05.2026
18:23:53
Signature Not Verified
OMP (COMM.) 380/2025
Page 15 of 22
dated 27th April 2023, there was no intimation by the Respondent
to the Claimant that 30th April 2023 was the inviolable deadline
for submission of the ILA forms. How this deadline was arrived
at is not even attempted to be explained by the Respondent either
in its SoD or even in the affidavits of evidence of the
Respondent's two witnesses.
63. In the written submissions tendered by the Respondent, the line
adopted by RW-1 in his above response, is sought to be reiterated
viz. that the Claimant had itself conveyed by an email dated 31st
January 2023 that it will take three to four months to dispatch the
entire lot of forms. This could not by any stretch of imagination
be construed as the Claimant having bound itself to a deadline of
30th April 2023. Apart from saying that the Claimant had been
given sufficient amount of time' the Respondent does not appear
to have any valid explanation for rejecting such a huge number of
ILA survey forms for payment only because they were not
submitted before 30th April 2023, which deadline is not found
anywhere in the Tender document/conditions or in the Agreement
dated 14th August 2020.
64. Reference could also be made at this juncture to the Minutes of
Meeting held on 3rd March 2023, 24th March 2023 and 5th April
2023 (Annexures R-24, R-25 and R-26 to the SoD). During these
meetings, the Respondent did not insist on any deadline of 30th
April 2023 by which the ILA survey forms in hard copy were
required to be submitted by the Claimant to the Respondent. This
is not even adverted to in the meeting held on 22nd May 2023.
65. Interestingly, it is nowhere denied by the Respondent that as of
2nd April 2023, more than six lakh forms were still to be
submitted by the Claimant to the Respondent. The Claimant had
in its emails of 31st January 2023 to the Respondent, referred to
hereinabove, given adequate reasons about the difficulty in
collecting and submitting the ILA survey forms. This has not been
refuted by the Respondent in its reply emails. In fact, those replies
which rejected the earnest appeal of the Claimant for extension of
the deadline, for submission of the ILA survey forms, were met
with a curt one-line reply of the Respondent that there would be
no extension of the deadline of 30th April 2023. In other words,
the Respondent was not even prepared to consider the reasons
being offered by the Claimant as to why the insistence upon a 30th
April 2023 deadline, imposed on 27th April 2023, for submission
of six lakh ILA survey forms, was both unfair and unrealistic.
66. Turning to the Tender itself, the specific clauses that might be
relevant for the issue are the following:
“4.21.2 Payment shall be released after receipt of
satisfactory reports as specified by AIC in desired formats
in conformity with scope of work specified and compliance
with the terms/ conditions/ requirements under Tender
document/ Work Order. OMP (COMM.) 380/2025
4.21.3 Agency shall submit the reports in the formats as desired by AIC in the mode (Offline/Online) as specified in the work order. On verification of the reports, AIC will approve the eligible surveys as per the terms and conditions of the work order / Tender document for the payment. Thereafter, Agency may raise the Invoice for payment. 4.21.4 Incomplete report / non submission / partial submission of specified documents, photos, videos etc. will not be considered for payment. 4.21.6 No Payment shall be made in the following cases. a. Less than 50% of the work order of each activity is completed. b. Less than 50% of the total assigned survey / CEs conducted in each notified area crop combination. For this purpose, the CCEs conducted without intimation would not be included provided the agency raised valid objections for those CCEs. c. Merely "submitting the report as per the formats provided " without performing the awarded work or merely Yield data collection or CCEs report submission without co-observing the CCEs or merely present during CCEs and submitting duly filled CCE co-observation form. d. The surveys are not conducted as specified in the Scope of Work and operational guidelines of the prevailing PRBY/RWBCIS Other Crop Insurance products guidelines and IRDAI regulations in force."
67.Even the Claimant does not dispute the requirements, spelt out under the above clauses. The reason why the Respondent rejected as many as 4,94,282 ILA survey forms for the Kharif 2022 for Maharashtra was only because they were not submitted before the deadline of 30th April 2023. That is not even a condition spelt out in any of the above clauses.
