Held

The Court noted that the State Government had issued revised guidelines on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines provide a detailed procedure for determining the GST-inclusive work value for the balance work executed after the implementation of GST. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised Schedule of Rates – 2014, adjusting for tender premium/discount, and then adding the applicable GST rate. The guidelines stipulate that if the revised GST-inclusive work value for the balance work is more than the original agreement work value, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, as expeditiously as possible, preferably by March 31, 2019. No coercive action is to be taken against the petitioner until March 31, 2019. The writ petition was disposed of with liberty to challenge the authority's decision if the petitioner remains aggrieved.

Facts

The petitioner, a works contractor, challenged the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) with effect from July 1, 2017. The petitioner also sought to quash Clause 1(iii) of a Finance Department Memorandum dated December 7, 2017. The grievance was that the introduction of GST required the petitioner to pay tax not envisaged in the original agreement. The State submitted revised guidelines dated December 10, 2018, superseding the earlier memorandum, which provided a procedure for determining the amount payable to works contractors for balance work executed after the GST implementation.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? The petitioner argued that due to the introduction of GST, they are obligated to pay taxes that were not contemplated when the agreements were finalized, leading to a financial burden. They sought reimbursement of this additional tax liability. The revenue (State) contended that revised guidelines have been issued by the Finance Department on December 10, 2018, which address the issue of works contracts under GST. These guidelines provide a mechanism for calculating the GST-inclusive work value for balance work and determine whether reimbursement or recovery is due. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.

AI-generated summary — verify with the full judgment below

03.

12.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.