M/S National Highways Authority Of INDIA vs. M/S Oriental Structural Engineers PVT LTD
Held
The Court held that the Petitioner had not demonstrated any patent illegality or perversity in the Arbitral Tribunal's award concerning Claim No. 1. The Tribunal's findings on the attribution of delay and the Respondent's contractual entitlement were reasoned and based on the material before it. The methodology for quantification was also found to be not arbitrary or contrary to the contract. Regarding Claims 3 and 4, the Court held that the Tribunal had finally determined the Respondent's entitlement and laid down the basis for quantification, leaving only a ministerial exercise of verification and certification to the Engineer. This was considered a valid declaratory award, not requiring specific quantification within the award itself. The Court found no merit in the challenge to the award of interest, noting it was awarded only for the pendente lite period and was supported by Clause 60.8 of the Contract. The Court concluded that the Petitioner's challenge was essentially an attempt to re-appreciate the contract terms and evidence, which is beyond the scope of Section 34 of the Arbitration and Conciliation Act, 1996. The Tribunal's view was deemed possible and plausible.
Facts
The Petitioner, National Highways Authority of India (NHAI), filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an Arbitral Award dated July 12, 2012. The award arose from disputes related to a contract dated March 26, 2002, for the four-laning and strengthening of a highway in Uttar Pradesh. The Respondent, Oriental Structural Engineers Pvt Ltd, was the successful bidder. The disputes concerned claims for compensation due to contract prolongation, reimbursement of additional expenses due to Service Tax and Education Cess, and separate payment for "filler type expansion joints". The Arbitral Tribunal partly allowed claims 1, 3, and 4, awarding a sum of Rs. 45,88,91,806/- with interest for Claim 1, and directing verification for amounts under Claims 3 and 4. The Petitioner challenged the award, arguing it was perverse and illegal.
Key Issues
1. Whether the Arbitral Tribunal's award of Rs. 45,88,91,806/- with interest under Claim No. 1 for prolongation costs, based on its findings regarding delay attribution and contractual entitlement, suffers from patent illegality or perversity, warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996. 2. Whether the Arbitral Tribunal's determination of the Respondent's entitlement to reimbursement of additional expenses for Service Tax and Education Cess (Claim No. 3) and separate payment for "filler type expansion joints" (Claim No. 4), by leaving the quantification to the Engineer's verification, is a valid declaratory award that does not require specific quantification within the award itself, and if such an award is amenable to execution. Petitioner's arguments: The Petitioner contended that the Arbitral Award suffered from patent illegality and perversity, particularly concerning the quantification of damages under Claim No. 1 and the nature of the awards under Claims 3 and 4, which they argued were not final adjudications. They also challenged the award of interest. Respondent's arguments: The Respondent argued that the Tribunal had made reasoned findings on delay and entitlement, and the methodology for quantification was not arbitrary. They contended that the awards under Claims 3 and 4 were valid declaratory awards, leaving only ministerial acts for quantification, and that the interest awarded was justified under the contract and law.
Sections Cited
Section 34
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
JUDGMENT %
2026
The present petition is filed under Section 34 of the Arbitration and Conciliation Act, 19961 assailing the Arbitral Award2 dated 12.07.2012 passed by a three-member Tribunal in disputes arising out of Contract dated 26.03.20023. 2. The disputes between the parties arise out of a contract awarded by the National Highways Authority of India4 for Four-Laning and 1 “the Act”, hereinafter 2 “impugned award”, a
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Delhi High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.