Laxmi Prasad vs. Union Of INDIA

WPC/1085/2021HC ChhattisgarhGSTCNR CGHC01005287202123 February 2021Bench: HON'BLE SHRI JUSTICE GOUTAM BHADURI3 pages
AI SummaryRemanded

Held

The Court held that the grievance of the petitioners regarding inadequate compensation, specifically concerning the application of the multiplier and the differential treatment of similar properties, needs to be addressed individually. The Court referred to Section 3G(5) of the National Highways Act, 1956, which provides for determination of compensation by an arbitrator if the amount determined by the competent authority is not acceptable. Since the Additional Commissioner of Bilaspur Division has been appointed as an Arbitrator for such matters, the Court directed the petitioners to raise their individual disputes before this authority. The Additional Commissioner is to decide the matter objectively by passing a speaking order. The petitioners were directed to approach the Additional Commissioner within two weeks, and the Arbitrator was expected to decide within 60 days of receiving the applications. The Court did not decide the merits of the compensation dispute itself but facilitated the process for its resolution.

Facts

The petitioners, Laxmi Prasad and Chaituram, are aggrieved by the compensation awarded for their properties acquired for the construction of National Highway No. 200 (New No. 49). They contend that the authorities failed to apply the proper multiplier while quantifying the compensation and applied different yardsticks for similar adjacent properties, leading to arbitrary and unequal compensation. The properties were acquired under the National Highways Act, 1956. The dispute concerns the amount of compensation determined by the competent authority.

Key Issues

1. Whether the compensation awarded for the acquired properties is inadequate due to the incorrect application of the multiplier, and whether the authorities applied different yardsticks for similar adjacent properties, rendering the compensation arbitrary? (Question of law and fact, turning on Section 3G(5) of the National Highways Act, 1956). Petitioner's Contention: The petitioners argued that the compensation awarded was inadequate because the authorities did not apply the proper multiplier and applied different standards for adjacent, similar properties, leading to arbitrary compensation. They sought a review of the compensation amount. Revenue/State's Contention: The respondents did not record specific arguments against the petitioners' claims regarding the compensation calculation. However, the Court noted that the Additional Commissioner of Bilaspur Division has been appointed as an Arbitrator under Section 3G(5) of the National Highways Act, 1956, to resolve such disputes.

Sections Cited

Section 3G(5)

AI-generated summary — verify with the full judgment below

1 NAFR HIGH COURT OF CHHATTISGARH, BILASPUR WPC No. 1085 of 2021

1.

Laxmi Prasad S/o Late Accheram Aged About 54 Years

2.

Chaituram S/o Nirghin Aged About 55 Years Both are R/o Village Seoni Tehsil Champa District Janjgir Champa Chhattisgarh ---- Petitioners Versus

1.

Union Of India Through Secretary, Ministry Of Road Transport And Highways Transport Bhawan, 1, Parliament Street New Delhi

2.

Project Director National Highway Authority Of India (Nhai) Project Implementation Unit D-61, Hig-1, Abhilasha Parisar Behind New Bus Stand Tifra Bilaspur Chhattisgarh

3.

State Of Chhattisgarh Through Secretary Department Of Revenue Mahanadi Bhawan Raipur District Raipur Chhattisgarh

4.

Collector Champa District Janjgir Champa Chhattisgarh

5.

Sub Divisional Officer Cum Competent Authority Land Acquisition Champa District Janjgir Champa Chhattisgarh

6.

Inspector General Registration And Superintendent Of Stamp Gst Bhawan, Raipur District Raipur Chhattisgarh ---- Respondents For Petitioners : Mr. K.K. Patel, Advocate For Respondent No. 1/UOI : Mr. Tushar Dhar Diwan, Advocate on behalf of Mr. Ramakant Mishra, ASG For Respondent No. 2/NHAI : Mr. Himanshu Pandey on behalf of Mr. B

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.