Gajendra Prasad Panda vs. State Of Orissa
Held
The Court noted that the State Government had issued revised guidelines on December 10, 2018, superseding the earlier ones dated December 7, 2017. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for balance work on contracts tendered before July 1, 2017, but executed thereafter. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised Schedule of Rates (SoR-2014), adjusting it for tender premium/discount, and then adding the applicable GST. The guidelines stipulate that if the revised GST-inclusive work value is higher than the original agreement value for the balance work, the contractor is to be reimbursed for the excess. Conversely, if it is lower, the payment is to be reduced, and any excess payment recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority, who would consider and dispose of it in light of these revised guidelines by March 31, 2019. The Court also stated that if the petitioner remained aggrieved, they could challenge the authority's decision. No coercive action was to be taken against the petitioner until March 31, 2019. The issue of the validity of the earlier clauses was implicitly addressed by the acceptance and application of the revised guidelines.
Facts
The petitioner, a works contractor, filed a writ petition challenging the State's action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also challenged specific clauses of Finance Department Memoranda dated July 22, 2017, and December 7, 2017. The core grievance was that the introduction of GST imposed tax liabilities not originally contemplated in agreements entered into prior to the GST regime. The State submitted revised guidelines issued on December 10, 2018, which superseded the earlier ones and provided a procedure for determining the GST-inclusive work value for balance work executed after June 30, 2017, on contracts tendered before July 1, 2017.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to July 1, 2017, but executed partly or wholly thereafter? 2. Whether Clause 6 of the Finance Department Memorandum dated July 22, 2017, and Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017, are valid and applicable in light of the transition to GST? Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an increased tax burden that was not factored into the original contract prices, leading to a financial disadvantage. They sought reimbursement of this differential tax amount. Revenue's Contention: The Additional Government Advocate submitted that the Government of Odisha had issued revised guidelines on December 10, 2018, to address the difficulties faced by contractors due to the GST implementation. These revised guidelines provided a mechanism for calculating the GST-inclusive work value for balance work and for reimbursement or recovery of amounts based on this calculation.
Sections Cited
CGST Act, SGST Act
AI-generated summary — verify with the full judgment below
19.12.2018
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also challenged Clause 6 of the Finance Department Memorandum dated 22.07.2017 and Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.