68.Having considered the relevant clauses of the Agreement (including clauses in the Tender and the Corrigendum thereto), the evidence on record in its totality and the submissions of learned counsel for the parties, the Tribunal concludes that there was no justification whatsoever factually or legally for the Respondent to have denied payment in respect of 4,94,282 ILA survey forms for the Maharashtra Kharif 2022 season involving payment of Rs. 12,35,70,500/-. Accordingly, the Tribunal holds that the aforementioned sum is due and liable to be paid by the Respondent to the Claimant forthwith together with the interest as prayed for by the Claimant.”
20.This Court has carefully perused the aforesaid findings of the OMP (COMM.) 380/2025
learned Arbitrator as well as the material placed on record. A reading of the Impugned award demonstrates that the learned Arbitrator has undertaken a detailed examination of the contractual provisions, the correspondence exchanged between the parties, and the evidence led during the proceedings.
21.The learned Arbitrator, upon due consideration, has returned a categorical finding that the rejection of the ILA survey forms on the ground of the alleged deadline of 30.04.2023 was unjustified. In support of the said conclusion, the learned Arbitrator has, inter alia, noted that the said deadline was introduced for the first time by way of an email dated 27.04.2023, that no such stipulation finds place in the contractual documents, and that the same was not reflected in any of the meetings held prior thereto.
22.In the backdrop of the aforesaid findings, the contention of the Petitioner, premised on the communication dated 07.08.2023, also does not merit acceptance. The said communication, when read in the context of the dispute as examined by the learned Arbitrator, does not advance the case of the Petitioner.
23.At this juncture, it is also pertinent to note that the learned Arbitrator has consciously adverted to and examined the said communication. The relevant extract of paragraph 107 of the Impugned Award, wherein the learned Arbitrator has specifically considered the said communication, is reproduced herein below for ready reference: "107. The clauses as they read do appear to favour the interpretation placed on them by the Respondent. The clauses do not require the Respondent to furnish to the Agency, the reasons for rejecting surveys or reports. In its written submissions, a pointed reference is made by the Respondent to the admission by CW-1 in his cross-examination on 5th September 2024 that the Claimant had OMP (COMM.) 380/2025
sent the email dated 7th August 2023. A perusal of that email would show that the Claimant thanked the Respondent for the payment against the invoices dated 18th July 2023. Although, the Claimant did ask for the details of the ILA surveys rejected, it really did not insist on the reasons for the rejection, much less raised the protest that it was accepting the said position and raising invoices only for the approved surveys due to financial constraints. The Respondent is right in its contention that it is not the case of the Claimant that it was coerced or pressurized by the Respondent into accepting the rejection of a large number of its reports / surveys / CCEs."
24.A reading of the aforesaid paragraph indicates that the learned Arbitrator has not only adverted to the communication dated 07.08.2023 but has also examined its contents in the course of its analysis and therefore, mere observation, that the Respondent did not insist upon the reasons for rejection of the surveys or raise an emphatic protest cannot, by itself, in the facts of the present case, be construed as an unconditional and unequivocal acceptance of the rejection of the surveys as final and binding.
25.In the considered opinion of this Court, the absence of protest by the Respondent in the said communication, in the facts and circumstances of the present case, is not synonymous with acceptance of the settlement.
26.It is a well-settled proposition of law that, for a plea of full and final settlement to be sustained and for an estoppel to arise therefrom, there must exist a clear, conscious, and unequivocal agreement between the parties. Such an agreement must be bilateral in nature and must demonstrably reflect a meeting of minds, whereby the payment tendered is expressly accepted by the receiving party as being in complete and final discharge of all subsisting claims, without any protest, demur, reservation, or indication to the contrary.
27.In the absence of such clear and unambiguous acceptance, a OMP (COMM.) 380/2025
mere reference to an expression “full and final settlement” in an email trail, by itself, cannot be construed as evidencing a concluded and binding agreement. In the considered opinion of this Court, such a reference, without any demonstrable meeting of minds or unequivocal consent of the parties, is insufficient to establish that a binding settlement has come into existence.
