Pyari Mohan Pradhan vs. State Of Odisha,Commissioner Cum Secretary ,Water Resourse Deptt

WP(C)/16814/2018HC OrissaGSTCNR ODHC01049845201812 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines provide a detailed procedure for determining the GST-inclusive work value for the balance work executed after the implementation of GST, particularly for contracts tendered before July 1, 2017. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised Schedule of Rates (SoR-2014), adjusting for tender premium/discount, and then adding the applicable GST. The guidelines stipulate that if the revised GST-inclusive work value for the balance work exceeds the original agreement work value for that balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority, who would consider and dispose of it in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by March 31, 2019. The petitioner was granted liberty to challenge the authority's decision if aggrieved. No coercive action was to be taken against the petitioner until March 31, 2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance stemmed from the petitioner being required to pay GST on contracts entered into before the GST regime, where such tax was not initially envisaged. The State submitted revised guidelines issued on December 10, 2018, superseding the earlier memorandum.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? The petitioner argued that the introduction of GST resulted in an unforeseen tax liability on contracts awarded before the GST regime, impacting their financial position. They contended that the initial guidelines were insufficient to address this disparity. The revenue, represented by the Additional Government Advocate, submitted that revised guidelines were issued on December 10, 2018, which provide a mechanism for determining the GST-inclusive work value for balance work executed after the GST implementation. These guidelines aim to address the concerns raised by contractors regarding the differential tax burden.

Sections Cited

Section 73, Section 129, Rule 86A

AI-generated summary — verify with the full judgment below

03.

12.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.