J.M.Swamy vs. Government Of INDIA

COMAP/330/2025HC KarnatakaGSTCNR KAHC01034699202517 October 2026Bench: D K SINGH,H.SHANTHI BHUSHAN28 pages
For Respondent: SRI. KUMAR M.N., ADVOCATE
AI SummaryDismissed

Held

The High Court held that the Commercial Court was justified in setting aside the Arbitrator's award. The Court found that the claims for overheads and loss of profit, idle manpower and machinery, and escalation were substantial and required a clear connection between the amounts awarded, the agreement terms, and the delay attributable to the Department. The Arbitrator's award did not adequately reconcile these claims with the contractual provisions, work completed, admitted stoppage, and escalation already paid. Similarly, the Commercial Court's examination of GST reimbursement, bank guarantee commission, and interest claims was found to be based on contractual entitlement and computation, not just a preference for another view. The Court concluded that the defects identified by the Commercial Court fell within the statutory grounds for interference under Section 34 of the Arbitration and Conciliation Act, 1996. The appellant failed to demonstrate that the Commercial Court exceeded its scope or committed an error warranting interference under Section 37. Therefore, the Commercial Appeal was dismissed, and the Commercial Court's judgment was affirmed.

Facts

The appellant, J.M. Swamy, a civil contractor, was awarded a work order by the respondent, Government of India (CPWD), for constructing a sewage treatment plant for Rs. 1,26,01,150/-. The stipulated completion period was eight months from February 2017. The appellant contended that delays were caused by the respondent, including delayed drawing approvals, site conditions, and decisions on extra items. The respondent granted extensions, ultimately up to November 2019, without compensation. The appellant completed civil work in June 2019 and O&M in November 2019. After submitting the final bill, payment was delayed, leading the appellant to invoke dispute resolution. The respondent sought to levy compensation of Rs. 12,60,115/-. An arbitrator was appointed, and the appellant claimed various amounts, including for extra items, interest, GST reimbursement, and overheads. The arbitrator passed an award in favor of the appellant. The Commercial Court set aside this award, and the present appeal challenges the Commercial Court's decision.

Key Issues

1. Whether the Commercial Court was justified in setting aside the Arbitrator's award, particularly concerning the claims for overheads and loss of profit, idle manpower and machinery, and escalation, by finding that the award lacked a satisfactory reconciliation with the contract and evidence? (Section 34 of the Arbitration and Conciliation Act, 1996, and Section 37 of the Arbitration and Conciliation Act, 1996). 2. Whether the Commercial Court erred in its assessment of the claims for GST reimbursement, bank guarantee commission, and interest, considering the contractual provisions and the nature of the amounts awarded? Petitioner's Arguments: The appellant argued that the Commercial Court could not reassess evidence as if hearing an appeal on facts and that a different interpretation of the contract is not a ground for setting aside an award. The appellant contended that the Commercial Court exceeded the permissible scope of Section 34. Respondent's Arguments: The respondent maintained that the claims required examination in accordance with the agreement and GCC. They disputed that the entire delay was attributable to the department and argued that extensions granted under Clause 5 did not extinguish the right to levy compensation under Clause 2. The respondent contended that the Commercial Court was justified in finding that the monetary awards could not be sustained due to lack of satisfactory reconciliation with contractual provisions, work completed, admitted stoppage, and escalation already paid.

Sections Cited

Section 13(1-A), Section 34, Section 37, Section 9, Section 11, Section 31(7)(b)

AI-generated summary — verify with the full judgment below

- 1 -

COMAP No. 330 of 2025

IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 17TH DAY OF OCTOBER 2026 PRESENT THE HON'BLE MR. JUSTICE D K SINGH AND THE HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN COMMERCIAL APPEAL NO. 330 OF 2025 BETWEEN:

J.M.SWAMY AGED ABOUT 60 YEARS, NO.20, 8TH 'B' MAIN, RAJAMAHAL VILAS EXTENSION, BANGALORE-560 080. …APPELLANT (BY SRI. MANUCHANDRA SEKHAR.P.,ADVOCATE)

AND:

GOVERNMENT OF INDIA CENTRAL PUBLIC WORK DEPARTMENT REP BY ITS THE EXECUTIVE ENGINEER BCD III, CPWD, KENDRIYA SADAN, KORAMANAGALA, BANGALORE 560 034. …RESPONDENT (BY SRI. KUMAR M.N.,ADVOCATE)

THIS COMAP FILED UNDER SECTION 13(1-A) OF THE COMMERCIAL COURT ACT, 2015 PRAYING TO 1) ADMIT THE PRESENT COMMERCIAL AND CALL FOR THE RECORDS OF THE LOWER COURT IN COM.AP NO.156/2024 VIDE ORDER DATED 19.04.2025 PASSED BY THE LXXXV ADDITIONAL CITY CIVIL AND SESSIONS JUDGE, AT BENGALURU (CCH-86) JUDGMENT MADE IN COMAP NO.156/2024 (ANNEUXRE -A) AND ETC.,

THIS APPEAL HAVING BEEN HEARD AND RESERVED FOR JUDGMENT ON 24.09.2026 AND COMING ON FOR PRONOUNCEMENT THIS DAY, HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN DELIVERED THE FOLLOWING:

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Karnataka High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.