M/S.M.S.Infraengineers PVT LTD vs. State Of Odisha
Held
The Court noted that the State had issued revised guidelines on December 10, 2018, superseding the earlier memorandum dated December 7, 2017. These revised guidelines provided a detailed procedure for determining the GST-inclusive work value for the balance work executed after June 30, 2017, for contracts tendered before July 1, 2017. The procedure involves ascertaining the work done after June 30, 2017, determining its revised estimated work value as per the Revised SoR-2014, adjusting it by the tender premium/discount, and then adding the applicable GST rate. The guidelines stipulate that if the revised GST-inclusive work value is more than the original agreement work value for the balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is less, the payment is to be reduced, and any excess payment made is to be recovered. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority is to consider and dispose of this representation in light of the revised guidelines dated December 10, 2018, expeditiously, preferably by March 31, 2019. The petitioner was granted liberty to challenge the authority's decision if aggrieved. No coercive action was to be taken against the petitioner until March 31, 2019.
Facts
The petitioner, a works contractor, filed a writ petition challenging the action of the opposite parties (State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) with effect from July 1, 2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The State submitted revised guidelines issued by the Finance Department on December 10, 2018, superseding the earlier memorandum, which provided a procedure for determining the GST-inclusive work value for balance work executed after July 1, 2017, on contracts tendered before that date.
Key Issues
1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into before July 1, 2017, but executed partly or wholly after that date? 2. Whether Clause 1(iii) of the Finance Department Memorandum dated December 7, 2017, is liable to be quashed? Petitioner's contentions: The petitioner argued that due to the introduction of GST, they are required to pay tax which was not anticipated at the time of entering into the agreements, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue's contentions: The State submitted revised guidelines issued on December 10, 2018, which provided a mechanism for calculating and reimbursing the differential GST amount for works contracts executed after the GST implementation but tendered prior to it. The State relied on the revised guidelines to address the petitioner's grievance.
Sections Cited
Section 1(iii) of Finance Department Memorandum dated 07.12.2017, Revised guidelines dated 10.12.2018
AI-generated summary — verify with the full judgment below
19.12.2018
Heard learned counsel for the parties.
By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.
Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by t
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.