M/S Anand Carbo Private Limited vs. South Eastern Coalfields Limited (Secl)
Facts
M/s Anand Carbo Private Limited (the applicant) filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of an Arbitrator. The dispute arose from an e-tender awarded by South Eastern Coalfields Limited (SECL, the respondent) for HEMM hiring. The applicant was issued a Letter of Intent on March 8, 2019, for a total tender value of Rs. 46,69,86,447.86, including 18% GST. An agreement was executed on December 14, 2019. On July 3, 2021, SECL issued a show cause notice alleging failure to achieve targets from December 2020 to May 2021, proposing a penalty of Rs. 3,77,35,839.92. The applicant disputed this penalty and sought its release. SECL contended that the applicant had provided a 'no claim' certificate upon final bill payment and release of security deposit on August 18, 2022, indicating no dispute existed.
Held
The Court considered the arguments from both sides. Regarding the maintainability due to the 'no claim' certificate, the Court noted the applicant's readiness to appear before the Committee. The primary focus shifted to the exhaustion of the internal dispute resolution mechanism. The Court acknowledged that SECL had constituted a committee as per Clause 13 of the GCC following the applicant's legal notice. The applicant's representative initially appeared before the committee on February 25, 2023, but subsequently failed to appear for scheduled meetings on March 4, 2023, and March 17, 2023. The Court observed that the applicant's counsel stated readiness to appear before the committee. Therefore, the Court directed that the applicant be sent advance notice for the committee meeting, and the applicant shall appear to resolve the dispute as per Clause 13 of the GCC. The Committee was directed to decide the dispute within four weeks from the receipt of the order. The arbitration request was disposed of with these observations and directions, implying that the arbitration application would be considered further only if the internal mechanism failed.
Key Issues
1. Whether the arbitration application is maintainable when the applicant has provided a 'no claim' certificate upon final payment, thereby allegedly waiving any right to raise subsequent disputes? 2. Whether the arbitration application is pre-mature and not maintainable because the applicant failed to exhaust the internal dispute resolution mechanism provided under Clause 13 of the General Conditions of Contract (GCC)? Contentions of the Applicant: The applicant sought the appointment of an Arbitrator to resolve the dispute regarding the penalty imposed by SECL. The applicant disputed the penalty and demanded its release. They invoked Clause 13 of the GCC for amicable settlement and later Clause 13A for arbitration, proposing a specific Senior Advocate as the sole Arbitrator. Contentions of the Respondent (SECL): SECL argued that the application is not maintainable because the applicant provided a 'no claim' certificate at the time of final payment, signifying acceptance of all payments and absence of disputes. They further contended that the application is pre-mature as the applicant did not exhaust the internal dispute resolution mechanism under Clause 13 of the GCC, citing Union of India v. Parmar Constructions. SECL also alleged that the applicant deliberately did not participate in the committee meetings constituted as per Clause 13, thereby waiving their right to dispute resolution.
Sections Cited
Section 11(6), Clause 13, Clause 13A
AI-generated summary — verify with the full judgment below
1 2024:CGHC:29338 N A F R HIGH COURT OF CHHATTISGARH AT BILASPUR ARBR No. 32 of 2023 M/s Anand Carbo Private Limited A Private Limited, A Private Company Registered Under The Companied Act 1956 Having Its Registered Office At 11, Clive Row, 3rd Floor, Suite No. 28, Kolkata- 700001 Through Its Authorized Person Mr. Chandan Kumar Singh.
... Applicant Versus
South Eastern Coalfields Limited (Secl) Through The Chairman Cum Managing Director, SECL Bhavan, Seepat Road, Bilaspur-495555, Chhattisgarh.
The General Manager (Operations) South Eastern Coalfields Limited, Chirmiri Area, P O-West Chirmiri, District- Korea- 497773, Chhattisgarh. ... Respondents For Applicant : Mr. Rishabh Garg, Advocate. For Respondents : Ms. Astha Shukla, Advocate Hon’ble Mr. Justice Ramesh Sinha, Chief Justice Order
On Board
06/08/2024
By this application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short, the Act of 1996), the applicant seeks appointment of an independent Arbitrator to resolve the dispute that has arisen between the parties.
Mr. Rishabh Garg, learned counsel for the applicant submits that on 01.12.2018, the non-ap
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.