M/S Bsbk Private Limited vs. State Of Chhattisgarh

WPC/3339/2023HC ChhattisgarhGSTCNR CGHC01023177202328 April 2024Bench: HON'BLE SHRI JUSTICE RAKESH MOHAN PANDEY43 pages
AI SummaryAllowed

Facts

M/s BSBK Private Limited (Petitioner) was awarded a contract by the Municipal Corporation, Bilaspur on March 7, 2019, for the construction of 5785 houses under the Pradhan Mantri Awas Yojna. The contract value was Rs. 2,62,11,92,000/- with a completion period of 36 months. The Petitioner faced significant delays in site handover, starting from June 2019, which impacted the project timeline and incurred financial losses. The Petitioner sought price escalation for work executed beyond the original contract period and refund of GST paid at an enhanced rate. The Municipal Corporation and other respondents are the revenue authorities. The Petitioner filed multiple writ petitions challenging the rejection of its representations and seeking directions for payment of price escalation and GST refund.

Held

The Court held that the Petitioner is entitled to price escalation for the work executed. The reasoning was based on the fact that the Municipal Corporation itself had asked the Petitioner to apply for price escalation. The Court relied on Supreme Court judgments in Assam State Electricity Board and NTPC Limited, which established that price escalation is a normal incident of delays in contract performance, especially in an inflationary environment, and is justified when delays are attributable to the other party. The Court also held that the Petitioner is entitled to a GST refund at the enhanced rate of 18% with effect from July 18, 2022, as per Clause 3.27 of the Agreement, given the government's notification increasing the GST rate. The Court found the writ petitions to be maintainable, referencing Supreme Court decisions in Tantia Construction Private Limited and Unitech Limited, which state that alternative remedies do not bar writ jurisdiction when there is discrimination, arbitrariness, or procedural impropriety. The Court also emphasized the importance of natural justice, citing Rajesh Agrawal, and noted that the Petitioner's representation was rejected cryptically without a proper hearing. The impugned order dated September 8, 2023, was quashed. The Court directed the Secretary, Department of Urban Administration and Development, to critically examine the matter of site allotment and prepare a report within sixty days, affording a hearing to all concerned. Subsequently, after considering inflation rates, an appropriate order for price escalation, particularly for sites handed over in 2022 and thereafter, was to be passed within a further sixty days. No coercive steps were to be taken against the Petitioner for 120 days.

Key Issues

1. Whether the Petitioner is entitled to price escalation for work executed beyond the original contract period of 36 months, considering the delays in site handover attributable to the respondents? (Question of law and fact, turning on contract terms and principles of fairness). 2. Whether the Petitioner is entitled to a refund of GST at the enhanced rate of 18% with effect from July 18, 2022, as per Notification No. 3/22 dated July 13, 2022? (Question of law, turning on the interpretation of the notification and contract clauses). Petitioner's Arguments: The Petitioner argued that the delays in site handover were solely attributable to the respondents, leading to extended execution periods. They contended that under principles of fairness and supported by Supreme Court judgments like Assam State Electricity Board and NTPC Limited, they are entitled to price escalation. Regarding GST, they argued that the increase in rate mandated by the government should be refunded as per Clause 3.27 of the agreement. They also argued that the writ petitions are maintainable despite an arbitration clause, as the issues involve arbitrariness and discrimination by the state instrumentalities, citing Tantia Construction Private Limited and Unitech Limited. They further argued that the rejection of their representation was cryptic and lacked adherence to natural justice principles. Respondents' Arguments: The respondents' arguments are not explicitly detailed in the provided excerpt regarding the specific contentions against price escalation or GST refund. However, the judgment mentions the existence of an arbitration clause (Clause 1.21) and a clause barring price escalation (Clause 3.26) as potential counterarguments, which the court addresses.

Sections Cited

Section 14, Section 129, Section 130, Section 131, Section 132, Section 133, Section 134, Section 135, Section 136, Section 137, Section 138, Section 139, Section 140, Section 141, Section 142, Section 143, Section 144, Section 145, Section 146, Section 147, Section 148, Section 149, Section 150, Section 151, Section 152, Section 153, Section 154, Section 155, Section 156, Section 157, Section 158, Section 159, Section 160, Section 161, Section 162, Section 163, Section 164, Section 165, Section 166, Section 167, Section 168, Section 169, Section 170, Section 171, Section 172, Section 173, Section 174, Section 175, Section 176, Section 177, Section 178, Section 179, Section 180, Section 181, Section 182, Section 183, Section 184, Section 185, Section 186, Section 187, Section 188, Section 189, Section 190, Section 191, Section 192, Section 193, Section 194, Section 195, Section 196, Section 197, Section 198, Section 199, Section 200, Section 201, Section 202, Section 203, Section 204, Section 205, Section 206, Section 207, Section 208, Section 209, Section 210, Section 211, Section 212, Section 213, Section 214, Section 215, Section 216, Section 217, Section 218, Section 219, Section 220, Section 221, Section 222, Section 223, Section 224, Section 225, Section 226, Section 227, Section 228, Section 229, Section 230, Section 231, Section 232, Section 233, Section 234, Section 235, Section 236, Section 237, Section 238, Section 239, Section 240, Section 241, Section 242, Section 243, Section 244, Section 245, Section 246, Section 247, Section 248, Section 249, Section 250, Section 251, Section 252, Section 253, Section 254, Section 255, Section 256, Section 257, Section 258, Section 259, Section 260, Section 261, Section 262, Section 263, Section 264, Section 265, Section 266, Section 267, Section 268, Section 269, Section 270, Section 271, Section 272, Section 273, Section 274, Section 275, Section 276, Section 277, Section 278, Section 279, Section 280, Section 281, Section 282, Section 283, Section 284, Section 285, Section 286, Section 287, Section 288, Section 289, Section 290, Section 291, Section 292, Section 293, Section 294, Section 295, Section 296, Section 297, Section 298, Section 299, Section 300

AI-generated summary — verify with the full judgment below

Heard together (2 matters)

W.P.(C) No. 3339 of 2023
W.P.(C) No. 3807 of 2023

Read from the judgment's own cause title. This page is filed under one of them.

1 AFR HIGH COURT OF CHHATTISGARH, BILASPUR Order reserved on : 01/04/2024 Order delivered on : 29/04/2024 W.P.(C) No. 3339 of 2023  M/s BSBK Private Limited having its registered office at 4th Floor, Surya Treasure Island Mall, Bhilai-490020, District – Durg (C.G.) Through its authorized representative Shri Raj Kumar Mahobe S/o Late Shri T.L. Mahobe, aged about 71 years, R/o 40-A/5, Motilal Nehru Nagar, Bhilai, District Durg (C.G.) ---- Petitioner Versus

1.

State of Chhattisgarh, Through the Secretary, Department of Urban Administration and Development, D- Block, 4th Floor, Indrawati Bhawan, Atal Nagar, Nava Raipur, District – Raipur (C.G.)

2.

Director, Department of Urban Administration and Development, D- Block, 4th Floor, Indrawati Bhawan, Atal Nagar, Nava Raipur, District – Raipur (C.G.)

3.

Commissioner, Municipal Corporation Bilaspur, District Bilaspur (C.G.)

4.

Executive Engineer/Nodal Officer, Pradhanmantri Awas Yojana, Municipal Corporation Bilaspur, District Bilaspur (C.G.)

5.

Chief Executive Officer, State Urban Development Agency, D – Block, 4th Floor, Indrawati Bhawan, Atal Nagar, Nava Raipur, District – Raipur (C.G.) ---- Respondents And W.P.(C) No. 3807 of 2023 M

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.