M/S Shri Buildcon Builders And Developers vs. Central Mine Planning And Design Institute Limited (Cmpdi)
Facts
The petitioner, M/s Shri Buildcon Builders And Developers, participated in a tender floated by Central Mine Planning And Design Institute Limited (CMPDI) for the construction of a sports complex. The Notice Inviting Tender (NIT) stipulated that the estimated cost was inclusive of GST and required bidders to submit relevant GST documents. The petitioner, quoting Rs. 2,10,98,725.50 including GST, was the L1 bidder. However, M/s SD JV quoted Rs. 1,99,83,837.71 without GST and incorrectly selected the 'GST Unregistered Category'. The e-procurement system mechanically identified SD JV as L1. The petitioner represented this discrepancy to CMPDI. Subsequently, the Tender Committee recommended rejecting SD JV's bid due to incorrect GST category selection and recommended cancelling the entire tender, as there was no provision to award to the L2 bidder. The petitioner protested the cancellation and the subsequent fresh tender.
Held
The Court held that the cancellation of the tender process and the issuance of a fresh tender were justified. The Court reasoned that it was not a case where the petitioner's candidature was rejected, but rather the entire tender process was cancelled due to a system-generated fault leading to an erroneous L1 bidder. The respondents discovered an error in the scrutiny of the documents submitted by the bidder declared L1. In such circumstances, the respondents were fully justified in cancelling the entire tender process and issuing a second call for tenders. The Court cited judgments like Jagdish Mandal v. State of Orissa and Central Coalfields Limited vs. SLL-SML (Joint Venture Consortium) to emphasize judicial restraint in interfering with administrative decisions in tender matters, provided the process is not mala fide, arbitrary, or irrational. The Court noted that the petitioner was at liberty to participate in the fresh NIT if they fulfilled its terms and conditions. No issue regarding the specific GST provisions or rules was expressly left undecided, but the court's decision implicitly upheld the respondents' right to cancel the tender based on their interpretation of the NIT and the discovered error.
Key Issues
1. Whether the cancellation of the tender and the subsequent fresh tender by CMPDI, despite the petitioner being the L1 bidder, is arbitrary and irrational, violating principles of fairness and Article 14 of the Constitution? 2. Whether the Tender Committee's recommendation to cancel the tender, instead of awarding it to the L2 bidder (petitioner), was justified given the identified discrepancies in the L1 bid? Petitioner's arguments: The petitioner argued that they were the rightful L1 bidder as per the NIT's terms, which required bids to be inclusive of GST. They contended that SD JV's bid was invalid due to quoting without GST and selecting the wrong GST category, making their mechanical L1 status incorrect. The petitioner relied on the principle that tender processes must be fair and transparent, citing judgments like Jagdish Mandal v. State of Orissa and Mihan India Ltd. vs. GMR Airports Ltd. They asserted that the cancellation was arbitrary and irrational, as the NIT did not preclude awarding to the L2 bidder in such circumstances. Respondents' arguments: The respondents, relying on Central Coalfields Limited vs. SLL-SML (Joint Venture Consortium), argued that the decision of the employer regarding the essentiality of NIT terms should be respected. They contended that if an error was found in the scrutiny of the L1 bidder's documents, cancelling the tender and issuing a fresh NIT was a justified administrative action, especially if no favoritism was shown. They maintained that the cancellation was not arbitrary, as the petitioner could participate in the new tender.
Sections Cited
Article 14, Article 226
AI-generated summary — verify with the full judgment below
1
2025:CGHC:58343-DB
NAFR HIGH COURT OF CHHATTISGARH AT BILASPUR WPC No. 6095 of 2025 M/s Shri Buildcon Builders And Developers Vinoba Nagar, Bilaspur C.G., Through Its Authorized Partner Raghudipak Sahu S/o Sukhdev Prasad Sahu.
--- Petitioner versus 1 - Central Mine Planning And Design Institute Limited (CMPDI) Through Its Chairman Cum Managing Director Gondwana Place, Kanke Road, Ranchi, Jharkhand – 834008. 2 - Regional Director, CMPDI Regional Institute- V, Seepat Road Bilaspur C.G. 495006. 3 - Head Of Department (Civil), CMPDI Regional Institute- V, Seepat Road Bilaspur C.G. 495006. 4 - JV, Near Chithra Talkies, Rani Road, Korba Chhattisgarh 495677, Through Mr. Karan Pandey Also R/o At Near Chithra Talkies, Rani Road, Korba, C.G. 495677. --- Respondent(s) (Cause Title Taken From Case Information System) For Petitioner(s) : Mr. Aman Saxena, Advocate. For Respondent(s) No. 1 to 3 : Mr. Vaibhav Shukla, Advocate Hon’ble Mr. Ramesh Sinha, Chief Justice Hon’ble Mr. Bibhu Datta Guru, Judge
2 Judgment
on Board
Per
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.