Gyanendra Ku.Routray vs. State Of Odisha

WP(C)/8911/2018HC OrissaGSTCNR ODHC01027478201819 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryRemanded

Held

The Court acknowledged the petitioner's grievance regarding the differential tax amount due to the GST regime change. However, it noted that the State had issued revised guidelines on 10.12.2018, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provide a detailed procedure for determining the GST-inclusive work value for balance work executed after 01.07.2017. The procedure involves ascertaining the work done after 30.06.2017, determining its revised estimated work value as per the Revised SoR-2014, adjusting it for tender premium/discount, and then adding the applicable GST rate. The guidelines also stipulate that if the revised GST-inclusive work value is higher than the original agreement value for the balance work, the contractor is to be reimbursed for the excess amount. Conversely, if it is lower, the payment is to be reduced, and any excess payment recovered. The Court directed the petitioner to make a comprehensive representation to the appropriate authority, which would then consider and dispose of the representation in light of these revised guidelines. No coercive action was to be taken against the petitioner until 31.03.2019.

Facts

The petitioner, a works contractor, challenged the action of the opposite parties (State) in not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner also sought to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. The grievance was that the GST liability was not envisaged when the agreements were entered into. The State submitted revised guidelines issued by the Finance Department on 10.12.2018, superseding the earlier memorandum, which provided a procedure for determining the GST-inclusive work value for balance work executed after 01.07.2017, based on revised Schedule of Rates (SoR-2014) and tender premium/discount. The Court directed the petitioner to make a representation to the appropriate authority based on these revised guidelines.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to 01.07.2017 but executed partly or wholly after 01.07.2017? 2. Whether Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017, which allegedly caused the grievance, is liable to be quashed? Petitioner's contention: The petitioner argued that due to the introduction of GST, they are required to pay tax that was not anticipated at the time of entering into the agreements, leading to a financial burden. They sought reimbursement of this differential tax amount. Revenue's contention: The learned Additional Government Advocate submitted that the Government had issued revised guidelines on 10.12.2018, superseding the earlier memorandum dated 07.12.2017. These revised guidelines provide a mechanism for calculating the GST-inclusive work value for balance work and address the contractors' claims for additional amounts towards GST.

Sections Cited

Section 1(iii) of Finance Department Memorandum dated 07.12.2017, Office memorandum No. FIN-CTI-TAX-0045-2017/38535/F Dated 10.12.2018

AI-generated summary — verify with the full judgment below

04.

19.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by t

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.