M/S Shri Vijay Kumar Singh vs. State Of Chhattisgarh

WPC/1403/2025HC ChhattisgarhGSTCNR CGHC01009519202528 April 2025Bench: HON'BLE THE CHIEF JUSTICE,HON'BLE SHRI JUSTICE ARVIND KUMAR VERMA10 pages
AI SummaryAllowed

Facts

The petitioner, M/s Shri Vijay Kumar Singh, a contractor, entered into a contract for construction of two bridges under the Pradhan Mantri Gram Sadak Yojana in District Jashpur. The work order was issued on February 9, 2021, with a completion period of 16 months. The petitioner commenced work but faced delays due to COVID-19 restrictions, design changes, rainfall, river water levels, high material costs, elections, and festivals. The petitioner sought extensions. On July 4, 2024, the Executive Engineer (Respondent No. 5) terminated the contract. Subsequently, a demand of Rs. 1.13 crore was made on November 5, 2024, by Respondent No. 3. A fresh tender was floated for the remaining work, and Respondent No. 6 was awarded the contract. The petitioner challenged the termination order, the demand, and the fresh work order.

Held

The Court allowed the writ petition. It held that the State/respondents did not controvert the petitioner's submission regarding the percentage of work completed and the undertaking to complete the balance work by December 31, 2025. The Court found that the State/respondents ought to have taken a lenient view and granted more time for completion of the balance work, given the petitioner's undertaking. Consequently, the Court set aside the impugned order dated July 4, 2024, terminating the petitioner's contract, and the order dated November 5, 2024, imposing the demand. The NIT dated November 25, 2024, by which the remaining work was awarded to Respondent No. 6, was also set aside. The petitioner was permitted to complete the balance work by December 31, 2025, as undertaken. The Court noted that if Respondent No. 6 had any grievance, they could approach the appropriate forum. The issue of the exorbitant rate for the remaining work and the alleged loss to the public exchequer was implicitly addressed by setting aside the fresh tender and allowing the petitioner to complete the work at the old rate.

Key Issues

1. Whether the termination of the petitioner's contract agreement by Respondent No. 5 on July 4, 2024, and the subsequent demand of Rs. 1.13 crore by Respondent No. 3 on November 5, 2024, were arbitrary, unreasonable, and violative of the principles of natural justice, considering the petitioner's cited reasons for delay and the alleged lack of a fair hearing. 2. Whether the acceptance and work order issued to Respondent No. 6 for the remaining work on November 25, 2024, at a rate of 18.8% + GST above the Probable Amount of Contract, causing a significant loss to the public exchequer, was illegal and amenable to judicial review. Petitioner's arguments: The petitioner contended that the termination was done without a fair opportunity to be heard and that the demand of Rs. 1.13 crore was illegal as there was no clause in the agreement for such a pre-hearing penalty. They argued that the fresh tender awarded to Respondent No. 6 at a much higher rate than their original quote (which was 7% below the probable amount) would cause immense loss to the public exchequer, citing the principle that public interest overrides contract law in public procurement and relying on the Apex Court's decision in Sudhir Kumar Kad v. Central Bureau of Investigation (CBI), (2021) 19 SCC 703. The petitioner also stated they had completed 95% of one bridge and were in a position to complete the remaining work by December 31, 2025, and were willing to have liquidated damages deducted from their bills. State/Respondents' arguments: The State argued that the petitioner failed to complete the work within the prescribed period and subsequent extensions, leading to the cancellation of the work order in accordance with law. They also submitted that the petitioner was aware of the fresh tender but did not challenge it, filing the petition only after Respondent No. 6 started work, to cause delay. Respondent No. 6 claimed to have started work and prayed that their order not be disturbed.

Sections Cited

None explicitly discussed or named in the provided text.

AI-generated summary — verify with the full judgment below

1

2025:CGHC:19330-DB

NAFR HIGH COURT OF CHHATTISGARH AT BILASPUR WPC No. 1403 of 2025 M/s Shri Vijay Kumar Singh Through - Partner- Ajay Singh S/o Shri R.B. Singh, Aged About 44 Years, R/o Behind Police Line, Bauripara, Ambikapur, P.S.- Kotwali, District- Sarguja (Chhattisgarh)

... Petitioner(s) versus 1 - State Of Chhattisgarh Through - Secretary, Public Works Department, Mahanadi Bhawan, Mantralaya, Atal Nagar, Nawa Raipur, District-

Raipur

(C.G.) 2 - Engineer In Chief Public Works Department, Raipur (C.G.) 3 - The Chief Engineer P.W.D. (Bridge Division), C.G. Rural Road Development Authority, Civil Line, Raipur (C.G.) 4 - The Superintending Engineer Project Division-1, C.G. Rural Road Development Authority, Ambikapur, District- Sarguja (C.G.) 5 - The Executive Engineer Project Implementation Unit-1, Chhattisgarh Rural Road Development Agency Jashpur, District- Jashpur (C.G.) 6 - M/s Shri Sai Associates Near Bus Stand Sitapur, District- Sarguja (C.G.) ---- Respondents (Cause-title taken from Case Information System) For Petitioner : Mr. Apoorva Tripathi, Advocate. For State/respondents No. 1 : Mr. Sha

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.