M/S.Nabadurga Construction PVT.LTD. vs. State Of Odisha
Held
The Court noted that the State had issued revised guidelines on 10.12.2018, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work executed after 01.07.2017, where tenders were invited prior to that date. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value, the contractor would be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment made would be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated 10.12.2018, as expeditiously as possible, preferably by 31.03.2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until 31.03.2019. The writ petition was disposed of with these directions.
Facts
The petitioner, a works contractor, filed a writ petition challenging the opposite parties' refusal to reimburse the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. The grievance stemmed from the GST liability on works contracts entered into before the GST regime but executed partly or wholly after its implementation. The State submitted revised guidelines issued on 10.12.2018, superseding the earlier memorandum, which provided a procedure for determining the GST-inclusive work value for balance work.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts executed partly or wholly after 01.07.2017, where tenders were invited prior to this date. 2. Whether Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017 is liable to be quashed. Petitioner's Contention: The petitioner argued that they are required to pay GST on works contracts which was not envisaged at the time of entering into the agreement, leading to a financial burden. They sought reimbursement of this additional tax liability. Revenue's Contention: The State submitted revised guidelines dated 10.12.2018, which provided a mechanism for calculating and reimbursing the differential GST amount for balance work executed after the GST implementation. The State implicitly argued that the revised guidelines address the petitioner's grievance.
Sections Cited
Not specified in the judgment
AI-generated summary — verify with the full judgment below
12.12.2018
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.