M/S Precision Infratech Private Limited vs. The State Of Andhra Pradesh
Held
The Court held that it should not interfere in technical matters like tender evaluations unless there is gross arbitrariness or mala fide intent. The Court found that the petitioner did not meet the eligibility criteria even before Corrigendum-3 was issued.
Facts
The petitioner challenged a tender process where new eligibility criteria were introduced via Corrigendum-3 after the petitioner had submitted its bid. The petitioner's bid was subsequently rejected based on these new criteria, and the contract was awarded to the 5th respondent.
Key Issues
Whether the introduction of new eligibility criteria after bid submission is permissible and whether the petitioner's bid was rightly rejected based on the tender conditions.
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
The Court made the following common order:
The case of the petitioner is that, pursuant to the G.O.Rt.No.339 dated 30.06.2025, the Superintending Engineer (3rd respondent) issued a Tender Document E-Procurement Notice Inviting Tender NIT No.19/2025-26, dated 09.01.2026 inviting bids for execution of "Repairs, Servicing and replacement
2
of Mechanical and Electrical Components on four arms and embankments of Sir Arthur Cotton Barrage", and the eligibility criteria relates to experience in executing similar works, minimum financial turnover and Technical
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Andhra Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.