M/S Prime Construction vs. The State Of Madhya Pradesh

WP/38992/2024HC Madhya PradeshGST18 December 2024Bench: HON'BLE SHRI JUSTICE VIVEK AGARWAL3 pages
For Petitioner: Swatantra PandeyFor Respondent: Advocate General
AI SummaryPartly Allowed

Held

The Court held that no disputed question of facts was involved in the case, thus the petitioner could not be relegated to the Dispute Resolution Forum under the agreement. The Court noted that Respondent No. 4 (State GST Department) also agreed that the GST rate had been enhanced from 12% to 18% and was liable to be paid by Respondent No. 2, a Government Entity. Following the parity with a previous order of the Division Bench dated December 12, 2024, in WP No. 39378 of 2024, the Court directed Respondent No. 2 to pay the difference of GST amount to the petitioner at 6% for the period from January 1, 2022, to September 30, 2022, within three months of receiving the order. Failure to comply would entitle the petitioner to interest at 6% per annum from the date of entitlement. The writ petition was disposed of with these directions.

Facts

The petitioner, M/s Prime Construction, filed a writ petition seeking a mandamus directing the respondents to release the admitted liability of the difference in GST amount of Rs. 4,01,780/- along with 24% interest. The petitioner is engaged in construction work and had agreements with Respondent No. 2, a public enterprise classified as a Government Entity. The GST rate applicable to the petitioner's services was enhanced from 12% to 18% effective January 1, 2022. However, Respondent No. 2 continued to pay GST at the old rate of 12% on running bills, creating a difference of 6% GST for invoices issued after January 1, 2022. Respondent No. 2 acknowledged this liability on September 26, 2022, but stated that approval from the State Government was pending. The petitioner approached the High Court as no approval was received.

Key Issues

1. Whether the Petitioner is entitled to a writ of mandamus directing the respondents to release the admitted differential GST amount of 6% for the period from January 1, 2022, to September 30, 2022, along with interest, considering the enhancement of GST rates and the admitted liability of Respondent No. 2. Contentions: Petitioner: Argued that Respondent No. 2 admitted the liability to pay the additional 6% GST from January 1, 2022, and that the petitioner is entitled to this amount along with interest. Relied on a Division Bench order dated December 12, 2024, in WP No. 39378 of 2024, which dealt with a similar issue of reimbursement of extra GST paid. Revenue/State: The judgment does not record specific arguments from the State GST Department (Respondent No. 4) beyond stating their agreement that the GST rate was enhanced and liable to be paid by Respondent No. 2. Respondents No. 2 and 3 filed a return raising objections regarding the maintainability of the writ petition and the availability of an alternative remedy under the Arbitration Act.

Sections Cited

Article 226

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR BEFORE HON'BLE SHRI JUSTICE VIVEK AGARWAL & HON'BLE SHRI JUSTICE DEVNARAYAN MISHRA ON THE 18th OF DECEMBER, 2024 WRIT PETITION No. 38992 of 2024 M/S PRIME CONSTRUCTION Versus THE STATE OF MADHYA PRADESH AND OTHERS Appearance: Shri Swatantra Pandey - Advocate for petitioner. Shri Yash Soni - Dy. Advocate General for State.

ORDER Per: Justice Vivek Agarwal Learned counsel for petitioner prays for issuance of writ of mandamus directing concerned respondent to release the admitted liability towards the difference of GST amount of Rs.4,01,780/- along with 24% rate of interest and to support of his contention, leaned counsel for petitioner places reliance on an order Division Bench of this Court dated 12.12.2024 passed in WP No.39378 of 2024 wherein it is observed as under :- "With the consent of parties, heard finally. The petitioner has filed the present under Article 226 of the Constitution of India for issuance of an appropriate writ, order or direction, directing the respondents to reimburse the extra GST amount paid @ 6% from 01.01.2022 to 30.09.2022 along with interest.

02.

The petitioner is a Company / Proprietorshi

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Madhya Pradesh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.