Rajkumar vs. Chief Engineer And Head Of Department

SPA/854/2019HC UttarakhandGSTCNR UKHC01014787201926 September 2019Bench: HON'BLE THE CHIEF JUSTICE,HON'BLE MR. JUSTICE ALOK KUMAR VERMA8 pages
AI SummaryDismissed

Held

The High Court held that the appellant's contention that the respondents ought to have negotiated with him was without merit, as the appellant had clearly stated his unwillingness to execute the work at the previously quoted prices after the expiry of the 120-day validity period and had sought a refund of his earnest money deposit. No useful purpose would have been served by such negotiations. The Court also rejected the contention that the tender process should have been cancelled and fresh tenders invited. It reasoned that any further delay would lead to cost escalation and adversely affect public interest. Given that the work was already awarded to L-2 and a significant period had passed, the learned Single Judge was justified in refusing to interdict the award. The Court further held that the appellant's claim for damages was a disputed question of fact requiring adjudication by a competent Civil Court based on evidence. The Special Appeal was dismissed, but the appellant was permitted to pursue his common law remedy for damages in the Civil Court.

Facts

The appellant, a lowest tenderer (L-1), was awarded a civil construction work contract by the Public Works Department for Rs. 75,48,139.50 + 12% GST. The tender prescribed a validation period of 120 days. The department failed to execute the agreement within this period, which expired on February 14, 2019. The appellant requested a refund of his earnest money deposit, stating the quoted rates were no longer economical. The department then negotiated with the second lowest tenderer (L-2) and awarded the contract to them on March 5, 2019, for Rs. 75,46,333.49 + 12% GST. The appellant challenged this award, seeking its quashing and a direction to allot the work to him. The Single Judge, while faulting the department for the delay, disposed of the writ petition by directing payment of Rs. 75,481/- to the appellant and initiating an inquiry into the delay. The appellant filed a Special Appeal against the non-cancellation of the contract awarded to L-2 and the inadequacy of the compensation.

Key Issues

1. Whether the respondents ought to have awarded the contract to the fourth respondent (L-2) when the appellant (L-1) had withdrawn from the contract due to the expiry of the validation period, and whether the tender process should have been cancelled and fresh tenders invited, or negotiations should have been held with the appellant as per the Procurement Rules? Petitioner's Arguments: The appellant contended that the award of the contract to L-2 was arbitrary and illegal. He argued that the learned Single Judge erred in granting only 1% of the project cost as damages, whereas the department's permitted profit margin was 10%, and a higher amount should have been awarded. The appellant also argued that the respondents should have either cancelled the tender and invited fresh bids or negotiated with him as per the Procurement Rules. Respondents' Arguments: The State Government argued that the learned Single Judge's direction to pay compensation and interest was erroneous. They did not explicitly argue against the appellant's contention regarding the award to L-2 or the need for fresh tenders, but their overall stance was against the compensation awarded to the appellant.

Sections Cited

Article 226

AI-generated summary — verify with the full judgment below

IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL

Special Appeal No. 854 of 2019

Rajkumar

…Appellant

Vs.

Chief Engineer and Head of the Department, Public Works Department and others

…Respondents

Mr. Parikshit Saini, learned counsel for the appellant. Mr. B.S. Parihar, learned Standing Counsel for the State of Uttarakhand-respondents 1 to 3. Dated: 26th September, 2019

Coram: Hon’ble Ramesh Ranganathan, C.J.

Hon’ble Alok Kumar Verma, J.

Ramesh Ranganathan, C.J. (Oral)

This Special Appeal is preferred against the order passed by the learned Single Judge in Writ Petition (M/S) No. 1435 of 2019 dated 29.08.2019. 2. The appellant herein is the petitioner in Writ Petition (M/S) No. 1435 of 2019. He invoked the jurisdiction of this Court seeking a writ of certiorari to quash the tender allotment order dated 05.03.2019; a writ of certiorari to declare the un-acceptance noting dated 25.01.2019, on the e-tender submitted by the second respondent, as illegal; and a writ of mandamus directing respondents 2 and 3 to allot the work to him.

3.

Facts, to the limited extent necessa

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Uttarakhand High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.