The Court acknowledged the petitioner's grievance regarding the differential tax amount due to the GST regime change. The Court noted that the State Government had issued revised guidelines on 10.12.2018, which provided a comprehensive procedure for determining the GST-inclusive work value for the balance work in cases where tenders were invited before 01.07.2017 but payments were made after the GST implementation. These guidelines stipulated that if the revised GST-inclusive work value for the balance work exceeded the original agreement work value, the contractor would be reimbursed for the excess amount. The Court directed the petitioner to make a comprehensive representation before the appropriate authority within four weeks, ventilating their grievance. The authority was directed to consider and dispose of the representation in light of the revised guidelines dated 10.12.2018, as expeditiously as possible, preferably by 31.03.2019. The Court also ordered that no coercive action would be taken against the petitioner until 31.03.2019. The writ petition was disposed of with liberty to the petitioner to challenge the authority's decision if aggrieved.

Facts

The petitioner, a works contractor, filed a writ petition challenging the opposite parties' action of not reimbursing the differential tax amount arising from the transition from Value Added Tax (VAT) to Goods and Services Tax (GST) on 01.07.2017. The petitioner's grievance was that they were required to pay GST on works contracts entered into before the GST regime, which was not initially envisaged. The State government, through the Finance Department, issued revised guidelines on 10.12.2018, superseding earlier guidelines dated 07.12.2017, to address such issues concerning works contracts executed partly or wholly after 01.07.2017 but tendered before that date. The revised guidelines provided a procedure for determining the GST-inclusive work value for the balance work and reimbursement of excess amounts.

Key Issues

1. Whether the petitioner is entitled to reimbursement of the differential tax amount arising from the change in tax regime from VAT to GST for works contracts entered into prior to 01.07.2017 but executed thereafter? (Question of law) Petitioner's contention: The petitioner argued that the introduction of GST resulted in an additional tax burden not contemplated at the time of entering into the agreements, and therefore, they should be reimbursed for this differential tax amount. Revenue/State's contention: The learned Additional Government Advocate submitted that the Government had issued revised guidelines on 10.12.2018, which provided a mechanism to address the grievances of contractors regarding works contracts executed post-GST implementation for tenders issued pre-GST. The State relied on the Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated 10.12.2018.

Sections Cited

Not specified in the judgment

AI-generated summary — verify with the full judgment below

02.

21.12.2018

Heard learned counsel for the parties.

By way of this writ petition, in substance, petitioner has challenged action of the opposite parties in not reimbursing the differential tax amount arising out of change in tax regime from Value Added Tax (VAT) to Goods and Service Tax (GST) with effect from 01.07.2017. Batch of writ petitions are being filed on this issue. The main issue involved in such matters is that the difficulty faced by the contractors due to change in the regime regarding works contract under GST. The grievance of the petitioner is that in view of the introduction of the GST, petitioner is required to pay tax which was not envisaged while entering into the agreement.

Learned Addl. Government Advocate submits that the Government has now come out with a revised guidelines in this respect in supersession of the guidelines issued vide Finance Department letter dated 07.12.2017. He files an Additional Counter Affidavit of O.P. No.2 annexing the revised guidelines relating to works contract under GST issued by the Government of Odisha, Finance Department vide Office memorandum No. FIN-CTI-TAX-

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Orissa High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.