28.In the present case, the communication dated 07.08.2023, also examined by the learned Arbitrator in paragraph 107 of the Impugned Award, falls far short of satisfying the aforesaid legal threshold of a concluded and binding settlement. The contents of the said communication neither evidence any unequivocal acceptance of the payment as being in full and final satisfaction of claims nor disclose any conscious relinquishment of rights by the Respondent. In view thereof, it cannot, by any stretch of imagination, be construed as giving rise to an estoppel so as to preclude the Respondent from raising disputes or asserting its claims arising therefrom.
29.Consequently, the reliance placed upon Nathani Steels Ltd. (supra) by the learned Senior Counsel for the Petitioner to contend that once payment is accepted in full and final discharge extinguishes any arbitrable dispute, does not merit acceptance in the facts of the present case. As the principle laid down therein proceeds on the existence of a clear, unequivocal and bilateral settlement between the parties, without any reservation or protest. However, in the present case, the contemporaneous conduct of the Respondent, as borne out from the material on record, does not evince the existence of any such settlement that transpired inter se the parties.
30.Insofar as the contention regarding the alleged non- consideration or inadequate weight accorded to the communication OMP (COMM.) 380/2025
dated 07.08.2023 in the adjudication of Claim No. 10 by the learned Arbitrator is concerned, it is well settled that an arbitral award is not required to expressly advert to or discuss each and every document placed on record. It is sufficient if the award, on a holistic reading, reflects due application of mind to the material issues arising for consideration and demonstrates that the Arbitrator has taken into account the substance of the dispute and the evidence placed before it.
31.In this regard, reference may be made to the judgment of the Division Bench of this Court in Delhi Transco Limited v. Hindustan Urban Infrastructure Limited6, wherein, upon placing reliance on the decision of the Hon‟ble Supreme Court in Board of Mining Examination and Chief Inspector of Mines v. Ramjee7, it was held that an Arbitral Tribunal is not required to deal with every contention or submission in a mechanical or pedantic manner. Rather, it is sufficient if the authority addresses those issues which are material and have a direct bearing on the outcome of the dispute. Consequently, an Arbitral Tribunal is not obligated to advert to each and every document or contention placed on record. It is well within its juri iction to confine its analysis to those aspects which are germane and central to the controversy, so long as the essential issues in dispute stand duly considered and adjudicated.
32.In the present case, the Impugned Award, when read as a whole, clearly demonstrates that the learned Arbitrator by diligently examining the chain of correspondence, including the emails dated 31.01.2023 and 27.04.2023, the responses thereto, the Minutes of Meetings held on various dates, and the relevant contractual clauses
6 2025:DHC:8941-DB 7 (1977) 2 SCC 256 OMP (COMM.) 380/2025
governing payment obligations has duly applied its judicious mind to the core issues arising between the parties and has rendered findings based on the material available on record. The learned Arbitrator has also taken note of the statement of RW-1 in cross-examination that the deadline of 30.04.2023 was communicated for the first time by way of the email dated 27.04.2023. 33. The conclusion arrived at by the learned Arbitrator, namely, that the rejection of the ILA survey forms solely on the basis of a deadline which was neither contractually stipulated nor communicated in advance was justified, does not warrant interference. Consequently, the mere absence of a specific reference to the communication dated 07.08.2023 in regard to Claim No. 10 in the Impugned Award does not, in the facts and circumstances of the present case, vitiate the Award.
34.Upon a careful examination of the record, including the documentary evidence and the email correspondence exchanged between the parties, the learned Arbitrator has arrived at a reasoned
conclusion which is borne out by and in consonance with the material on record. Having regard to the limited scope of juri iction under Section 34, this Court finds that the contentions advanced by the Petitioner do not merit acceptance and are accordingly rejected.
DECISION:
35.In view of the foregoing, this Court is of the considered opinion that the limited challenge raised by the Petitioner in the present Petition does not fall within the narrow confines of interference contemplated under Section 34 of the A&C Act. The findings returned by the learned Arbitrator are founded upon a due and proper OMP (COMM.) 380/2025
appreciation of the material on record, represent a plausible and reasonable view, and do not suffer from any patent illegality or perversity so as to warrant interference by this Court in exercise of its juri iction under Section 34. 36. Accordingly, the present Petition, along with pending Application(s), if any, stands dismissed.
HARISH VAIDYANATHAN SHANKAR, J. APRIL 28, 2026/v/jk