Alok Ranjan Bedbak vs. State Of Odisha
Held
The Court noted that the revenue/State had issued revised guidelines on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work executed after July 1, 2017, for contracts tendered before that date. The guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value for the balance work, the works contractor was to be reimbursed for the excess amount. Conversely, if it was less, the payment would be reduced, and any excess payment already made would be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by March 31, 2019. The petitioner was granted liberty to challenge the decision of the authority if aggrieved. No coercive action was to be taken against the petitioner until March 31, 2019.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (revenue/State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) effective July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the introduction of GST imposed taxes not envisaged at the time of entering into agreements. The revenue/State submitted revised guidelines issued by the Government of Odisha, Finance Department, on December 10, 2018, superseding the earlier memorandum.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed partly or wholly after that date, under the existing guidelines. 2. Whether Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017, is arbitrary or illegal in its application to works contracts executed post-GST implementation. Petitioner's Contention: The petitioner argued that the introduction of GST resulted in an increased tax burden that was not accounted for in the original agreements, leading to a financial disadvantage. They sought reimbursement of this differential tax amount. Revenue/State's Contention: The revenue/State submitted that revised guidelines were issued on December 10, 2018, to address the concerns of contractors regarding works contracts executed post-GST. These guidelines provided a procedure for determining the GST-inclusive work value and reimbursement of any excess amount payable to the contractor.
Sections Cited
Section 1(iii) of the Finance Department Memorandum dated 07.12.2017, Finance Department Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F Dated 10.12.2018
AI-generated summary — verify with the full judgment below
19.12.2018
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by t
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.