Bharat Jena vs. Odisha State Rural Road Agency
Held
The Court noted that the State had issued revised guidelines on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines provide a comprehensive procedure for determining the GST-inclusive work value for the balance portion of works contracts where tenders were invited before July 1, 2017, but execution extended beyond that date. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised Schedule of Rates (SoR-2014), adjusting for tender premium/discount, and then adding the applicable GST rate. The guidelines stipulate that if the revised GST-inclusive work value for the balance work exceeds the original agreement value, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority within four weeks, which the authority must consider and dispose of in light of these revised guidelines, preferably by March 31, 2019. The Court also stated that if the petitioner is aggrieved by the authority's decision, they can challenge it. No coercive action is to be taken against the petitioner until March 31, 2019. The issue of quashing Clause 1(iii) of the earlier memorandum is rendered moot by the issuance of the revised guidelines.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding the earlier memorandum, to address issues related to works contracts under GST for tenders invited before July 1, 2017, but executed partly or wholly after that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed thereafter? The petitioner argued that they are required to pay tax under the GST regime which was not contemplated at the time of entering into the agreements, leading to a financial burden. The petitioner relied on the grievance that the original agreements were based on the pre-GST tax structure. The State contended that revised guidelines have been issued to address such situations. The State presented the Finance Department's Office Memorandum dated December 10, 2018, which provides a procedure for determining the GST-inclusive work value for the balance work and reimbursement or recovery of excess amounts. The State implicitly argued that the revised guidelines offer a mechanism for resolving the petitioner's grievance.
Sections Cited
Section 1(iii) of the Finance Department Memorandum dated 07.12.2017, Office memorandum No. FIN-CTI-TAX-0045-2017/38535/F Dated 10.12.2018
AI-generated summary — verify with the full judgment below
12.12.2018
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.