M/S Jagdish Kumar Sehgal vs. Union Of INDIA And Ors

CWP/22060/2019HC Punjab and HaryanaGSTCNR PHHC01098255201921 August 2019Bench: MR. JUSTICE TEJINDER SINGH DHINDSA2 pages
AI SummaryDismissed

Held

The Court held that there was no warrant for interference with the recovery notice as the petitioner did not dispute the GST liability. Regarding the prayer for an installment schedule, the Court found no provision in law to support such a request. Consequently, the Court dismissed the petition. The ratio decidendi is that a writ court will not interfere with recovery proceedings when the liability is not disputed, and no statutory provision exists for granting installment facilities for tax payments. The operative direction was the dismissal of the petition.

Facts

The petitioner, M/s Jagdish Kumar Sehgal, a government contractor, filed a writ petition challenging a recovery notice dated 12.06.2019 issued by the Garrison Engineer (West), Military Engineer Services (MES) Department, Ferozepur Cantt. The petitioner had completed a work order in October 2018 and received a completion certificate and final bill payment. The recovery notice pertained to the deposit of Goods and Services Tax (GST) related to the executed work and paid bill. The petitioner's counsel did not dispute the liability for GST deposit.

Key Issues

1. Whether the Court should interfere with the recovery notice for GST deposit when the petitioner does not dispute the liability, as per Article 226 of the Constitution of India. 2. Whether the petitioner is entitled to an installment schedule for depositing the GST amount, despite no statutory provision supporting such a prayer. Petitioner's arguments: The petitioner sought quashing of the recovery notice and, alternatively, requested an installment schedule for depositing the GST amount to allow reasonable time for payment. Revenue's arguments: The judgment records no specific arguments from the revenue or the Garrison Engineer. However, the Court's decision implies that the revenue's position was that the recovery notice was valid and no installment schedule was permissible.

AI-generated summary — verify with the full judgment below

CWP No. 22060 of 2019 1 IN THE HIGH COURT OF PUNJAB & HARYANA AT CHANDIGARH

CWP No. 22060 of 2019

Date of Decision:21.08.2019 M/s Jagdish Kumar Sehgal

......Petitioners Versus Union of India and others ........Respondents CORAM: HON'BLE MR. JUSTICE TEJINDER SINGH DHINDSA Present:- Mr. Gautam Sehgal, Advocate for the petitioners. ***** TEJINDER SINGH DHINDSA J.(Oral) Instant petition has been filed under Article 226 of the Constitution of India, seeking quashing of the letter/recovery notice dated 12.06.2019 (Annexure P-4) issued at the hands of respondent No.3 i.e.the Garrison Engineer (West), Military Engineer Services (MES) Department, Ferozepur Cantt., Punjab. Counsel for the petitioner has been heard at length and the pleadings on record have been perused. Apparently, the petitioner firm is a Government contractor and had been issued a work order in pursuance to a tender process at Annexure P-1. Petitioner successfully completed the work in question in the month of October 2018 and was even issued a completion certificate. Final bill was also submitted. The impugn

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Punjab and Haryana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.