M/S Ram Gopal Somani vs. Bilaspur Smart City Limited

WPC/1123/2021HC ChhattisgarhGSTCNR CGHC01005289202107 April 2021Bench: HON'BLE THE CHIEF JUSTICE,HON'BLE SHRI JUSTICE NARENDRA KUMAR VYAS22 pages
AI SummaryAllowed

Held

The Court held that the decision-making process by BSCL was fundamentally flawed and unsustainable. Regarding the financial criteria, the Court found that BSCL erred in considering only the turnover of a single financial year (2018-19) instead of the average turnover over the three stipulated years (2016-17, 2017-18, and 2018-19). The petitioner's assertion that the 3rd respondent's average turnover was less than ₹8.00 crores, thus entitling them to fewer marks, was not directly refuted with contrary evidence by BSCL. This alone would have disqualified the 3rd respondent. Furthermore, concerning the work experience criteria, the Court noted that the clarification obtained by BSCL from Chhattisgarh State Power Distribution Company Limited indicated that while a significant portion of the work was completed, the measurement for the remaining part was still pending. Crucially, the clarification did not explicitly state 'satisfactory completion' of the entire work, a requirement mandated by the corrigendum. Therefore, the Court concluded that the 3rd respondent was not qualified based on both financial and experience criteria. The impugned order dated 22.01.2021 and the tender proceedings finalized in favour of the 3rd respondent were set aside. BSCL was directed to either negotiate with the petitioner (L-2) for awarding the tender or to conduct a fresh tender process with clear qualification criteria.

Facts

The petitioner, M/s Ram Gopal Somani, challenged the tender process conducted by Bilaspur Smart City Limited (BSCL) for external electrification. The petitioner alleged that BSCL wrongly declared the 3rd respondent, M/s Future Engineering, as the successful bidder (L-1) despite the latter not meeting the financial and experience criteria stipulated in the tender. The petitioner, placed as L-2, raised objections pointing out discrepancies in the 3rd respondent's disclosed turnover and work experience. BSCL rejected these objections, stating the evaluation was done as per tender terms. The petitioner then filed a writ petition seeking to quash BSCL's decision and direct them to reject the 3rd respondent's bid and award the contract to the petitioner.

Key Issues

1. Whether the 3rd respondent met the financial criteria as stipulated in the tender, specifically concerning the average annual turnover over three financial years (Section 5.3, Clause 5.3.1(a) of the Tender Document)? - Petitioner argued that the 3rd respondent's disclosed turnover was less than ₹8.00 crores, entitling them to only 20 marks, not the full 30 marks awarded, thus disqualifying them as they did not meet the minimum 70 marks requirement. - Respondents argued that the 3rd respondent's turnover for FY 2018-19 was ₹11.854 crores, exceeding ₹8.00 crores, justifying the full marks. 2. Whether the 3rd respondent met the work experience criteria as stipulated in the tender, specifically the requirement of 'satisfactory completion' of a similar work (Section 5.3, Clause 5.3.1(b) of the Tender Document, as amended by Corrigendum dated 21.11.2020)? - Petitioner argued that the 3rd respondent did not have the requisite experience as the work was not satisfactorily completed. - Respondents argued that the 3rd respondent had satisfactorily completed a work of ₹10,66,95,776/-, and the corrigendum allowed consideration of ongoing works.

Sections Cited

Section 5.3, Clause 5.3.1(a), Clause 5.3.1(b)

AI-generated summary — verify with the full judgment below

AFR HIGH COURT OF CHHATTISGARH, BILASPUR Judgment Reserved on : 24.03.2021 Judgment Delivered on : 08.04.2021 HIGH COURT OF CHHATTISGARH, BILASPUR WPC No. 1123 of 2021 • M/s Ram Gopal Somani Through its Partner, Ram Gopal Somani, S/o Late Shri Ganesh Narayan Ji Somani, age 62 Years, R/o Station Road, Champa, District- Janjgir-Champa, Chhattisgarh 495671 ---- Petitioner Versus

1.

Bilaspur Smart City Limited Through its Managing Director, 3rd Floor, Pinglee Bhawan, Nehru Chowk, 495001 Bilaspur, Chhattisgarh.

2.

The Manager Bilaspur Smart City Limited, 3rd Floor, Pinglee Bhawan, Nehru Chowk, 495001, Bilaspur, Chhattisgarh.

3.

M/s Future Engineering a Company Incorporated under the Companies Act 2013 having its Registered Office at Vidya Nagar Bilaspur, Chhattisgarh 495001. ---- Respondents ________________________________________________________________ For Petitioner : Mr. Kshitij Sharma, Advocate For Respondents No.1 & 2 : Mr. Mateen Siddiqui, Advocate For Respondent No.3 : Mr. B.D. Guru and Mr. S.S. Baghel, Advocates _________________________________________________________________ Hon'ble Shri P. R. Ramachandra Menon, Chief Justice Hon'ble Shri Narendra Kumar Vyas, J

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.