Cause title — parties, addresses and appearances
APHC010233142024
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3331]
WEDNESDAY, THE 8th DAY OF JULY 2026
PRESENT
THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 11999/2024
Between:
1. M. RAMANAIAH, S/O. M. VENKATAIAH, AGED ABOUT 57 YEARS,
OCC. CONTRACTOR, R/O.D.NO. 5-107, YEKARAKUKNTAPALLI,
NALLA CHERLOPALLI, MUDGUBBA MANDAL, ANANTAPURAMU
DISTRICT.
...PETITIONER
AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY
(IRRIGATION
DEPARTMENT),
SECRETARIAT
BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT.
2. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY
(
FINANCE
DEPARTMENT)
SECRETARIAT
BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT.
3. THE
ENGINEERINCHIEF
IRRIGATION,
WATER
RESOURCES
DEPARTMENT, VIJAYAWADA. KRISHNA DISTRICT.
4. THE
SUPERINTENDENT
ENGINEER,
WATER
RESOURCES
DEPARTMENT,
IRRIGATION
CIRCLE
ANANTAPUR,ANANTAPURDISTRICT.
5. THE EXECUTIVE ENGINEER, WATER RESOURCES DEPARTMENT,
I.B DIVISION, PENUKONDA, ANANTAPUR DISTRICT.
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased to issue a Writ, order or direction more particularly one in the nature
of Writ of Mandamus declaring the action of the Respondents in not returned
Page 2 of 4
the EMDs and FSDs along with GST total and also not paying the interest in
respect of works done by the Petitioner from the date of submitting bill to final
payment payable to the petitioner in relation to the execution of works under
the schem of Neeru Chettu i.e vide Agreement No.186 SEA /2017-2018,
dated 26-10-2017, Agreement No.63 SEA /2018- 2019, dated 21-06-2018,
Agreement No.61 SEA /2018-2p19, dated 21-06- 2018, Agreement No.62
SEA/2018-2019, dated 21-06-2018, Agreement No.99 SEA/2018-2019, dated
12-07-2018, 39/2018-2019 and Agreement No.20-12- 2018, 40/2018-19,
dated 20-12-2018 as illegal, arbitrary, violation of principles of natural justice,
violation of Articles 14, 19(1)(g) and 21 of the Constitution of India and also
violation of G.O.R.T No. 266 dated 15-02-2021 ad Memo No 1279341/FMU-
WR. 1/2020 dated 18-02-2021 and violation of Orders passed by this Hon'ble
Court in W.A No. 724 of 2021 and consequently direct the Respondents to
return the EMDs and FSDs along with interest @ 6 percent per annum from
the date of submitting bill to final payment and to pass
IA NO: 1 OF 2024
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased to
direct the Respondents to return the EMD's and FSD's along with interest @
6% per annum from the date of submitting bill to final payment for the
Agreement No. 186 SEA /2017-2018, dated 26-10-2017 Agreement No.63
SEA/2018-2019, dated 21-06-2018, Agreement No.61 SEA /2018-2019,
dated 21-06-2018, Agreement No.62 SEA /2018-2019, dated 21- 06-2018,
Agreement No.99 SEA/2018-2019, datedi2-07-2018, 39/2018-2019 and
Agreement No.20-12-2018, 40/2018-19, dated 20-12-2018, pending disposal
of the above writ petition and pass
IA NO: 1 OF 2025
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased to
receive/ permit the counter copies on record by granting leave to the
Respondent in the above Writ Petition and pass
Counsel for the Petitioner:
1. BANDI SRIHARI
Page 3 of 4
Counsel for the Respondent(S):
1. GP FOR FINANCE PLANNING
2. GP FOR IRRIGATION COMM AREA DEV
The Court made the following:
The above writ petition was filed to declare the action of the respondents in not returning the EMD and F amount along with GST and not paying interest, in relation to the works executed by the petitioner, as illegal and arbitrary.
2.Today, when the matter is taken up for consideration, Ms. Shaik Thabasum, learned counsel representing Sri Bandi Srihari, learned counsel for the petitioner submitted that pending the writ petition, amount has been paid to the petitioner and hence, nothing survives for adjudication, in this writ petition.
___________________________ JUSTICE SUBBA REDDY SATTI Date: 08.07.2026 IKN Whether the order is : Speaking Yes/No / Reasoned Yes/No Reportable Yes/No / Non-Reportable Yes/No THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI