M/S.Biswal Construction Co. vs. State Of Odisha

WP(C)/16821/2018HC OrissaGSTCNR ODHC01049856201812 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work executed after the implementation of GST, for contracts tendered before July 1, 2017. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised Schedule of Rates (SoR-2014), adjusting it by the tender premium/discount, and then adding the applicable GST. If the revised GST-inclusive work value is higher than the original agreement work value for the balance work, the contractor is to be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority would consider and dispose of in light of the revised guidelines dated December 10, 2018, preferably by March 31, 2019. No coercive action was to be taken against the petitioner until March 31, 2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of a Finance Department Memorandum dated December 7, 2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The State submitted revised guidelines issued on December 10, 2018, superseding the earlier memorandum, which provided a procedure for determining the amount payable to works contractors for balance work executed after GST implementation.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? Petitioner's contention: The petitioner argued that the introduction of GST created an additional tax burden not contemplated in the original agreements, thus necessitating reimbursement of the differential tax amount. The petitioner challenged the initial guidelines that did not adequately address this issue. Revenue's contention: The Revenue submitted revised guidelines issued on December 10, 2018, which provided a mechanism for calculating and reimbursing the differential tax amount for balance work executed post-GST implementation. The Revenue relied on these revised guidelines as the basis for addressing the petitioner's grievance.

Sections Cited

Section 73, Section 129, Rule 86A

AI-generated summary — verify with the full judgment below

03.

12.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.