West End Infrastructure vs. State Of Odisha

WP(C)/18324/2018HC OrissaGSTCNR ODHC01054298201819 December 2018Bench: MR. JUSTICE K. S. JHAVERI (CJ),MR. JUSTICE K.R.MOHAPATRA4 pages
AI SummaryDisposed

Held

The Court noted that revised guidelines were issued to address the issue of works contracts under GST. The petitioner was directed to make a representation to the appropriate authority, which would decide it based on the revised guidelines.

Facts

The petitioner challenged the non-reimbursement of differential tax amounts due to the shift from VAT to GST for works contracts entered into before GST implementation but executed after. The petitioner also sought to quash a specific clause in a Finance Department Memorandum.

Key Issues

The primary issue was how to handle tax implications for works contracts executed after the GST regime began, when the contracts were tendered under the previous VAT regime. This involved determining the reimbursement of additional tax burdens.

Sections Cited

None

AI-generated summary — verify with the full judgment below

02.

19.12.2018

Heard learned counsel for the parties.

By way of this writ petition, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017 and has also prayed to quash Clause 1(iii) of the Finance Department Memorandum dated 07.12.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by t

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.