Gopal Chandra Sahu vs. State Of Odisha

WP(C)/15570/2018HC OrissaGSTCNR ODHC01046591201812 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court acknowledged that the issue pertained to difficulties faced by contractors due to the change in tax regime for works contracts under GST. The revenue/State presented revised guidelines dated December 10, 2018, which superseded the earlier memorandum dated December 7, 2017. These revised guidelines established a procedure for calculating the GST-inclusive work value for the balance work executed after June 30, 2017, based on the original agreement rates and the revised Schedule of Rates (SoR-2014). The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for that balance portion, the works contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, which the authority was to consider and dispose of in light of the revised guidelines dated December 10, 2018, preferably by March 31, 2019. The Court also ordered that no coercive action would be taken against the petitioner until March 31, 2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (revenue/State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The revenue/State submitted revised guidelines issued on December 10, 2018, superseding the earlier memorandum, which provided a procedure for calculating and reimbursing the differential GST amount for works contracts tendered before July 1, 2017, but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter, under the provisions of the GST regime. Petitioner's contention: The petitioner argued that due to the introduction of GST, they are required to pay taxes that were not contemplated at the time of entering into the agreements, leading to a financial burden. They sought reimbursement of this additional tax liability. Revenue/State's contention: The revenue/State submitted revised guidelines dated December 10, 2018, which provide a mechanism for determining and reimbursing the differential GST amount for such contracts. They relied on the said revised guidelines to address the petitioner's grievance.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

02.

12.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.