M/S.Biswal Construction Co. vs. State Of Odisha

WP(C)/16822/2018HC OrissaGSTCNR ODHC01049857201812 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on 10.12.2018, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provided a mechanism for determining the GST-inclusive work value for the balance portion of works contracts executed after 01.07.2017, where tenders were invited prior to that date. The procedure outlined in the revised guidelines allows for reimbursement to the works contractor if the revised GST-inclusive work value for the balance work is more than the original agreement work value for that balance work. The Court directed the petitioner to make a comprehensive representation before the appropriate authority, ventilating their grievance in light of these revised guidelines. The authority was directed to consider and dispose of the representation expeditiously, preferably by 31.03.2019. The Court also stated that if the petitioner remained aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until 31.03.2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner also sought to quash Clause 1(iii) of a Finance Department Memorandum dated 07.12.2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The State submitted revised guidelines dated 10.12.2018, superseding the earlier memorandum, to address issues related to works contracts under GST for tenders invited before 01.07.2017 but executed partly or wholly after that date.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before 01.07.2017 but executed thereafter? (Question of law) Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an additional tax burden that was not contemplated at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. They challenged the initial memorandum that did not provide for such reimbursement. Revenue's Contention: The Revenue (State) submitted revised guidelines issued on 10.12.2018, which provided a procedure for determining the GST-inclusive work value for the balance work executed after 01.07.2017. These guidelines stipulated that if the revised GST-inclusive work value exceeded the original agreement work value, the contractor would be reimbursed for the excess amount. The Revenue relied on these revised guidelines.

Sections Cited

Section 73, Section 129, Rule 86A

AI-generated summary — verify with the full judgment below

03.

12.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.