M/S.Shiva Jyoti Construction vs. State Of Odisha
Held
The Court noted that the State Government had issued revised guidelines on 10.12.2018, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provide a detailed procedure for calculating the GST-inclusive work value for the balance portion of works contracts executed after 01.07.2017, where tenders were invited before that date based on the pre-GST Schedule of Rates – 2014 (SoR-2014). The guidelines stipulate that if the revised GST-inclusive work value for the balance work exceeds the original agreement work value for that balance portion, the works contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment already made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, which the authority must consider and dispose of in light of the revised guidelines dated 10.12.2018, preferably by 31.03.2019. The petitioner was granted liberty to challenge the authority's decision if aggrieved. No coercive action was to be taken against the petitioner until 31.03.2019.
Facts
The petitioner, a works contractor, challenged the action of the opposite parties (State authorities) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. The grievance stemmed from the requirement to pay GST on works contracts entered into before the GST regime, where the original agreements were based on the Schedule of Rates – 2014 (SoR-2014) which included all indirect taxes. The State submitted revised guidelines dated 10.12.2018, superseding the earlier memorandum, to address such issues.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to 01.07.2017 but executed partly or wholly after that date, and if the action of the opposite parties in not reimbursing this amount is arbitrary and illegal? Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not envisaged at the time of entering into the agreements, and therefore, they are entitled to reimbursement of this differential tax amount. They challenged the initial guidelines that did not adequately address this issue. Revenue/State's contention: The learned Additional Government Advocate submitted that the Government had issued revised guidelines on 10.12.2018 to address the difficulties faced by contractors regarding works contracts under GST, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provide a procedure for determining the GST-inclusive work value for the balance work and reimbursement of excess amounts.
Sections Cited
Section 1(iii) of Finance Department Memorandum dated 07.12.2017, Revised guidelines dated 10.12.2018
AI-generated summary — verify with the full judgment below
19.12.2018
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by t
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.