M/S.Biraja Construction vs. State Of Odisha

WP(C)/16871/2018HC OrissaGSTCNR ODHC01050003201812 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court noted that the State had issued revised guidelines on December 10, 2018, which superseded the earlier memorandum dated December 7, 2017. These revised guidelines provided a comprehensive procedure for determining the GST-inclusive work value for the balance work in cases where tenders were invited before July 1, 2017, but payments were made after the implementation of GST. The guidelines stipulated that if the revised GST-inclusive work value for the balance work was more than the original agreement work value for the balance work, the works contractor was to be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by March 31, 2019. The Court also stated that if the petitioner was aggrieved by the authority's decision, they could challenge it. No coercive action was to be taken against the petitioner until March 31, 2019.

Facts

The petitioner, a works contractor, filed a writ petition challenging the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the introduction of GST necessitated paying tax not originally envisaged in the agreements. The State submitted revised guidelines issued on December 10, 2018, superseding the earlier memorandum, which addressed the issue of works contracts under GST for tenders invited before July 1, 2017, but executed thereafter.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly after that date? 2. Whether Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017, which allegedly prevented such reimbursement, is liable to be quashed? Petitioner's Contention: The petitioner argued that due to the introduction of GST, they are required to pay taxes that were not contemplated when the agreements were finalized, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue's Contention: The Additional Government Advocate submitted that the Government had issued revised guidelines on December 10, 2018, in supersession of the earlier memorandum dated December 7, 2017. These revised guidelines provided a procedure for determining the amount payable to works contractors, including provisions for reimbursement of excess amounts if the revised GST-inclusive work value exceeded the original agreement value.

Sections Cited

Section 73, Section 129, Rule 86A

AI-generated summary — verify with the full judgment below

02.

12.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Mr. M.S. Sahoo, learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.