Isc Projects PVT. LTD. vs. Haryana Rail Infr. Development Corp. LTD.
Facts
The petitioner, ISC Projects Pvt. Ltd., filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of an independent Arbitrator. A contract agreement dated 15.07.2021 was entered into between the petitioner and the respondent, Haryana Rail Infra. Development Corp. Ltd., for construction work. A dispute arose concerning liability for an increase in GST rates from 12% to 18% during the execution of the work. The petitioner invoked the arbitration clause, and the respondent provided a panel of eight retired railway officials. The petitioner objected to these officials, deeming them ineligible. The respondent contended that the contract terms stipulate the petitioner bears any tax increases and that retired railway officials are eligible arbitrators as per Clause 64.3 of the General Conditions of Contract (GCC).
Held
The Court held that the objection of the petitioner to the appointment of retired railway officials cannot be accepted, in view of the dictum of the Supreme Court in Central Organization for Railway Electrification Vs. Eci-Spic-Smo-Mcml (JV). The Supreme Court had interpreted Clause 64.3 of the GCC, specifically the modified clause 64(3)(b), and held that when the agreement specifically provides for the appointment of an Arbitral Tribunal consisting of three arbitrators from a panel of serving or retired railway officers, the appointment must be in terms of the agreement. The High Court was not justified in appointing an independent sole arbitrator ignoring these clauses. Consequently, the Court appointed three individuals from the panel provided by the respondent: Mr. Surender Kaul, Mr. Parmod Kumar, and Mr. Ravinder Kumar, as Arbitrators. They are required to make a declaration under Section 12 of the Act regarding their independence and impartiality. The Arbitrators will decide amongst themselves who will be the Presiding Arbitrator. The proceedings are to be completed within the time limit specified under Section 29-A of the Act, and their fees will be as per the Fourth Schedule of the Act. All questions arising between the parties are left open for determination by the Arbitral Tribunal.
Key Issues
1. Whether retired railway officials are eligible to be appointed as Arbitrators in terms of Clause 64.3 of the General Conditions of Contract (GCC) and the arbitration agreement between the parties? The petitioner argued that the retired railway officials provided by the respondent were not eligible. The respondent, relying on Clause 64.3 of the GCC and the Supreme Court judgment in Central Organization for Railway Electrification Vs. Eci-Spic-Smo-Mcml (JV), argued that retired railway officials are eligible and that the appointment must be in accordance with the agreed terms. 2. Whether the High Court is justified in appointing an independent sole arbitrator, ignoring the specific clauses of the General Conditions of Contract regarding the constitution of the Arbitral Tribunal? This issue stems from the petitioner's initial request for an independent arbitrator and the respondent's insistence on adhering to the GCC's provisions for appointing a tribunal from a panel of railway officials.
Sections Cited
Section 11(6), Section 12, Section 29-A
AI-generated summary — verify with the full judgment below
ARB-353-2023 -1- IN THE HIGH COURT OF PUNJAB & HARYANA AT CHANDIGARH 268 ARB-353-2023 Date of decision:20.05.2024 CORAM: HON'BLE MR. JUSTICE SUVIR SEHGAL Present: Mr. Shrey Goel, Advocate for the petitioner. Mr. Sandeep Vermani, Advocate for the respondent. *** SUVIR SEHGAL J. (ORAL)
By way of present petition filed under Section 11(6) of the Arbitration and Conciliation Act, 1996, (for short “the Act”), read with the Scheme of appointment of Arbitrators by the Chief Justice of Punjab and Haryana High Court, 2003, petitioner has approached this Court for appointment of an independent Arbitrator.
Counsel for the petitioner submits that a contract agreement dated 15.07.2021, Annexure P-6, was entered into between the parties for construction of elevated BG railway line from KM 79/6 to KM 85/7. He submits that during the execution of the construction work, GST rates were increased from 12% to 18% and a dispute arose as to which of the Sheetal 2024.05.31 18:02 I attest to the accuracy and authenticity of this order/judgment High Court, Chandigarh
ARB-353-2023 -2- two par
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Punjab and Haryana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.